Aera Energy LLC v. Federal Energy Regulatory Commission

789 F.3d 184, 416 U.S. App. D.C. 39, 2015 U.S. App. LEXIS 10075
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 16, 2015
Docket13-1138, 13-1303
StatusPublished
Cited by2 cases

This text of 789 F.3d 184 (Aera Energy LLC v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aera Energy LLC v. Federal Energy Regulatory Commission, 789 F.3d 184, 416 U.S. App. D.C. 39, 2015 U.S. App. LEXIS 10075 (D.C. Cir. 2015).

Opinions

Opinion for the Court filed by Senior Circuit Judge SENTELLE.

Concurring statement filed by Senior Circuit Judge SILBERMAN.

SENTELLE, Senior Circuit Judge:

Petitioner Kern River Gas Transmission Company owns and operates an interstate pipeline that transports natural gas from its production area in Wyoming to markets in Utah, Nevada, and California. Petitioners Aera Energy LLC and several other natural gas and transportation companies (collectively “Shippers”) ship natural gas using Kern River’s pipeline. In their consolidated petitions, Kern River and the Shippers seek review of different aspects of seven orders issued by the Federal Energy Regulatory Commission during rate proceedings. We conclude that the Commission complied with the Natural Gas Act and our precedents. The Commission responded meaningfully to petitioners’ objections and articulated a rational explanation for its decisions under the particularly deferential standard of review we apply to ratemaking decisions. We therefore deny the petitions for review.

I.

A. Factual Background

To construct a pipeline, a natural gas company must first obtain a certificate from the Commission. See 15 U.S.C. § 717f(c). When Kern River applied for its certificate, then-existing regulations allowed it to obtain an optional certificate and assume the economic risks of the project. FERC approved Kern River’s optional certificate and permitted Kern River to charge separate rates during three periods: (1) Period One, the 15-year term of the original contracts; (2) Period Two, the period from the expiration of those con[187]*187tacts to the end of the pipeline’s 25-year depreciation life; and (3) Period Three, the period thereafter. Kern River Gas Transmission Co., 50 FERC ¶ 61,069, at 61,150-51 (1990). The Commission also allowed “Kern River to utilize a levelized cost of service” during Period One. Id. at 61,150. Using levelized rates, Kern River planned to “recover all of its debt service during the first 15 years, and to recover its return of equity primarily during the second period.” Id.

Unlike a traditional rate structure, in which a pipeline charges higher rates during the early years of its life, Kern River’s levelized rate plan provided lower rates during the early years of operation. Lower initial rates help new .pipelines market their capacity and compete with other established pipelines. There is, however, a trade-off. By charging lower rates during the first half of the levelization period, Kern River defers the recovery of costs that it would otherwise recover during the early years of operation if it had used a traditional rate structure. Kern River therefore entered into long-term contracts with the Shippers, which extend beyond the initial period of lower rates, to ensure that it will adequately recover its costs.

With respect to calculating Kern River’s return on capital investment, FERC recognized that Kern River would not maintain its original ratio of 70 percent debt and 30 percent equity over the course of the pipeline’s life. Kern River Gas Transmission Co., 60 FERC ¶ 61,123, at 61,347 (1992). In accordance with its optional certifícate, Kern River would instead retire the debt principal during the first 15 years of the project (i.e., during Period One) and operate with a 100 percent equity capital structure thereafter (i.e., Periods Two and Three). Id. FERC noted “that in the latter years of the projects, the rate of return on equity ... may not be appropriate as the overall rate of return.” Id. Thus, FERC reserved its right to reexamine the issue in future general rate proceedings. Id.

In 1992, FERC issued the certificate order, and Kern River started operating its pipeline. Eight years later, Kern River proposed to lower its shipping rates by refinancing its debt. All existing customers, referred to as “original shippers,” extended the terms of their contracts in exchange for lower rates. Some original shippers agreed to new 10-year contracts (2001 to 2011), while others agreed to new 15-year contracts (2001 to 2016). FERC approved the proposal, allowing levelized rates to continue and permitting Kern River, consistent with its original certificate order, to recover its debt “by the end of the new debt repayment period.” Kern River Gas Transmission. Co., 92 FERC ¶ 61,061 at 61,157 (2000).

A few years later, Kern River sought to increase the capacity of its pipeline. Because of the unique nature of its existing levelized rate plan, Kern River could not use typical roll-in methodology to recover its expansion costs. Kern River therefore proposed to roll the costs of the proposed expansion into the cost of the original system by adjusting the rates for all “rolled-in” shippers (i.e., existing customers and new expansion customers). Kern River Gas Transmission Co., 96 FERC ¶ 61,137, at 61,576-77 (2001). In 2002, Kern River allowed new expansion customers to choose 10-year or 15-year terms to pay for the additional capacity, and FERC approved the plan. Id. at 61,582. In 2003, Kern River again expanded the pipeline and offered its new expansion customers 10-year or 15-year contracts. Kern River thus had six groups of customers paying levelized Period One rates following its second expansion:

[188]*188• Original shippers with 10-year contracts (2001 to 2011)
• 2002 expansion shippers with 10-year . contracts (2002 to 2012)
• 2003 expansion shippers with 10-year contracts (2003 to 2013)
• Original shippers with 15-year contracts (2001 to 2016)
• 2002 expansion shippers with 15-year contracts (2002 to 2017)
• 2003 expansion shippers with 15-year contracts (2003 to 2018).

B. Procedural Background

In 2004, Kern River filed a general rate case pursuant to Section 4 of the Natural Gas Act, 15 U.S.C. § 717c, seeking to adjust Period One rates (at that time, all customers were paying Period One rates). Kern River Gas Transmission Co., Initial Decision, 114 FERC ¶ 63,031 P 1 (2006). Kern River submitted proposed rates based on a 12-month test period ending in January 2004, “as adjusted for known and measurable changes occurring through October 31, 2004.” Id. In May 2004, the Commission conditionally accepted Kern River’s proposed rates subject to refund and the outcome of further proceedings. Id. P 2. After considering testimony and evidence submitted by the parties, an administrative la\y judge found that Kern River had carried its burden under Section 4 of the Natural Gas Act to prove “that its levelized cost-of-service/ratemaking methodology can produce just and reasonable rates.” Id. P 253. “However,” the administrative law judge concluded that “Kern River ha[d] not proven that its levelized methodology will produce just and reasonable rates if all of its proposed cost-of-service and cost-allocation elements are approved.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
789 F.3d 184, 416 U.S. App. D.C. 39, 2015 U.S. App. LEXIS 10075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aera-energy-llc-v-federal-energy-regulatory-commission-cadc-2015.