Oklahoma Gas and Electric Company v. FERC

11 F.4th 821
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 27, 2021
Docket20-1062
StatusPublished
Cited by8 cases

This text of 11 F.4th 821 (Oklahoma Gas and Electric Company v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oklahoma Gas and Electric Company v. FERC, 11 F.4th 821 (D.C. Cir. 2021).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 14, 2021 Decided August 27, 2021

No. 20-1062

OKLAHOMA GAS AND ELECTRIC COMPANY, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

CPV KEENAN II RENEWABLE ENERGY COMPANY, LLC, ET AL., INTERVENORS

Consolidated with 20-1101

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

John Longstreth and Matthew J. Binette argued the causes for petitioners Oklahoma Gas and Electric Company and Southwest Power Pool, Inc. With them on the joint briefs were Donald A. Kaplan and Victoria M. Lauterbach.

Bruce A. Grabow, Jennifer Brough, Stuart A. Caplan, Matthew A. Fitzgerald, Noel Symons, Daniel E. Frank, Allison 2

E. Speaker, and Molly Suda were on the joint briefs for intervenors CPV Keenan II Renewable Energy Company, LLC, et al. in support of petitioners. William M. Keyser, entered an appearance.

Beth G. Pacella, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were David L. Morenoff, Acting General Counsel, and Robert H. Solomon, Solicitor.

Joseph W. Lowell argued the cause for intervenors Xcel Energy Services Inc., et al. in support of respondent. With him on the joint brief were Craig W. Silverstein, Stephen C. Pearson, Cynthia S. Bogorad, Amanda C. Drennen, Stacey L. Burbure, Phyllis G. Kimmel, Stephen M. Spina, and Timothy T. Mastrogiacomo.

Before: TATEL, RAO, and WALKER, Circuit Judges.

Opinion for the Court filed by Circuit Judge RAO.

RAO, Circuit Judge: This case concerns the authority of the Federal Energy Regulatory Commission (“FERC” or “Commission”) to order a retroactive waiver of a billing requirement contained in a filed tariff. Several utilities that are managed by the Southwest Power Pool (“SPP”), a regional transmission operator, paid for upgrades to the transmission grid. The operative tariff required other utilities who benefitted from these upgrades to share the costs of the expanded network. The tariff, however, also required SPP to invoice the charges monthly and to make any adjustments within one year. The reimbursement calculation proved complicated, and it took SPP eight years to implement it, during which time SPP did not invoice for the upgrade charges. 3

The Commission initially granted SPP a waiver of the tariff’s one-year time bar, but later determined it lacked the authority to waive this provision retroactively. FERC’s revised determination meant the utilities that had made substantial outlays for upgrades were denied reimbursement for the eight years that had elapsed. SPP and Oklahoma Gas and Electric, one of the companies that sponsored upgrades and has been denied reimbursement, filed these consolidated petitions for review.

We deny the petitions. Once a tariff is filed, the Commission has no statutory authority to provide equitable exceptions or retroactive modifications to the tariff. SPP may impose only those charges contained in the filed rate. Because the one-year time bar for billing is part of the filed rate, FERC could not retroactively waive it, even to remedy the arguable windfall for users of the upgraded transmission networks. FERC therefore properly denied the waiver, and it was not arbitrary or capricious to order SPP to refund the retroactive charges it had collected under the invalidated waiver.

I.

SPP is a regional transmission organization servicing about 60,000 miles of transmission lines stretching from Arkansas to Wyoming and from Texas to North Dakota. SPP manages the transmission of electricity by collecting and distributing various charges and revenues among its stakeholders, which include both private and public utilities. SPP and its stakeholders operate under a tariff approved by FERC.

