Cities of Campbell and Thayer, Missouri v. Federal Energy Regulatory Commission, Arkansas Power & Light Company, Intervenor

770 F.2d 1180, 248 U.S. App. D.C. 267
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 25, 1985
Docket84-1017
StatusPublished
Cited by22 cases

This text of 770 F.2d 1180 (Cities of Campbell and Thayer, Missouri v. Federal Energy Regulatory Commission, Arkansas Power & Light Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cities of Campbell and Thayer, Missouri v. Federal Energy Regulatory Commission, Arkansas Power & Light Company, Intervenor, 770 F.2d 1180, 248 U.S. App. D.C. 267 (D.C. Cir. 1985).

Opinion

MacKINNON, Senior Circuit Judge:

The Cities of Campbell and Thayer, Missouri (“Cities”) petition under 15 U.S.C. § 3416(a)(4) for review of a Federal Energy *1182 Regulatory Commission (“FERC” or “Commission”) order affirming and adopting an initial Administrative Law Judge’s decision and denying rehearing construing contracts between the Cities and the Arkansas Power & Light Company (“AP & L”) as permitting unilateral rate increases under § 205 of the Federal Power Act (“FPA” or “Act”), 16 U.S.C. § 824d (1981). The issue on review is whether the Commission correctly interpreted the contracts between AP & L and the Cities. We conclude that the Commission’s interpretation was correct, and affirm.

I.

In 1975, the Cities contracted to purchase electric power from the Arkansas-Missouri Power Company (“Ark-Mo”), the predecessor-in-interest of AP & L. These contracts contained identical clauses, stating:

ARTICLE III — Rate
Each month Customer will pay to the Company for all energy delivered during the preceding month an amount determined in accordance with Company’s R-l rate as now on file with the Federal Power Commission or as same may be amended from time to time____
******
ARTICLE VII — Regulatory Approval
This agreement is entered into subject to the approval of regulatory agencies having jurisdiction over such company matters. In addition, the rate, terms and conditions stated in the contract are subject to change at any time subject to the approval of governmental regulatory bodies having jurisdiction.

(Joint Appendix (J.A.) 1601, 1602) (emphasis added).

In 1978, Ark-Mo raised the rates unilaterally by filing the new rates with the Commission under § 205 of the Federal Power Act. Although these rates represented an increase of approximately 30%, and took effect upon filing under § 205, the Cities did not object. Three years later, in 1981, AP & L, the successor to Ark-Mo, notified the Cities of another rate increase of 95%, to become effective, as did the previous increase, after filing with the Commission under § 205. Upon learning of this rate increase, the Cities filed their Protest and Petition to Intervene before the Commission (J.A. 1515). The Cities did not, however, contest at this time the right of the company to increase the rates unilaterally under § 205, but requested, as they were entitled to under that section, that the Commission suspend the proposed rate filing for the maximum period of five months. The Cities filed a motion to dismiss the filing as to the Missouri Utilities Company or alternatively to intervene and suspend the rate for the maximum, five month period (J.A. 1887-1900). Petitioners did not raise the objection that the underlying contracts did not permit AP & L to make unilateral rate changes under § 205 until two months later. The Commission accepted the filing and suspended the proposed rates for five months, setting the matter for hearing (J.A. 1537-44).

On December 30,1981, petitioners moved the Commission to modify its August 28, 1981 order to reject AP & L’s proposed rate increase rather than to suspend it for five months. The rate increase, petitioners said, violated their contracts which they alleged permitted rate changes to take effect only after the Commission approved them (J.A. 1788-99). The Commission denied petitioners’ motion on March 3, 1982, finding that the plain language of the contract provided for a unilateral rate change procedure that was consistent with § 205 of the Act (J.A. 186). On April 5, 1982, the Cities filed a Petition for Rehearing, which the Commission denied as untimely on May 5, 1982. The Cities subsequently on June 4, 1982 filed a Petition for Rehearing and Reconsideration of the May order. The Commission on July 6,1982 denied the Petition for Rehearing and ordered a reconsideration of its Order of March 3, 1982. The Commission set for hearing the issue of whether extrinsic evidence indicated that the parties’ intent as to the contract differed from that ascribed to them by the Commission in its interpretation of the con *1183 tract. The AU, after hearing the evidence and excluding some testimony as untimely, upheld the Commission’s interpretation. The Cities appeal now from the Commission’s subsequent order upholding the rate increase as consistent with the provisions of the contract.

II.

On appeal, the Cities raise three main issues. First, the Cities argue that the Commission improperly applied the Sierra-Mobile doctrine to the contracts by finding that they permitted unilateral rate increases. Second, the Cities claim the Commission erred in affirming the ALJ’s decision that the extrinsic evidence showed that the parties intended that changes could become effective upon unilateral filing of rate changes by the company under § 205. Third, the Cities claim the Commission, in approving the AU’s exclusion from evidence of the testimony of the Cities’ two witnesses, was arbitrary and capricious and denied the City a fair hearing. As a preliminary matter we address AP & L’s claim that the Cities’ petition for review should be dismissed because their Petition for Rehearing was untimely filed.

A. AP & L’s Claim of Untimeliness

AP & L argues that the Cities’ appeal should be dismissed because the Cities did not file a Petition for Rehearing within 30 days of a final Commission order as provided by statute. See 16 U.S.C. § 8521 (a). In AP & L’s view, the order for reconsideration by the Commission, from which petitioners presently appeal, is not properly appealable because it merely allowed the prior order to remain and had itself no independent effect. Thus, AP & L contends that the present appeal is no more than an evasion of the statutory jurisdictional requirement of a timely rehearing petition.

AP & L’s argument would have merit except for the particular circumstances of this case. Section 313(a) of the Federal Power Act provides that “[n]o proceeding to review any order of the Commission shall be brought by any person unless such person shall have made application to the Commission for a rehearing thereon.” 16 U.S.C. § 825Z (a). Applications for rehearing may be made within 30 days after FERC’s issuance of the challenged order. Id. The 30-day time requirement of this statute is as much a part of the jurisdictional threshold as the mandate to file for a rehearing. Boston Gas Co. v. FERC, 575 F.2d 975 (1st Cir.1978). See also Dayton Power & Light Co. v. FPC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SFPP LP v. FERC
967 F.3d 788 (D.C. Circuit, 2020)
Commonwealth v. Williamson
971 N.E.2d 250 (Massachusetts Supreme Judicial Court, 2012)
ME Pub Util Cmsn v. FERC
454 F.3d 278 (D.C. Circuit, 2006)
Atl City Elec Co v. FERC
329 F.3d 856 (D.C. Circuit, 2002)
Power, David F. v. FLRA
D.C. Circuit, 1998
Keith Equipment Co. v. Casa Grande Cotton Finance Co.
928 P.2d 683 (Court of Appeals of Arizona, 1996)
Dynaquest Corp. v. United States Postal Service
12 F.3d 1144 (D.C. Circuit, 1994)
In Re Teamsters Industrial Employees Welfare Fund
989 F.2d 132 (Third Circuit, 1993)
Jones v. District of Columbia Department of Employment Services
584 A.2d 17 (District of Columbia Court of Appeals, 1990)
Immigration & Naturalization Service v. Abudu
485 U.S. 94 (Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
770 F.2d 1180, 248 U.S. App. D.C. 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cities-of-campbell-and-thayer-missouri-v-federal-energy-regulatory-cadc-1985.