Pacific Gas & Electric Co. v. Federal Energy Regulatory Commission

533 F.3d 820, 382 U.S. App. D.C. 348, 2008 U.S. App. LEXIS 15407
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 22, 2008
Docket17-5217
StatusPublished
Cited by10 cases

This text of 533 F.3d 820 (Pacific Gas & Electric Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas & Electric Co. v. Federal Energy Regulatory Commission, 533 F.3d 820, 382 U.S. App. D.C. 348, 2008 U.S. App. LEXIS 15407 (D.C. Cir. 2008).

Opinion

Opinion for the Court filed by Circuit Judge GARLAND.

GARLAND, Circuit Judge:

Pacific Gas & Electric Company (PG & E) petitions for review of Federal Energy Regulatory Commission (FERC) orders that require the California Independent System Operator, rather than Participating Transmission Owners like PG & E, to conduct interconnection studies when a new electric generator seeks to interconnect with the electric transmission grid. PG & E contends that the orders violate § 206 of the Federal Power Act. But PG & E’s petition, while cloaked in the guise of a challenge to the orders below, is in fact an impermissible collateral attack on a series of orders that FERC issued in 2003 and 2004. We therefore dismiss the petition for review.

I

In its Order No. 888, FERC laid the foundation for the development of competitive wholesale power markets by requiring public utilities to offer nondiscriminatory open access transmission services. Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 680-81 (D.C.Cir.2000), aff 'g Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Services by Public Utilities, Order No. 888, FERC Stats. & Regs. ¶ 31,036, 61 Fed.Reg. 21,540 (1996). The Order required all transmission-owning utilities to provide access to their transmission lines to any entity generating or purchasing electricity in the interstate market on the same terms as the utilities use their own lines. Id. at 681. To effectuate this reform, “FERC adopted a pro forma Open Access Transmission Tariff (OATT), containing minimum terms and conditions for non-discriminatory service, which every transmission-owning public utility must file with the Commission and by which it must abide in providing transmission services to itself and others.” Id. at 727.

As one means of complying with Order No. 888, FERC encouraged public utilities “to participate in Independent System Operators (ISOs).” California Indep. Sys. Operator Corp. v. FERC, 372 F.3d 395, 397 (D.C.Cir.2004). As we have explained:

An ISO conducts the transmission services and ancillary services for all users of such a system, replacing the conduct of such services by the system owners— that is, the integrated electric utilities whose market power FERC was attempting to control by encouraging the creation and operation of the ISOs. In order to accomplish that purpose, FERC deems it crucial that an ISO be independent of the market participants so that decisions of policy, operation, and dis *823 pute resolution be free of the discriminatory impetus inherent in the old system.

Id. (citing Order No. 888, FERC Stats. & Regs. ¶ 31,036, at 31,731). The California electric power industry responded in part by restructuring its market and establishing the California Independent System Operator (“California ISO” or “CAI-SO”). See Pacific Gas & Elec. Co., 81 F.E.R.C. ¶ 61,122, at 61,435-36 (1997).

In the period immediately after the Commission issued Order No. 888, FERC monitored one element of open access transmission service — interconnection agreements between operators of generators and transmission facilities — on a case-by-case basis. National Ass’n of Regulatory Util. Comm’rs v. FERC (NARUC), 475 F.3d 1277, 1279 (D.C.Cir.2007). In its 1997 proceedings regarding the establishment and implementation of the California ISO, for example, the Commission considered, inter alia, whether “Participating Transmission Owners [PTOs] should have the exclusive right to perform Facilities Studies” necessary for interconnection, or whether the California ISO should “be made the coordinator for all expansion projects,” including any necessary studies. Pacific Gas & Elec. Co., 81 F.E.R.C. at 61,487-88. At that time, the Commission concluded that the PTOs should retain responsibility for performing such studies. Id. at 61,489.

The case-by-case approach, however, produced an increasing number of interconnection-related disputes, and, in its Order No.2003, FERC concluded that this approach was “an inadequate and inefficient means to address interconnection issues.” Standardization of Generator Interconnection Agreements and Procedures, Order No.2003, 104 F.E.R.C. ¶ 61,103, at ¶ 10 (2003). “In the interests of achieving transparency and preventing transmission facility owners from favoring affiliated generators over independents in interconnection,” the Commission decided to “require all transmission facilities to adopt a standard agreement for interconnecting with generators larger than 20 megawatts.” NARUC, 475 F.3d at 1279. FERC’s Order No.2003 series required all public utilities that own, control, or operate facilities used for transmitting electricity in interstate commerce to file revised open access transmission tariffs that include pro forma Large Generator Interconnection Procedures and a pro forma Large Generator Interconnection Agreement, unless the Commission approved a utility’s request for a regional variance from the standard terms. Order No.2003, 104 F.E.R.C. at ¶¶ 2, 26.

Among other things, Order No.2003’s proforma procedures address interconnection studies, which are performed to evaluate a proposed interconnection in detail, identify any adverse system impacts, and specify any facility modifications needed to complete the interconnection safely and reliably. Id. at ¶ 36. The procedures provide that the interconnection studies will “be performed by, or at the direction of, the Transmission Provider.” Id. In California, the Transmission Provider is the California ISO, which exercises operational control over the facilities owned by the California PTOs, including PG & E, Southern California Edison Company, and San Diego Gas & Electric Company. See California Indep. Sys. Operator Corp., 112 F.E.R.C. ¶ 61,009, at 61,022 (2005) (“First Order on Review”); PG & E Br. 16, 57. In its orders on rehearing of Order No.2003, FERC clarified various aspects of the pro forma procedures, including the requirement that interconnection studies be performed by the Transmission Provider. See generally Order No.2003-A, 106 F.E.R.C. ¶ 61,220 (2004); Order No.2003B, 109 F.E.R.C. ¶ 61,287 (2004); Order NO.2003-C, 111 F.E.R.C. ¶ 61,401 (2005). This court upheld the Order No.2003 ser *824 ies against an unrelated challenge in NARUC, 475 F.3d 1277.

PG & E submitted its initial Order No.2003 compliance filing in January 2004, and made an amended filing to comply with Order Nos.2003 and 2003-A in January 2005. It submitted its Order No.2003B compliance filing in February 2005. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
533 F.3d 820, 382 U.S. App. D.C. 348, 2008 U.S. App. LEXIS 15407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-electric-co-v-federal-energy-regulatory-commission-cadc-2008.