When a utility seeks to expand its generation capabilities, it may need transmission service beyond what the transmission grid currently can accommodate. To facilitate and encourage 4

investment in upgrades to the grid, SPP proposed a reimbursement mechanism to its tariff, which FERC accepted. See Sw. Power Pool, Inc., 110 FERC ¶ 61,028 (2005). Attachment Z provided that a utility would initially fund upgrades needed to accommodate its expansion of service— that utility is the “upgrade sponsor.” Other utilities that subsequently use the upgraded transmission facilities—the “upgrade users”—would pay a share of the upgrade costs. This reimbursement would continue until the upgrade sponsor was fully reimbursed. SPP later proposed, and FERC accepted, Attachment Z2, which clarified the standard for imposing upgrade charges. See Sw. Power Pool, Inc., 123 FERC ¶ 61,208 (2008). Under Attachment Z2, an upgrade sponsor would receive credits from any upgrade users whose service could not be provided “but for” the upgrade. See Resp’t Br. Add. 10–16 (Attachment Z2).

Later that year, Oklahoma Gas and Electric Company (“Oklahoma Gas”), an SPP stakeholder, wanted to develop wind generation in western Oklahoma. Although this region has strong winds, it lacked sufficient connection to the transmission grid to profitably move the energy to market. Oklahoma Gas decided to fund upgrades to the grid’s transmission facilities in reliance on Attachment Z2’s promise of credits from later users of the upgrades.

Meanwhile, the implementation of the upgrade crediting process proved to be complex. SPP obtained a vendor to develop special software necessary to calculate the upgrade charges, but it encountered delays and problems over the next several years. In the meantime, sponsors continued to fund network upgrades. SPP utilized a task force composed of its stakeholders to address the calculation of the upgrade charges. This stakeholder process kept the relevant parties apprised of SPP’s efforts to implement the upgrade charges. SPP also 5

periodically provided “study reports” to the utilities, which contained notations that upgrade charges “may be required for the following Network Upgrades in accordance with Attachment Z2.” J.A. 89. In 2015, SPP found a new software vendor and a year later, finally was able to calculate the upgrade charges for 2008 to 2016, which the parties refer to as the “historical period.” At this point, the utilities using the upgrades had not been billed for their share of the upgrade costs.

By 2016, Oklahoma Gas had completed the upgrades to transmit the energy it generated from wind. Several other SPP stakeholders, including Xcel Energy Services, also used these transmission upgrades. Although Oklahoma Gas was entitled to compensation, it had not received any credits for its upgrade costs.

Out of what it said was an abundance of caution, SPP petitioned FERC for a waiver of a tariff provision governing the timing of invoices. Section I.7.1 of SPP’s tariff provides that, “[w]ithin a reasonable time after the first day of each month, [SPP] shall submit an invoice to the Transmission Customer for the charges for all services furnished under the Tariff during the preceding month.” Pet’rs Br. Add. 15 (hereinafter Tariff § I.7.1). Although SPP may later adjust the bills, adjustments must be made “within one year after rendition of the bill reflecting the actual data for such service.” Tariff § I.7.1. SPP sought a waiver of Section I.7.1 to permit it to bill upgrade users for the upgrade charges incurred during the historical period, i.e., more than a year prior. Xcel, along with several other upgrade users, objected to the waiver request on the ground that Section I.7.1 is part of the filed rate, so the Commission cannot waive it. 6

The Commission initially granted SPP a waiver of Section I.7.1, applying the waiver both retroactively and prospectively. See Sw. Power Pool, Inc., 156 FERC ¶ 61,020, slip decision (2016).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petro Star Inc. v. FERC
D.C. Circuit, 2026
Michigan Electric Transmission Company, LLC v. FERC
141 F.4th 1296 (D.C. Circuit, 2025)
EDF Renewables, Inc. v. FERC
Eighth Circuit, 2024
Shell Energy North America (US), L.P. v. FERC
107 F.4th 981 (D.C. Circuit, 2024)
PJM Power Providers Group v. FERC
96 F.4th 390 (Third Circuit, 2024)
East Texas Electric Cooperative, Inc. v. FERC
90 F.4th 579 (D.C. Circuit, 2024)
Xcel Energy Services Inc. v. FERC
77 F.4th 1057 (D.C. Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
11 F.4th 821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oklahoma-gas-and-electric-company-v-ferc-cadc-2021.