City of Boston Delegation v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 27, 2018
Docket16-1081
StatusPublished

This text of City of Boston Delegation v. FERC (City of Boston Delegation v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Boston Delegation v. FERC, (D.C. Cir. 2018).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued October 19, 2017 Decided July 27, 2018

No. 16-1081

CITY OF BOSTON DELEGATION, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

ALGONQUIN GAS TRANSMISSION, LLC, ET AL., INTERVENORS

Consolidated with 16-1098, 16-1103

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Thomas S. Fitzpatrick argued the cause for petitioner City of Boston Delegation. With him on the briefs was Joshua S. Grossman.

Carolyn Elefant argued the cause for petitioners Riverkeeper, Inc., et al. With her on the briefs were Jeffrey M. Bernstein, Rebecca F. Zachas, and Alexander English. 2 Ross R. Fulton, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the briefs were James P. Danly, General Counsel, Robert H. Solomon, Solicitor, and Holly E. Cafer, Senior Attorney.

Jeremy C. Marwell argued the cause for intervenor Algonquin Gas Transmission, LLC, et al. With him on the briefs were Anita R. Wilson, Michael B. Wigmore, Andrew N. Beach, and Steven E. Hellman.

Before: HENDERSON and SRINIVASAN, Circuit Judges, and WILLIAMS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge SRINIVASAN.

SRINIVASAN, Circuit Judge: In March 2015, the Federal Energy Regulatory Commission approved an application from Algonquin Gas Transmission, LLC, to undertake an upgrade to its natural gas pipeline system. The $972 million project would enable Algonquin to meet some of the increasing demand for natural gas in New England and reduce pricing volatility in the region.

A number of parties now seek to challenge the Commission’s approval of Algonquin’s project. They allege, among other things, that the Commission erred in assessing the project’s environmental impacts, unreasonably relied on expert opinions concerning the project’s safety, and failed to recognize the bias of a third-party contractor. At the outset, we dismiss one party’s petition for review for want of standing. We deny the remaining petitions for review on the merits. 3 I.

A.

The Natural Gas Act grants the Federal Energy Regulatory Commission authority to regulate the interstate transportation of natural gas. 15 U.S.C. §§ 717b, 717c. To construct or operate an interstate natural gas pipeline, a company must obtain “a certificate of public convenience and necessity,” 15 U.S.C. § 717f(c), known as a Section 7 certificate. The Commission will grant a Section 7 certificate “only if the public benefits from the project outweigh any adverse effects.” Certification of New Interstate Natural Gas Pipeline Facilities, 88 FERC ¶ 61,227, at 61,750 (Sept. 15, 1999), clarified, 90 FERC ¶ 61,128, at 61,396-98 (Feb. 9, 2000), further clarified, 92 FERC ¶ 61,094, at 61,373-75 (July 28, 2000).

As part of the process of issuing a Section 7 certificate, the Commission must satisfy the requirements of the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. NEPA establishes an environmental review process under which federal agencies “identify the reasonable alternatives to [a] contemplated action and look hard at the environmental effects of their decisions.” Minisink Residents for Envtl. Pres. & Safety v. FERC, 762 F.3d 97, 102 (D.C. Cir. 2014) (alterations and internal quotation marks omitted). In the case of “major Federal actions significantly affecting the quality of the human environment,” NEPA calls for the relevant federal agency to prepare “a detailed” environmental impact statement. 42 U.S.C. § 4332(2)(C).

B.

Algonquin Gas Transmission, LLC, operates a natural gas pipeline system that starts in New Jersey, runs north through 4 New York, Connecticut, and Rhode Island, and ends in Massachusetts. In light of increasing demand for natural gas in the New England area, Algonquin planned several discrete projects to increase the capacity of its pipeline system. One of those projects, the Algonquin Incremental Market Project (AIM Project), is the subject of the petitions for review we consider in this case.

In February 2014, Algonquin applied to the Commission for authorization to construct the AIM Project. The proposal sought to replace 29.2 miles of existing pipeline with larger diameter pipe, construct 8.2 miles of new pipeline, build three new meter stations, and modify various other compressor and meter stations.

Of particular relevance, the AIM project included a proposal to construct roughly five miles of new pipeline known as the West Roxbury Lateral, which would run adjacent to an active quarry outside of Boston. The project also sought to install larger-diameter replacement pipeline next to the Indian Point Energy Center, a nuclear facility in Westchester County, New York. Overall, the AIM Project would give Algonquin an additional 342,000 dekatherms per day of natural gas transport capacity from Ramapo, New York, to various cities in Connecticut, Rhode Island, and Massachusetts.

In addition to the AIM Project, Algonquin is pursuing two other upgrades to its northeast pipeline system. Those ventures are known as the Atlantic Bridge Project and the Access Northeast Project. In the Atlantic Bridge Project, Algonquin seeks to create 132,705 dekatherms per day of capacity from New Jersey and New York to various points on its system, by replacing several miles of pipeline with larger-diameter pipes and constructing or modifying a number of compressor and meter stations. Algonquin applied for a Section 7 certificate 5 for Atlantic Bridge in October 2015, and the Commission granted the certificate in January 2017. Order Issuing Certificate, Algonquin Gas Transmission, LLC, 158 FERC ¶ 61,061 (Jan. 25, 2017) (Atlantic Bridge Certificate Order). In the Access Northeast Project, Algonquin planned to install pipeline and modify facilities in order to provide natural gas to electric power plants in New England. Pre-filing review for the Access Northeast Project began in November 2015, but Algonquin withdrew the pre-filing application in June 2017.

On January 23, 2015, the Commission issued its final environmental impact statement under NEPA for the AIM Project. On March 3, 2015, after receiving comments on the environmental impact statement, the Commission issued an order granting Algonquin a Section 7 certificate to construct and operate the AIM Project. Order Issuing Certificate, Algonquin Gas Transmission, LLC, 150 FERC ¶ 61,163 (Mar. 3, 2015).

Several parties in the agency proceedings, including the petitioners in this case, requested rehearing before the Commission. The City of Boston Delegation alleged that the Commission failed to give adequate consideration to the safety risks of running the West Roxbury Lateral adjacent to an active quarry. The Town of Dedham, Massachusetts, and Riverkeeper, Inc., argued in part that the Commission impermissibly segmented its NEPA review by failing to consider Algonquin’s three planned projects together in a single environmental impact statement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
DaimlerChrysler Corp. v. Cuno
547 U.S. 332 (Supreme Court, 2006)
Sierra Club v. Environmental Protection Agency
292 F.3d 895 (D.C. Circuit, 2002)
Commty Agnst Runway v. FAA
355 F.3d 678 (D.C. Circuit, 2004)
Parker v. District of Columbia
478 F.3d 370 (D.C. Circuit, 2007)
Town of Sudbury v. Department of Public Utilities
218 N.E.2d 415 (Massachusetts Supreme Judicial Court, 1966)
Town of Wilmington v. Department of Public Utilities
165 N.E.2d 99 (Massachusetts Supreme Judicial Court, 1960)
New York v. U.S. Nuclear Regulatory Commission
824 F.3d 1012 (D.C. Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
City of Boston Delegation v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-boston-delegation-v-ferc-cadc-2018.