Sierra Pacific Power Company v. Federal Energy Regulatory Commission, and Utah Power and Light Company, Intervenor

793 F.2d 1086, 1986 U.S. App. LEXIS 26799
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 8, 1986
Docket84-7627
StatusPublished
Cited by7 cases

This text of 793 F.2d 1086 (Sierra Pacific Power Company v. Federal Energy Regulatory Commission, and Utah Power and Light Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Pacific Power Company v. Federal Energy Regulatory Commission, and Utah Power and Light Company, Intervenor, 793 F.2d 1086, 1986 U.S. App. LEXIS 26799 (9th Cir. 1986).

Opinion

BRUNETTI, Circuit Judge:

Sierra Pacific Power Company (“Sierra”) petitions for review of the Federal Energy Regulatory Commission’s (“FERC”) orders permitting the costs of Utah Power and Light Company’s (“UP & L”) lower voltage transmission system to be rolled-in with the costs of its higher voltage system. Sierra argues that FERC’s findings are not supported by substantial evidence and that FERC erroneously failed to follow its own precedent. We affirm.

FACTS AND PROCEEDINGS BELOW

In January 1982, pursuant to section 205(d) of the Federal Power Act, 16 U.S.C. § 824d(d) (1982), UP & L filed with FERC revised rate schedules that increased electricity rates to its interstate resale customers. In March 1982, FERC accepted the revised rate schedules for filing, ordered a hearing concerning the reasonableness of the revised rates pursuant to 16 U.S.C. § 824d(e) (1982), and permitted several parties, including Sierra, one of UP &x L’s interstate resale customers, to intervene as objectors.

In June 1983, FERC accepted a settlement in the rate revision controversy with one exception. The unresolved issue concerned Sierra’s (a higher voltage customer) disagreement with UP & L’s use of the rolled-in allocation method. Sierra asserted, inter alia, that it should not have to pay for any of the forty-six and sixty-nine kilo-volt transmission facilities because it receives no benefit from them.

The Administrative Law Judge’s decision, issued in September 1983, held that res judicata barred relitigation of the issue because FERC had found rolled-in allocation appropriate in an earlier UP & L case. Nevertheless, the AU reached the merits of the case and concluded alternatively that rolled-in allocation was appropriate in the current proceeding. In May 1984, FERC rejected the ALJ’s res judicata analysis but affirmed and adopted his decision to accept rolled-in allocation. In June 1984, pursuant to 16 U.S.C. § 825/ (a) (1982), Sierra applied to FERC for rehearing. FERC denied the application in July 1984, and Sierra timely petitioned for review of FERC’s opinion and order denying rehearing pursuant to 16 U.S.C. § 825/(b) (1982).

DISCUSSION

1. Rolled-in Transmission Costs

FERC’s finding that rolling-in transmission costs is permissible is a question of fact. See Nevada Power Company v. Federal Power Comm’n, 589 F.2d 1002, 1007 (9th Cir.1979) (roll-in of transmission costs reviewed by court under the substantial evidence standard); cf. Anaheim v. Federal Energy Regulatory Comm’n, 669 F.2d 799, 810 (D.C.Cir.1981) (allocation of hardware costs to distribution or transmission function is a question of fact). The Federal Power Act provides that “[t]he finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive.” 16 U.S.C. § 825/ (b). Accord, Nevada Power Company, 589 F.2d at 1006. Substantial evidence “means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion”. Consolidated Edison Company v. National Labor Relations Board, 305 U.S. 197, 229, 59 S.Ct. 206, 216, 83 L.Ed. 126 (1938). Deference to FERC’s decisions is suitable because of “the breadth and complexity of the Commission’s responsibilities” under the Federal Power Act, Permian Basin Area Rate Cases, 390 U.S. 747, 790, 88 S.Ct. 1344, 1372, 20 L.Ed.2d 312 (1968) (quoted in Nevada Power Company, 589 F.2d at 1005), and because this rate *1088 case raises “numerous intricate and detailed contentions within the special competence of the Commission.” Nevada Power Company, 589 F.2d at 1006. Moreover, it is the Commission’s function to reach conclusions on conflicting engineering and economic issues so long as its judgment is reasonable and based on evidence. City of Cleveland, Ohio v. Federal Power Commission, 525 F.2d 845, 849 n. 36 (D.C.Cir. 1976).

When a utility uses the rolled-in allocation method for transmission costs, all customers share proportionately in the ownership, operation, and maintenance costs of all transmission facilities. If costs are not rolled-in, each customer class pays only for the transmission system that serves it. FERC favors rolled-in cost allocation when a system is integrated. Fort Pierce Utilities Authority v. Federal Energy Regulatory Commission, 730 F.2d 778, 782 n. 11 (D.C.Cir.1984) (citing Otter Tail Power Company, 12 FERC 1161,169, at 61,420 (1980)). Intervenor UP & L supplies the best definition of integration in this record:

Lower voltage transmission facilities are “integrated,” ... when, in addition to being connected with higher voltage facilities, the lower voltage facilities are themselves interconnected and designed to operate in parallel. This is also referred to as “looping,” that is, the lower voltage transmission facilities form parallel paths for electric energy with the higher voltage transmission facilities. The existence of two or more parallel transmission paths from sources of power to receiving points establishes integration. This is true even where one of the parallel paths is normally operated “opened,” that is, with the connection broken by opening a switch.

Intervenor’s Br. at 10. “[Wjhen ... a higher voltage line goes out of service, power is automatically rerouted throughout the parallel 46 kilovolt system because of this “looping” or integration in accordance with the laws of physics.” Id. at 11. The record confirms this definition.

In a previous UP & L rate case to which Sierra was a party, FERC held that UP & L's transmission costs should be rolled-in because UP & L’s transmission system is integrated. Utah Power & Light Company, 11 FERC 11 63,017, pp. 65,078-79 (1980), aff’d, 14 FERC 11 61,162, p. 61,296, reh’g denied, 15 FERC 11 61,076, pp. 61,183-84 (1981). Because Sierra proposed a change from FERC’s earlier conclusion that UP & L’s transmission system costs should be rolled-in, Sierra was required to show by a preponderance of the evidence, see Steadman v. Securities & Exchange Commission, 450 U.S. 91, 101-02,101 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
793 F.2d 1086, 1986 U.S. App. LEXIS 26799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-pacific-power-company-v-federal-energy-regulatory-commission-and-ca9-1986.