Energy Harbor, LLC v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 11, 2025
Docket24-1092
StatusPublished

This text of Energy Harbor, LLC v. FERC (Energy Harbor, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Energy Harbor, LLC v. FERC, (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued January 31, 2025 Decided July 11, 2025

No. 24-1092

ENERGY HARBOR, LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

OLD DOMINION ELECTRIC COOPERATIVE AND PJM INTERCONNECTION, L.L.C., INTERVENORS

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Pamela T. Wu argued the cause for petitioner. With her on the briefs was J. Daniel Skees.

Robert M. Kennedy, Senior Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. Angela X. Gao, Trial Attorney, Federal Energy Regulatory Commission, entered an appearance. 2

Andrew T. Swers argued the cause for intervenor in support of respondent. With him on the brief was Ryan J. Collins. Wendy B. Warren entered an appearance.

Before: PILLARD and GARCIA, Circuit Judges, and RANDOLPH, Senior Circuit Judge.

Opinion for the court filed by Senior Circuit Judge RANDOLPH.

RANDOLPH, Senior Circuit Judge: PJM Interconnection, L.L.C. operates the largest competitive wholesale energy market in the country. It assessed $12 million in penalties on Energy Harbor, LLC, the owner and operator of the W.H. Sammis power plant, for failing to comply with PJM’s Tariff during a major winter storm in December 2022. Energy Harbor filed a complaint with the Federal Energy Regulatory Commission contesting the penalties. FERC denied the complaint. Energy Harbor now petitions for judicial review of that decision.

I.

A.

PJM operates an interstate transmission grid covering all or parts of thirteen mid-Atlantic and Midwestern states and the District of Columbia. PJM’s grid connects individual customers to electricity generation companies via local utilities. PJM does not itself produce electricity. Instead, its role is as a middleman. End-users purchase electricity from their local utility, that utility purchases electricity from PJM, and PJM purchases the electricity from an electricity generation company. To complete the transaction, the electricity is physically transmitted from electricity generation companies, across high-voltage power lines operated by PJM, to the user’s local utility. 4

Because the demand for electricity is variable, the local utilities and PJM require assurances that there will be sufficient supply when demand is high. PJM solves this problem by entering into futures contracts with generation companies. Each company commits to produce up to a set amount of electricity during a given time period, at a specified price. That price is set at yearly auctions held by PJM. The rates, rules and operating procedures for this system are FERC-approved and outlined in PJM’s “Open Access Transmission Tariff.”

B.

In 2014, PJM proposed revisions to its Tariff to ensure that generators would deliver electricity when needed.1 FERC approved the changes in 2015, see PJM Interconnection, L.L.C., 151 FERC ¶ 61,208, at P 2 (2015), and our court upheld FERC’s decision in Advanced Energy Management Alliance v. FERC, 860 F.3d 656, 674 (D.C. Cir. 2017). In essence, the proposal implemented a pay-for-performance model, charging generators stiff penalties if they failed to perform during any emergency period PJM declared. These penalties were then to be used to fund bonus payments to generators that over-performed in relation to their capacity commitments. See PJM Interconnection, 151 FERC ¶ 61,208, at P 2.

To illustrate the concept, take the following example. Imagine a generator with a 100-megawatt capacity commitment.

1 Technically, PJM revised its “Market Rules,” which include “the rules, standards, procedures, and practices of the PJM Markets set forth in the PJM Tariff, the PJM Operating Agreement, the PJM Reliability Assurance Agreement, the PJM Consolidated Transmission Owners Agreement, the PJM Manuals, the PJM Regional Practices Document, the PJM-Midwest Independent Transmission System Operator Joint Operating Agreement,” and other documents. J.A. 261. 4

During an emergency period, PJM calls on that plant to provide 90 megawatts—a request clearly within the 100-megawatt commitment. If the generator cannot deliver the full request, it owes a penalty proportional to the shortfall. Thus, if the generator is only able to produce 80 megawatts, it owes PJM a penalty on 10 megawatts. And if it cannot deliver at all, it owes a penalty for the full 90 megawatts. See Advanced Energy, 860 F.3d at 665 (describing this hypothetical).

The actual penalty scheme is more complex—and that complexity led to this litigation.

The Tariff defines the owner of an electricity generation company as a “Capacity Market Seller.” See J.A. 221. Each Capacity Market Seller owns a facility that produces a set number of megawatts and pledges that capacity through PJM’s auctions. A Capacity Market Seller’s pledged capacity is termed the “Capacity Resource.” See J.A. 302. But since generation companies sometimes fail to live up to their commitments, the Tariff imposes a penalty for nonperformance. PJM evaluates a Capacity Market Seller’s nonperformance by looking both at its “Expected Performance,” or promised output, and its “Actual Performance,” or metered output of energy actually delivered to PJM. See J.A. 291-93.

The Tariff creates a multi-step process for determining Expected Performance. The initial step is to determine what a Capacity Resource can produce in ideal conditions, or the “[I]nstalled [C]apacity.” See Keyspan-Ravenswood, LLC v. FERC, 474 F.3d 804, 807 (D.C. Cir. 2007). But recognizing that electrical generation is often interrupted by technical problems, the Tariff decreases Expected Performance below the level of a facility’s Installed Capacity in two ways.

First, PJM accounts for a Capacity Resource’s past 5

performance when calculating Expected Performance. The “Forced Outage Rate” represents the historical rate at which a Capacity Resource performs, relative to its Installed Capacity. Id. Multiplying the inverse of the Forced Outage Rate—one minus the Forced Outage Rate—by the Installed Capacity produces an estimate of a generator’s likely capacity based on its past results. This is termed “Unforced Capacity.” J.A. 324. Resource Committed Capacity is the total megawatts of Unforced Capacity of the Capacity Resource committed by a Capacity Market Seller. J.A. 292.

Next, the Tariff adds an additional buffer by looking to the average performance of all generators within the PJM grid. This is the “Balancing Ratio,” which is calculated by dividing PJM- wide Actual Performance by PJM-wide Unforced Capacity. Id. If, for example, all PJM members committed 1,000,000 megawatts but only produced 800,000 megawatts, the Balancing Ratio for that period would be 0.8.

Multiplying the Balancing Ratio by Resource Committed Capacity produces Expected Performance. Said differently, Expected Performance is the total megawatts that a Capacity Resource can produce in ideal conditions (Installed Capacity), adjusted for (i) that Capacity Resource’s historical performance (Forced Outage Rate), and (ii) the performance of all of PJM’s members (Balancing Ratio). Or more simply:

Unforced Capacity = Installed Capacity * (1 - Forced Outage Rate)

Resource Committed Capacity = total megawatts of committed Unforced Capacity

Expected Performance = Resource Committed Capacity * Balancing Ratio 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Energy Harbor, LLC v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/energy-harbor-llc-v-ferc-cadc-2025.