Public Service Electric and Gas Co. v. Federal Energy Regulatory Commission

783 F.3d 1270, 414 U.S. App. D.C. 407, 2015 U.S. App. LEXIS 5998, 2015 WL 1638541
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 14, 2015
Docket12-1382
StatusPublished
Cited by14 cases

This text of 783 F.3d 1270 (Public Service Electric and Gas Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Electric and Gas Co. v. Federal Energy Regulatory Commission, 783 F.3d 1270, 414 U.S. App. D.C. 407, 2015 U.S. App. LEXIS 5998, 2015 WL 1638541 (D.C. Cir. 2015).

Opinion

Opinion for the Court filed by Senior Circuit Judge SENTELLE.

*1271 SENTELLE, Senior Circuit Judge:

Petitioners are fourteen electrical transmission companies operating as members of the regional transmission organization PJM Interconnection, LLC. As incumbent members of the organization, petitioners contend that PJM’s governing agreements afford them a right of first refusal for proposed transmission facility expansions or upgrades within their zones. The Federal Energy Regulatory Commission (“FERC”) held that no such right of first refusal exists and that PJM may designate third-party developers to construct transmission facilities within incumbent members’ zones. The incumbent transmission owners petition for review, arguing that the Commission lacks jurisdiction over transmission facility development and that the Commission’s interpretation of PJM’s governing agreements is arbitrary, capricious, or otherwise not in accordance with law under the Administrative Procedure Act, 5 U.S.C. § 706(2).

We held this case in abeyance pending the decision in South Carolina Public Service Authority v. FERC, 762 F.3d 41 (D.C.Cir.2014). Now that there is a final decision in that case, we remove this case from abeyance. After reviewing the original and supplemental briefing, and with the benefit of oral argument, we dismiss the petition for review because Article III of the Constitution does not permit us to issue an advisory opinion.

I.

Petitioners are members of PJM Interconnection, LLC, a regional transmission organization “to which transmission providers ... transfer operational control of their facilities for the purpose of efficient coordination.” Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., Wash., 554 U.S. 527, 536, 128 S.Ct. 2733, 171 L.Ed.2d 607 (2008). Regional transmission organizations like PJM combine multiple utility power grids into a single transmission system to “reduce technical inefficiencies caused when different utilities operate different portions of the grid independently.” Id. Formed in 1927, PJM is the oldest and largest regional transmission organization. Atlantic City Elec. Co. v. FERC, 295 F.3d 1, 5 (D.C.Cir.2002). Today, PJM coordinates the movement of wholesale electricity in thirteen mid-Atlantic states and the District of Columbia. Maryland Pub. Serv. Comm’n v. FERC, 632 F.3d 1283, 1284 (D.C.Cir.2011) (per curiam).

“Among its duties, PJM is responsible for preventing interruptions to the delivery of electricity ... by ensuring that its system has sufficient generating capacity.” Id. PJM fulfills this duty in part by upgrading and enhancing its system in accordance with procedures set forth in its governing agreements, which include: the Regional Transmission Expansion Plan in PJM’s Operating Agreement, the Consolidated Transmission Owners Agreement (“Owners Agreement”), and the PJM Open Access Transmission Tariff (“Tariff’).

Petitioners seek review of four FERC orders from two proceedings. In both proceedings, non-incumbent developers argued that no right of first refusal existed within PJM’s governing agreements for incumbent transmission owners.

A.

The first proceeding arose on a petition to the Commission by Primary Power, LLC, a non-incumbent developer hoping to build the Grid Plus project, a proposed expansion project comprised of four installations within the PJM system. Primary Power sought FERC’s assurance that if it were selected for the project, it would be *1272 eligible to employ cost-based rate recovery in the operation of the project. Incumbent members of PJM, petitioners before us, opposed the petition, arguing that Section 1.5.6 of the Regional Transmission Expansion Plan created a right of first refusal which would be violated by the grant of rights to the newcomer. Section 1.5.6(f) states, in pertinent part:

For each enhancement or expansion that is included in the recommended. plan, the plan shall consider [a number of selection factors] ... and designate one or more Transmission Owners or other entities to construct, own and, unless otherwise provided, finance the recommended transmission enhancement or expansion. To the extent that one or more Transmission Owners are designated to construct, own and/or finance a recommended transmission enhancement or expansion, the recommended plan shall designate the Transmission Owner that owns transmission facilities located in the Zone where the particular enhancement or expansion is to be located.

FERC rejected the incumbent transmission owners’ arguments in Primary Power, LLC, 131 FERC ¶ 61,015 (2010) (order on petition for declaratory order). Interpreting PJM’s Operating Agreement, FERC explained that Sections 1.5.7(c)(iii) and 1.5.6(f) of the Agreement allowed non-incumbent developers to compete for and construct projects under the expansion protocol. Id. PP 62-65. FERC held that “the PJM Tariff permits, but does not require, PJM to designate Primary Power, an entity other than an incumbent transmission owner, as the entity to build Grid Plus.” Id. P 62. FERC concluded that Section 1.5.6(f) did not create a right of first refusal for incumbent transmission owners because the “shall designate” clause requiring PJM to assign projects to transmission owners who own facilities in the zone where the project is located only “applies by its own terms ‘to the extent that one or more Transmission Owners are designated.’ ” Id. P 65 (quoting Operating Agreement § 1.5.6(f)). The “shall designate” . clause, FERC further explained, does not apply when PJM designates non-incumbent “other entities” to construct the project. Id. P 64.

Addressing the recovery of development costs, FERC acknowledged that merchant transmission facilities are not eligible for cost-based rates under the PJM Tariff. Id. P 68. But if PJM includes the Grid Plus project in its expansion plan, FERC explained that Primary Power “would be eligible to seek cost-based rate recovery as would any other transmission owner.” Id. P 70. In other words, FERC noted that the “PJM’s Tariff contains no prohibition on a non-incumbent party becoming a transmission owner to receive cost-based rates.” Id.

Incumbent transmission owners timely sought rehearing. Among other things, they argued that FERC ignored their exclusive right to build and operate all non-merchant projects in their own zones, and FERC misinterpreted the “other entity” language from Section 1.5.6(f) of the PJM Operating Agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Municipal Power, Inc. v. FERC
86 F.4th 922 (D.C. Circuit, 2023)
American Hospital Association
District of Columbia, 2023
Gerald Farrell v. Antony Blinken
4 F.4th 124 (D.C. Circuit, 2021)
Khalid Qassim v. Donald Trump
927 F.3d 522 (D.C. Circuit, 2019)
Clean Water Action v. Pruitt
District of Columbia, 2018
Clean Water Action v. Pruitt
315 F. Supp. 3d 72 (D.C. Circuit, 2018)
Albra v. Bd. of Trs. of Miami Dade Coll.
296 F. Supp. 3d 181 (D.C. Circuit, 2018)
Cause of Action Inst. v. U.S. Dep't of Justice
282 F. Supp. 3d 66 (D.C. Circuit, 2017)
Hand v. Perez
672 F. App'x 24 (D.C. Circuit, 2016)
Hand v. Perez
District of Columbia, 2015

Cite This Page — Counsel Stack

Bluebook (online)
783 F.3d 1270, 414 U.S. App. D.C. 407, 2015 U.S. App. LEXIS 5998, 2015 WL 1638541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-electric-and-gas-co-v-federal-energy-regulatory-commission-cadc-2015.