Canadian Ass'n of Petroleum Producers v. Federal Energy Regulatory Commission

308 F.3d 11, 353 U.S. App. D.C. 335, 157 Oil & Gas Rep. 882, 2002 U.S. App. LEXIS 22408
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 25, 2002
DocketNo. 00-1498
StatusPublished
Cited by8 cases

This text of 308 F.3d 11 (Canadian Ass'n of Petroleum Producers v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Canadian Ass'n of Petroleum Producers v. Federal Energy Regulatory Commission, 308 F.3d 11, 353 U.S. App. D.C. 335, 157 Oil & Gas Rep. 882, 2002 U.S. App. LEXIS 22408 (D.C. Cir. 2002).

Opinion

Opinion for the Court filed by Chief Judge GINSBURG.

GINSBURG, Chief Judge:

The Canadian Association of Petroleum Producers petitions for review of two orders of the Federal Energy Regulatory Commission approving an increase in the rates charged by Northwest Pipeline Corporation for transporting natural gas. The CAPP contends that the Commission allowed Northwest an excessive rate of return on equity (ROE), resulting in unduly high rates. Because the CAPP failed in its request for rehearing before the Commission to raise its current challenge to the proxy group range of ROEs upon which the Commission based Northwest’s ROE, we lack jurisdiction to consider, and therefore dismiss, that aspect of its petition. Because the Commission’s decision to place Northwest at the median of the proxy group range was reasonable and supported by substantial evidence, we deny the remainder of the petition.

I. Background

In 1995 Northwest applied for a general rate increase that would raise its revenues by $19.2 million per year. The Commission, pursuant to its authority under § 4 of the Natural Gas Act, 15 U.S.C. § 717c, to regulate rates for interstate gas transmission, scheduled an evidentiary hearing before an Administrative Law Judge to consider, among other things, the appropriate rate of return on the equity invested in the pipeline.

The Commission uses a discounted cash flow (DCF) analysis to determine the appropriate ROE for a regulated pipeline company. See Canadian Association of Petroleum Producers v. F.E.R.C., 254 F.3d [13]*13289, 293 (D.C.Cir.2001) ("CAPP I"). For a publicly-traded company, DCF analysis provides an estimate of ROE based upon the price of the company’s stock, the dividend it pays, and projected growth in its earnings. Id. For a company that is not publicly traded, such as Northwest,

the Commission has recourse to calculating the implicit rate of return on companies that are comparable (or at least companies whose business is predominantly the operation of natural gas pipelines) and publicly traded. These companies are called the “proxy group.” The Commission then makes adjustments for specific characteristics of the company whose rates are in question.

Id. at 294.

Northwest proposed to calculate its ROE using a DCF analysis of a “proxy group” composed of six companies. The CAPP, through its expert witness Malcolm Ketchum, challenged the representativeness of that group based upon a “fundamental and continuing evolution taking place in the portfolio of business ventures” in which the proxy companies were engaged. According to Mr. Ketchum, deregulation had enabled pipeline companies to diversify by segregating “pure pipeline” gas transmission operations into affiliated entities and then pursuing related — or, indeed, unrelated — lines of business that posed higher risks but offered greater potential for earnings growth. A higher estimate of growth, when factored into the Commission’s DCF analysis, results in a higher ROE than would be required to attract investment in a less risky, pure pipeline company. Therefore, Mr. Ket-chum argued, the Commission should supplement its DCF analysis with “a critical assessment of the relative business risks faced by a pure regulated pipeline, such as Northwest.”

The ALJ did not adjust the proxy group range of ROEs upon the basis of Mr. Ketchum’s analysis. Neither, however, did the ALJ accept Northwest’s ROE figure, which was based upon a DCF analysis using only short-term growth projections. Instead, using the Commission’s then-prevailing DCF methodology, the ALJ calculated the proxy group range by giving equal weight to short- and long-term growth projections. See Northwest Pipeline Corp., 87 F.E.R.C. ¶ 61,266 at 62,058, 1999 WL 357897 (June 1, 1999) (“Order”). Based upon Northwest’s risk profile, the ALJ then placed Northwest at the midpoint of the proxy group range. Id.

The Commission modified the ALJ’s calculation of the proxy group range in keeping with an intervening decision, Transcontinental Gas Pipe Line Corp., 84 F.E.R.C. ¶ 61,084, 1998 WL 608596 (July 29, 1998) (“Transco”), in which the Commission had decided to give short-term growth projections more weight than long-term growth projections in its DCF calculations. Order at 62,061. As for placement of Northwest within the range, the Commission analyzed the company’s competitive circumstances and the status of its contracts for the delivery of gas to users, and affirmed the ALJ’s finding that Northwest faced an average level of risk. In another modification stemming from Transco, however, the Commission placed Northwest, as a company of average risk, at the median rather than the midpoint of the proxy group range of ROEs. Id. at 62,068. The Commission noted but, curiously, did not address the CAPP’s argument that the ALJ had erred by failing to take into account, when placing Northwest within the range, the difference in risk between Northwest and the companies in the proxy group. Order at 62,065.

The CAPP sought rehearing of the Order in two respects relevant here. First, [14]*14the CAPP argued that the Commission had erred in placing Northwest at the median of the proxy group range. Specifically, the CAPP challenged the Commission’s finding that Northwest faced significant competition and argued that the Commission’s analysis of Northwest’s contracts was flawed. Again curiously, however, the CAPP did not protest the Commission’s failure to address the CAPP’s argument for adjusting Northwest’s position within the range to account for differences between Northwest and the proxy companies.

Rather, the CAPP relied upon those differences to support its second ground for rehearing, namely, that the Commission, in determining the proxy group range, should not have applied the recently-revised weighting formula adopted in Transco. The CAPP argued that short-term growth projections were influenced by the non-pipeline businesses of the proxy group companies and thus skewed upward the range of ROEs for the proxy group.

The Commission rejected both the CAPP’s arguments. Northwest Pipeline Corp., 92 F.E.R.C. ¶ 61,287, 2000 WL 1457024 (Sept. 29, 2000) (“Rehearing Order"). First, the Commission adhered to its position in Transco that short-term growth projections are inherently more reliable than long-term growth projections, and therefore should be weighted more heavily. Id. at 62,003-04. Acknowledging that “there may be some differences between the proxy companies and Northwest,” the Commission was satisfied nevertheless that the proxy group comprised “the six publicly traded companies whose operations most closely mirror the operations of a pure pipeline company.” Id. at 62,005. Second, the Commission reiterated its conclusion that Northwest faced average business risks stemming from actual and potential competition and from a short average contract life relative to the depre-ciable life of its facilities. Id. at 62,006-08.

II. Jurisdiction

Before addressing the merits of the CAPP’s petition for review, we consider, at the Commission’s urging, a jurisdictional question arising from the difference between the CAPP’s position here and what it urged before the Commission in its request for rehearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cellwitch Inc. v. Tile, Inc.
N.D. California, 2024
Maine v. Federal Energy Regulatory Commission
854 F.3d 9 (D.C. Circuit, 2017)
Basardh v. Gates
545 F.3d 1068 (D.C. Circuit, 2008)
Can Assn Petro v. FERC
308 F.3d 11 (D.C. Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
308 F.3d 11, 353 U.S. App. D.C. 335, 157 Oil & Gas Rep. 882, 2002 U.S. App. LEXIS 22408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/canadian-assn-of-petroleum-producers-v-federal-energy-regulatory-cadc-2002.