City of Holyoke Gas & Electric Department v. Federal Energy Regulatory Commission, Northeast Utilities Service Company, Intervenor

954 F.2d 740, 293 U.S. App. D.C. 309
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 31, 1992
Docket90-1565
StatusPublished
Cited by11 cases

This text of 954 F.2d 740 (City of Holyoke Gas & Electric Department v. Federal Energy Regulatory Commission, Northeast Utilities Service Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Holyoke Gas & Electric Department v. Federal Energy Regulatory Commission, Northeast Utilities Service Company, Intervenor, 954 F.2d 740, 293 U.S. App. D.C. 309 (D.C. Cir. 1992).

Opinion

Opinion for the Court filed by Circuit Judge D.H. GINSBURG.

D.H. GINSBURG, Circuit Judge:

The City of Holyoke Gas & Electric Department entered into a power transmission agreement with Northeast Utilities Service Co. (NU). When NU filed the agreement with the FERC, Holyoke challenged the rate on various grounds, but the Commission approved it. Holyoke now petitions for review, alleging that the Commission acted arbitrarily and capriciously in upholding the rate as reasonable, denying Holyoke’s request for an evidentiary hearing on the question of undue discrimination, and waiving the statutory notice period for filing a rate agreement.

Although we do not take issue with the methodology the Commission used in order to determine that NU’s proposed rate is reasonable, we remand for the FERC to make the factual findings necessary to justify use of that methodology in this case, and to provide sufficient explanation of its decision and the assumptions underlying it. We conclude that the Commission’s refusal to grant Holyoke a hearing and its waiver of the statutory notice period were proper.

I. Background

Under a 1982 contract, NU charged Ho-lyoke a rate of about $5 per kilowatt-year for nonfirm transmission of electrical power. Before that contract expired on October 31, 1988, NU notified Holyoke that the rate in the replacement contract would be raised to about $24 per kilowatt-year for the same service. Holyoke signed the renewal contract under protest and paid the increased rate as of November 1, 1988. Subsequently, Holyoke and NU negotiated two reductions of the renewal rate, which ultimately brought it down to about $11 per kilowatt-year.

During the eighteen-month period between the expiration of the old contract and the negotiation of the $11 rate, NU billed Holyoke under the terms of the applicable renewal agreement. NU did not file any of the new agreements with the Commission as required by § 205(e) of the Federal Power Act, Pub.L. No. 333, 49 Stat. 847 (1935) (codified as amended at 16 U.S.C. § 824d(e)), until Holyoke had, in April 1990, executed the $11 agreement without expressing any reservations. *742 When it did finally file that agreement, NU also asked the Commission to waive the sixty-day notice requirement of § 205(d) in order to give the agreement an effective date of November 1, 1988, as provided by its terms.

In June 1990, Holyoke filed a protest out of time, claiming that waiver of the statutory notice period was unjustified and that the proposed rate was unreasonable and discriminatory and would enable NU to earn an excessive return on its equity. The Commission allowed the protest, but accepted the $11 rate as reasonable after determining that NU could lawfully have charged even a significantly higher rate. In accordance with its longstanding practice of deferring where possible to the terms of a private agreement, the FERC also granted NU’s request for a waiver of the statutory notice period. Northeast Utilities Service Co., 52 FERC ¶ 61,097 (1990) (NU Order). Holyoke sought rehearing and, when the FERC denied it, Northeast Utilities Service Co., 52 FERC ¶ 61,336 (1990) (NU Rehearing), petitioned this court for review.

II. Analysis

Holyoke now argues that the FERC was arbitrary and capricious in (A) finding NU’s proposed rate reasonable, (B) denying Ho-lyoke’s request for a hearing at which to challenge NU’s proposed rate as unduly discriminatory, and (C) waiving the statutory notice period. We consider these arguments in turn.

A. The Reasonableness of the Proposed Rate

NU derived the $11 rate by determining the revenue it would require in order to recoup the costs it incurs to own and maintain those of its transmission facilities that are part of the New England Power Pool (NEPOOL), plus a 14.5% return on equity. Before the Commission, Holyoke maintained that the $11 rate is unreasonable on two grounds: 14.5% is too high a return on equity, and the city is entitled to the 50% “multi-system discount” that it formerly received. That discount was designed, by its terms, “to give due recognition of the payments made by [Holyoke] to other utility systems providing transmission service over [New England Power] Pool Transmission Facilities” for the same power.

Instead of evaluating the reasonableness of the proposed rate in light of Holyoke’s specific objections, the Commission calculated the rate that NU could lawfully have charged Holyoke if it had “rolled in” the costs it incurs for all of its transmission facilities. Using this larger cost base and the lower return on equity proposed by Holyoke (11.25%), the FERC derived a comparison rate nearly double NU’s proposed rate. The Commission therefore concluded that, a fortiori, NU’s proposed “formula rate produces reasonable rates and provides Holyoke with a discount of about 47 percent from a rate level that would reflect a reasonable contribution to [NU’s] rolled-in transmission costs.” NU Order, 52 FERC at 61,487.

Holyoke takes issue with the Commission’s use of a comparison rate based upon NU’s rolled-in total costs — not in principle, for the practice seems eminently reasonable, but in the specific context of this case. The Commission did so upon the premise that in Public Service Company of New Hampshire, 46 FERC ¶ 61,419 (1989) (PSNH), it had “recently affirmed the reasonableness of evaluating transmission rates in the New England region on the basis of the utility’s rolled-in transmission costs.” NU Order, 52 FERC at 61,486 n. 12. Holyoke, however, argues first that “[t]he FERC’s finding in PSNH was utility-specific,” made “in the context of the demonstrated and explained rolled-in cost of that one utility’s facilities;” (emphasis original) and second that even if the use of rolled-in costs is proper in this case, the agency impermissibly failed to disclose the data and assumptions upon which it relied in calculating the comparison rate.

1. Rolled-in Costs

In reviewing the rate to be charged by an “integrated” transmission system— i.e., an interconnected system designed to operate in parallel, see Sierra Pac. Power Co. v. FERC, 793 F.2d 1086, 1088 (9th Cir.1986) — the “FERC favors rolled-in cost allocation.” Id. at 1086 (citing Fort Pierce Util. Auth. v. FERC, 730 F.2d 778, 782 n. 11 (D.C.Cir.1984), which in turn cites Otter Tail Power Co., 12 FERC ¶ 61,169 at 61,-420 (1980)); see also Detroit Edison Co., 54 FPC 3012 (1975). If a transmission system is not integrated, however, then a rate set on the basis of rolled-in costs would require some ratepayers to bear the costs of facilities from which they derive no benefit. See Otter Tail, 12 FERC at 61,420 (implicit in use of rolled-in costs is “assumption that all customers ... receive the benefits that are inherent in ... an integrated system”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph Padgett v. Brian Loventhal
706 F.3d 1205 (Ninth Circuit, 2013)
We MA Elec Co v. FERC
D.C. Circuit, 1999
Checkosky v. Sec
23 F.3d 452 (D.C. Circuit, 1994)
Checkosky v. Securities & Exchange Commission
23 F.3d 452 (D.C. Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
954 F.2d 740, 293 U.S. App. D.C. 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-holyoke-gas-electric-department-v-federal-energy-regulatory-cadc-1992.