City of Cleveland, Ohio v. Federal Power Commission, Cleveland Electric Illuminating Company, Intervenor

525 F.2d 845, 174 U.S. App. D.C. 1
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 9, 1976
Docket73--1282
StatusPublished
Cited by77 cases

This text of 525 F.2d 845 (City of Cleveland, Ohio v. Federal Power Commission, Cleveland Electric Illuminating Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cleveland, Ohio v. Federal Power Commission, Cleveland Electric Illuminating Company, Intervenor, 525 F.2d 845, 174 U.S. App. D.C. 1 (D.C. Cir. 1976).

Opinion

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

This petition for review poses centrally the question whether the Federal Power Commission erred in adopting a rate structure specified in a schedule filed by a public electric utility without resolving its municipal customer’s contention that the schedule contravenes a preexisting agreement between the parties. We answer that question in the affirmative. Accordingly, while we affirm the Commission on all other issues presented, we remand the case for further proceedings.

I

The City of Cleveland, Ohio, operates an electric light plant from which a part of the electrical power it consumes is derived. Its remaining requirements are served by the Cleveland Electric Illuminating Company (CEI), a public utility as defined by the Federal Power Act. 1 During the 1969 Christmas season, the municipal plant suffered a forced outage of its largest generating unit, which rendered it unable to supply normal street lighting and customer service. The train of activity designed to meet this crisis led ultimately to the litigation now before us.

Negotiations between the City and CEI produced an early understanding on *847 a temporary load transfer service 2 to alleviate the emergency. 3 To satisfy a requirement of the City’s charter, 4 its City Council, on January 19, 1970, passed Ordinance No. 161-70 5 authorizing a contract with CEI for the service at rates previously worked out. 6 On the following day, representatives of the parties signed a letter agreement 7 calling for the service for a maximum term expiring on December 31, 1971. 8 The letter agreement and subsequent modifications 9 were later submitted to 10 and accepted by the Commission for filing as a rate schedule. 11

*848 CEI commenced service in February, 1970, and the City made payments therefor through March, 1971. At this point, the City challenged CEI’s billings on the ground that the rates which it had filed with the Commission exceeded those which the parties had agreed to and which Ordinance No. 161 — 70 had authorized. This dispute, together with another over amounts allegedly owed by the City, 12 disrupted efforts to arrange a permanent interconnection, and precipitated a suit by CEI for arrearages, 13 a complaint by the City launching the proceeding under review, 14 and a notice by CEI that it was cancelling the service. 15

In its complaint to the Commission, filed May 13, 1971, the City sought a permanent interconnection with CEI, 16 a ruling on the rate and arrearages issues, and ah order forbidding termination of the temporary service. 17 CEI extended its cancellation notice to December 16, 1971, at which time the Commission suspended the notice until May 17, 1972, 18 and on May 18 continued the service and the filed rates in effect pending further order. 19 On May 30, the Commission fixed interim rates for continuation of the service until entry of its final order in the proceedings. 20

During March and April, 1972, hearings were conducted by an examiner 21 who, on July 12, issued an initial decision 22 finding that a permanent synchronous interconnection would serve the public interest. 23 He directed the interconnection on specified terms and conditions, including authority to levy a charge for late payment of bills, 24 and proceeded to set rates for the permanent service. 25 The examiner found wanting the City’s argument that the rates filed by CEI, and exacted until the Commission-fixed rates went into operation, 26 *849 did not abide the actual agreement of the parties. 27

Both the City and CEI filed exceptions, upon consideration of which the Commission, in Opinion No. 644, adopted the examiner’s decision in all but several relatively minor respects. 28 Adjustments were made in the rates, 29 which were to include the effects of an Ohio excise tax, 30 an item which the examiner had excluded. 31 The Commission retained and refined the examiner’s late-charge feature, 32 and left standing his rejection of the City’s objection to the filed rates. 33 By Opinion No. 644-A, the City’s application for rehearing was denied, 34 whereupon its petition for review by this court followed.

The petition presents for our decision contentions that the Commission erred (a) in adhering to the rates filed by CEI despite the claims that they did not accurately reflect those previously agreed to; 35 (b) in prescribing permanent rates allegedly lacking substantial supporting evidence; 36 (c) in including the *850 amount of the Ohio excise tax in the makeup of the permanent rates; 37 and (d) in sanctioning the charge for late payment. 38 We agree with the City on *851 the first point, 39 and with the Commission on the others. 40

II

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoover v. HSBC Mortgage Corp.
9 F. Supp. 3d 223 (N.D. New York, 2014)
BNSF Railway Co. v. Surface Transportation Board
741 F.3d 163 (D.C. Circuit, 2014)
Gordon v. Council of the City of New Orleans
977 So. 2d 212 (Louisiana Court of Appeal, 2008)
Centerpoint Energy Entex v. Railroad Commission
208 S.W.3d 608 (Court of Appeals of Texas, 2006)
In Re Enron Corp.
327 B.R. 526 (S.D. New York, 2005)
Hagelin v. Federal Election Commission
332 F. Supp. 2d 71 (District of Columbia, 2004)
Big Rivers Electric Corp. v. Thorpe
921 F. Supp. 460 (W.D. Kentucky, 1996)
Cooperative Communications, Inc. v. AT & T CORP.
867 F. Supp. 1511 (D. Utah, 1994)
Daily Advertiser v. TRANS-LA, ETC.
612 So. 2d 7 (Supreme Court of Louisiana, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
525 F.2d 845, 174 U.S. App. D.C. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cleveland-ohio-v-federal-power-commission-cleveland-electric-cadc-1976.