City of Girard, Kansas v. Federal Energy Regulatory Commission, Kansas Gas and Electric Company, Intervenor

790 F.2d 919, 252 U.S. App. D.C. 358, 1986 U.S. App. LEXIS 25016
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 16, 1986
Docket84-1210
StatusPublished
Cited by16 cases

This text of 790 F.2d 919 (City of Girard, Kansas v. Federal Energy Regulatory Commission, Kansas Gas and Electric Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Girard, Kansas v. Federal Energy Regulatory Commission, Kansas Gas and Electric Company, Intervenor, 790 F.2d 919, 252 U.S. App. D.C. 358, 1986 U.S. App. LEXIS 25016 (D.C. Cir. 1986).

Opinion

Opinion for the Court filed by Senior Circuit Judge McGOWAN.

McGOWAN, Senior Circuit Judge:

Petitioner Girard, Kansas, is a municipality that purchases wholesale power from intervenor Kansas Gas and Electric (“KG & E”). Girard maintains its own power generation facilities but purchases its excess requirements from KG & E. Girard then resells some or all of its power to retail customers. In this case, Girard challenges an order of the Federal Energy Regulatory Commission (“Commission” or “FERC”) refusing to grant retroactive effect to a KG & E rate filing. Based on the filed rate doctrine, we reject Girard’s claim of entitlement to a retroactive effective date. We further find that whether or not the ban on retroactive ratemaking disables the Commission from implementing KG & E’s new rate retroactive to the date the *920 rate was filed, Girard has failed to present good cause for waiving the entire sixty-day notice period before new rates generally become effective.

I. The Statutory Framework

Under §§ 205 and 206 of the Federal Power Act, Pub.L. No. 333, 49 Stat. 847, 851-52 (1935) (codified as amended at 16 U.S.C. §§ 824d, 824e (1982)), FERC has the authority and duty to regulate the rates at which wholesale electrical power is sold. A utility is prohibited from charging unjust and unreasonable rates. 16 U.S.C. § 824d(a) (1982). There are two tracks for securing review of a rate. Under § 205 of the Act, public utilities can prompt review of a proposed rate by filing a new rate schedule with the Commission. Under § 206, the Commission may review the lawfulness of a rate already in effect after a complaint, or on its own motion.

Under § 205(d), the first track for review, a utility may apply for a new rate. After sixty days’ notice to the Commission and the public, the new rate may become effective. 1 The Commission has the power to waive this sixty-day notice requirement “for good cause shown.” 16 U.S.C. § 824d(d) (1982). If the Commission determines that a proposed rate may be unlawful, it may suspend its effective date for up to five months pending a hearing. Federal Power Act § 205(e), 16 U.S.C. § 824d(e) (1982). 2

Section 206 comprises the second track for Commission review. 3 The Commission may review rates already in effect under § 206 on complaint or on its own motion. If the Commission finds the rate unjust or unreasonable, it may set a new rate “to be thereafter observed.” Federal Power Act § 206(a), 16 U.S.C. § 824e(a) (1982). It is settled that the Commission has no power under § 206 to order relief other than prospectively from the date of its decision that the existing rate is unlawful. See Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, 578, 101 S.Ct. 2925, 2930, 69 L.Ed.2d 856 (1981). 4

In this case, we review the Commission’s determination in a § 205 proceeding that a new rate filed by a utility on December 5, *921 1983 could become effective only on January 31, 1984.

II. The Girard Dispute

Girard maintains a power distribution system to serve its inhabitants. Some or all of this power is initially supplied to Girard by KG & E. As with all customers, Girard’s rates are determined by a tariff on file with the Commission., The particular filing applicable to Girard is entitled “Schedule 147.” Schedule 147 incorporates rate features designed for municipal customers who take only part of their requirements from the utility. 5 Schedule 147 was filed with the Commission on March 24, 1981. It detailed the terms under which KG & E would sell power to Girard, and had a term of five years. Under Schedule A of Schedule 147, the precise amount of prearranged, or “firm,” power supplied each year by KG & E to Girard was to be expressed in yearly letters of intent signed by each of the parties. These letters of intent obligated KG & E to sell, and Girard to buy, an agreed-upon amount of power during the term of the letter. On September 24, 1981, Girard and KG & E executed a letter of intent specifying the quantity to be purchased by Girard over a fourteen-month period beginning July 1, 1981. On September 20, 1982, the parties executed a new letter of intent covering the period from August 1, 1982, to July 31, 1983.

Sometime prior to July 31, 1983, Girard’s power generation facilities failed. Since Girard was incapable of generating any power on its own, it became fully dependent on purchases from KG & E. The City requested that KG & E charge Girard under a lower rate schedule, reflecting Girard’s new status as a full-requirements customer. KG & E did have a tariff on file with the Commission (Schedule PWM-883) setting the rate it charged certain full-requirements municipal customers. Prior to this dispute, however, it was KG & E’s policy to file PWM-883 as the rate schedule applicable to a particular full-requirements customer only if that customer executed a full-requirements contract with the utility. Since Girard and KG & E were still in the process of negotiating such a contract, the utility did not immediately accede to Girard’s request. After July 31, 1983, the parties’ contract, as memorialized by the second letter of intent, had expired. KG & E continued to charge Girard under Schedule 147, the partial-requirements tariff, while the parties attempted to negotiate a new contract.

On December 5, 1983, after four months of unsuccessful negotiations, KG & E filed a new, full-requirements rate schedule applicable to Girard. Girard intervened, challenging the new rate on the merits, as well as KG & E’s proposed effective date of January 31, 1984. Girard argued that it was entitled to purchase power under the lower, full-requirements schedule as of August 1, 1983, when its contract expired and it was a “de facto” full-requirements user. On February 3, 1984, the Commission rejected Girard’s claims and implemented the new full-requirements rate as of January 31, 1984, subject to some limitations not relevant here. Kansas Gas & Elec. Co., 26 F.E.R.C. ¶ 61,122 at 61,305 (1984) (“Initial Decision”). The Commission denied Girard’s petition for rehearing on April 4, 1984. Kansas Gas & Elec. Co., 27 F.E.R.C. ¶ 161,009 at 61,015 (1984) (“Rehearing”).

Girard now petitions this court for review of the Commission’s order regarding the effective date of the new rate. We have jurisdiction based on 16 U.S.C. § 825Z

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Iowa Network Services, Inc. v. Qwest Corp.
385 F. Supp. 2d 850 (S.D. Iowa, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
790 F.2d 919, 252 U.S. App. D.C. 358, 1986 U.S. App. LEXIS 25016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-girard-kansas-v-federal-energy-regulatory-commission-kansas-gas-cadc-1986.