Xcel Energy Services Inc. v. FERC

77 F.4th 1057
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 4, 2023
Docket20-1429
StatusPublished
Cited by1 cases

This text of 77 F.4th 1057 (Xcel Energy Services Inc. v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Xcel Energy Services Inc. v. FERC, 77 F.4th 1057 (D.C. Cir. 2023).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued May 5, 2023 Decided August 4, 2023

No. 20-1429

XCEL ENERGY SERVICES INC., ON BEHALF OF ITS PUBLIC UTILITY AFFILIATE, SOUTHWESTERN PUBLIC SERVICE COMPANY, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

GOLDEN SPREAD ELECTRIC COOPERATIVE, INC., ET AL., INTERVENORS

Consolidated with 22-1049, 22-1064

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Joseph W. Lowell and Phyllis G. Kimmel argued the causes for petitioners. With them on the joint briefs was Timothy T. Mastrogiacomo. Pamela Wu and Stephen M. Spina entered appearances. 2 Beth G. Pacella, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor.

Matthew J. Binette argued the cause for intervenors for respondent. With him on the brief were John Longstreth, Donald A. Kaplan, Victoria M. Lauterbach, Gunnar Birgisson, Daniel E. Frank, Allison E. Speaker, and Richard M. Lorenzo.

Before: SRINIVASAN, Chief Judge, RAO and CHILDS, Circuit Judges.

Opinion filed for the Court by Circuit Judge CHILDS.

CHILDS, Circuit Judge: In the energy industry, utility companies can ask their Regional Operator to fulfill a transmission service request, a physical transfer of power to its electrical grids. That increased power may require use of an existing physical structure that amplifies the grid’s capability, known as a Creditable Upgrade.

It is the Regional Operator’s responsibility to assess charges for Creditable Upgrade usage. The Tariff standard for doing so is whether use of an upgrade is not needed “but for” the request. A methodology then actualizes that standard to assign the associated costs directly to the utility company for reimbursement by their customers.

In this consolidated appeal of the Federal Energy Regulatory Commission’s (FERC) orders, two utility companies argue that Attachment Z2 plainly requires utilizing the N-1 Contingency Analysis (N-1) methodology. And they assert that FERC erred in concluding that the Tariff was ambiguous, relying on extrinsic evidence to interpret that the 3 Reservation Stack Analysis (RSA) was the appropriate methodology. Second, they claim that the Regional Operator violated the filed rate doctrine because the filed rate was unclear about how much they would be charged. Finally, Petitioners contend that their charges offend Attachment Z1 because the Regional Operator neither identified the upgrade facilities that would accommodate their requests nor provided them with an estimate of the costs of such upgrades.

We deny in part and dismiss in part the petitions for review. FERC correctly concluded that Section II.B of Attachment Z2 does not plainly require the N-1 methodology because the Tariff is ambiguous. Further, FERC’s reliance on extrinsic evidence to ascertain that the Tariff allows the RSA methodology was not arbitrary and capricious. We lack jurisdiction to consider Petitioners’ filed rate doctrine argument because they failed to exhaust it at the rehearing stage below. And the challenged sections of Attachment Z1 do not concern the Attachment Z2 charges for which Petitioners complain.

I.

A.

Kansas Electric Power Cooperative, Inc. (KEPCo) and Xcel Energy Services, Inc. (Xcel) (collectively, Petitioners) are utility companies that distribute electricity to their customers. Intervenor Southwest Power Pool, Inc. (Regional Operator) provides transmission services for that electricity. Its electrical transmission lines stretch approximately 60,000 miles, from Arkansas to Wyoming and from Texas to North Dakota. The terms and conditions between Petitioners’ and the Regional Operator’s contracted services are governed by individual service agreements. Incorporated in those service agreements 4 is a Tariff, which sets the rates of service. Attachment Z is the Tariff at issue in this consolidated appeal.

“Attachment Z provide[s] that a utility [] initially fund[s] upgrades needed to accommodate its expansion of service . . . . Other utilities that subsequently use the upgraded transmission facilities . . . pay a share of the upgrade costs.” Okla. Gas & Elec. Co. v. FERC, 11 F.4th 821, 825 (D.C. Cir. 2021). Attachment Z “does not guarantee full reimbursement; rather, it provides financial compensation to the funding customer when use is made of the Network Upgrades . . . .” Sw. Power Pool, 122 FERC ¶ 61,060, 61,370 (2008).

In 2008, FERC approved splitting Attachment Z into the two attachments relevant to this appeal. Attachment Z2 provides the standard which figures Petitioners’ costs for use of existing Creditable Upgrades.

The same year that FERC approved Attachment Z2’s creation, the Regional Operator proposed a revision to provide revenue credits from transmission service requests “that could not be provided ‘but for’” the upgrade. Request For Rehearing of Xcel Energy Services Inc. [hereinafter Xcel Reh’g Req.] at 22, J.A. 420 (quoting Regional Operator Transmittal Letter at 7–8); see also Request for Rehearing of Kansas Electric Power Cooperative, Inc. [hereinafter KEPCo Reh’g Req.] at 19 nn.63– 64, J.A. 161. The Regional Operator’s goal was to reimburse utilities that supply entities by using network upgrades for usage not only by customers who received service in the forward direction of the initial overload but also from those who received energy in the backward direction. Sw. Power Pool, 123 FERC ¶ 61,208, 62,329 (2008). The “but for” language augmented, but did not disturb, the Tariff’s dual standard that utilities be charged for any request’s “subsequent incremental use” of the Creditable Upgrade itself. 5

FERC accepted the Regional Operator’s filing requesting the additional “but for” language and the Regional Operator’s reasoning that the revision would complement a continued “subsequent incremental use” standard to assess upgrade charges. Id. Petitioners did not object to FERC’s order at the time. And neither the filing requesting the Attachment Z2 revision nor FERC’s order approving it mentioned any methodology because both were still being developed. Indeed, the software needed to calculate the credits was not developed until 2015. See Okla. Gas, 11 F.4th at 825.

The relevant version of Attachment Z2, Section II.B, provides:

Revenue for credits will be provided from (i) new Long- Term Network Integration Transmission Service, and (ii) new transmission service taken under the non-rate terms and conditions of this Tariff by Transmission Owners subject to Section 39.1 of this Tariff, that could not be provided but for one or more Creditable Upgrades to accommodate designation of new Network Loads or Transmission Owner’s(s’) loads, new Designated Resources or increases in the designation of existing Designated Resources above previously designated levels.

Attachment Z2, § II.B (2013), Pet’r’s Br. at A28 (emphasis added).1 In the immediate next sentence, the Tariff introduces the phrase “subsequent incremental use.” Id. It states:

Revenue credits shall be determined based upon the subsequent incremental use of each affected Creditable

1 Attachment Z2 was revised in 2008, 2010, and 2013. The 2010 and 2013 revisions did not augment Section II.B’s “but for” and 6 Upgrade for such new or increased Network Load or Transmission Owner load or Network Resource.

Id. (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jazz Pharmaceuticals, Inc. v. Becerra
District of Columbia, 2024

Cite This Page — Counsel Stack

Bluebook (online)
77 F.4th 1057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/xcel-energy-services-inc-v-ferc-cadc-2023.