Xcel Energy Services Inc. v. Federal Energy Regulatory Commission

510 F.3d 314, 379 U.S. App. D.C. 86, 2007 U.S. App. LEXIS 28882
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 14, 2007
Docket06-1174
StatusPublished
Cited by2 cases

This text of 510 F.3d 314 (Xcel Energy Services Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Xcel Energy Services Inc. v. Federal Energy Regulatory Commission, 510 F.3d 314, 379 U.S. App. D.C. 86, 2007 U.S. App. LEXIS 28882 (D.C. Cir. 2007).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

WILLIAMS, Senior Circuit Judge:

Section 205 of the Federal Power Act, 16 U.S.C. § 824d, and FERC regulations, 18 C.F.R. § 35.3, require that utilities provide 60 days prior notice to the Federal Regulatory Energy Commission before a rate takes effect. FERC may waive that requirement, however, “for good cause shown.” Id. at § 35.11. Xcel Energy Services, Inc. challenges FERC’s decision not to waive the prior notice requirement for four interconnection agreements that Xcel filed more than four years after the effective date chosen by the parties. Xcel’s challenge to the ruling on one of the four agreements fails for want of standing; as to the other three, we find FERC’s decision neither arbitrary nor capricious.

* * *

Four interconnection agreements are at issue here, but the four share origins with a fifth, on which the four disputed ones pivot. Public Service Company of Colorado — an affiliate of Xcel (and, for simplicity’s sake, also referred to here as “Xcel”) — conducted a competitive bidding process that resulted in power purchase agreements and five interconnection agreements with four companies. Xcel entered into all five interconnection agreements at various times between January 26, 2001 and October 26, 2001. Xcel filed an agreement with Plains End, LLC — the one of the five that is not directly at issue here- — on August 22, 2001, but a dispute arose between the two over the calculation of the facilities charge as set forth in the agreement. See Xcel Energy Servs., Inc., 100 FERC ¶ 61,267 at 62,016 P 9 (2002). FERC conditionally accepted the Plains End agreement on September 13, 2002, made it effective as of August 23, 2001, and held the facilities charge dispute in abeyance in order to permit settlement negotiations between the parties. Id. at 62,019 P 33. The parties reached an agreement on March 12, 2004, which FERC accepted on May 27, 2004. See Xcel Energy Servs., Inc., 107 FERC ¶ 61,-198 (2004).

Of the four remaining transactions, an agreement was initially filed for one in July 2001 (an agreement with Fountain Valley Power, LLC), providing for a charge of about $31,000 a month. FERC *316 accepted it and granted a waiver allowing a retroactive date of February 21, 2001. Agreements for the remaining three transactions — two with Black Hills Colorado, LLC, and another with BIV Generation Co., LLC — were also signed in 2001 but not filed with FERC. For about three of the next four years, service proceeded while the parties awaited resolution of the Xcel-Plains End dispute. As we have seen, that wrapped up in March 2004 and FERC accepted the result in May.

Just shy of a year-and-a-half later, on November 14, 2005, Xcel filed the four “Amended and Restated” interconnection agreements now at issue. Each new agreement provided for a new facilities charge calculated pursuant to the terms of the Plains End settlement agreement. We note, and will return to the point later, that the Fountain Valley agreement filed in 2005 provided for a charge of about $6500 a month; the new rate represented about an 80% reduction from the prior filing, presumably due to the influence of the Plains End settlement. Xcel requested waiver of the 60-day prior notice requirement, asking that each agreement be effective as of the 2001 date of the initial interconnection agreements. FERC declined to waive the prior notice requirement and instead accepted the four interconnection agreements with an effective date of January 13, 2006. Xcel Energy Servs., Inc., Letter Order, Docket Nos. ER06-207-000, ER06-208-000. ER06-209-000, ER06-210-000 (Dec. 23, 2005).

Xcel requested rehearing. In an order denying rehearing, FERC found that Xcel had failed to show either that the agreements fit within the narrow situations in which it was willing to grant waiver as a matter of course, or that there were “extraordinary circumstances” justifying waiver. Xcel Energy Servs. Inc., 114 FERC ¶ 61,295 at 62,048 P 9 (2006) (“Order. Denying Reh’g ”). FERC explicitly rejected the idea that the multi-year provision of service under unfiled agreements, while the parties awaited resolution of the Plains End matter, presented extraordinary circumstances. Id. This petition followed.

Standing. Before we can reach the substance of Xcel’s petition for review, we must .address two issues related to its standing.

Xcel describes a financial arrangement underlying all four interconnection agreements that seems — at least at first glance — somewhat odd. Those interconnection agreements provide for Xcel to collect monthly facilities charges from its counterparts, but power purchase agreements between the parties require Xcel to reimburse its counterparts for those charges in the same amount. Thus it would seem that what Xcel takes it then gives away, resulting in a net gain of nothing (or, more important for our purposes, a loss of nothing from FERC’s decision not to waive the prior notice requirement). But Xcel explains that this odd arrangement is in fact a stepping stone to a financial recovery: collection and reimbursement are a predicate to Xcel’s recovering the amounts of its reimbursements from its retail customers. So while the net effect between Xcel and its counterparts is zero, Xcel’s net injury is not. As a direct effect of FERC’s refusal to waive the prior notice requirement and permit an earlier effective date for these agreements, Xcel cannot recover those amounts from its retail customers. FERC offers nothing to contradict this analysis. Thus Xcel has an injury-in-fact — except as to one agreement.

As to the fourth agreement the math fails. Xcel admits that one of its interconnection agreements with Black *317 Hills Colorado, one related to the Valmont Generating Facility, establishes a $0 monthly facilities charge. Because Xcel collects nothing, it also reimburses nothing, so the agreement gives it no ability to recover any amounts from retail customers. Xcel essentially concedes that FERC’s decision not to waive the prior notice requirement for this agreement caused it no harm, but it nonetheless asks that we review the decision simply because FERC addressed this interconnection agreement in the same orders in which it addressed the others. That coincidence provides no substitute for injury-in-fact, and thus we dismiss the petition for review for lack of subject-matter jurisdiction insofar as it challenges FERC’s orders in Docket No. ER06-208.

Merits. The filing and prior notice requirements of section 205 of the Federal Power Act, 16 U.S.C. § 824d, and FERC regulations, 18 C.F.R. § 35.3, provide FERC with timely information from which it can “monitor[] the reasonableness of prices and undue discrimination in the marketplace” and “assist the public in filing complaints” by providing it with “good information about energy transactions.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
510 F.3d 314, 379 U.S. App. D.C. 86, 2007 U.S. App. LEXIS 28882, Counsel Stack Legal Research, https://law.counselstack.com/opinion/xcel-energy-services-inc-v-federal-energy-regulatory-commission-cadc-2007.