We MA Elec Co v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 15, 1999
Docket92-1665
StatusPublished

This text of We MA Elec Co v. FERC (We MA Elec Co v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
We MA Elec Co v. FERC, (D.C. Cir. 1999).

Opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued October 2, 1998 Decided January 15, 1999

No. 92-1665

Western Massachusetts Electric Company,

Petitioner

v.

Federal Energy Regulatory Commission,

Respondent

Pittsfield Generating Company, L.P.,

and Masspower,

Intervenors

Consolidated with

Nos. 94-1290 & 97-1726

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

David B. Raskin argued the cause for petitioner. With him on the briefs was Frederic Lee Klein.

Samuel Soopper, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Jay L. Witkin, Solicitor, and John H. Conway, Deputy Solicitor. Edward S. Geldermann, Attorney, entered an appearance.

Before: Henderson, Randolph, and Tatel, Circuit Judges.

Opinion for the Court filed by Circuit Judge Randolph.

Randolph, Circuit Judge: Western Massachusetts Electric Company--WMECO--petitions for review of six orders of the Federal Energy Regulatory Commission asserting juris- diction over certain interconnection agreements and ordering the cost of grid upgrades associated with the interconnections to be rolled into WMECO's rate base rather than be borne exclusively by the interconnecting facilities. For the reasons that follow, we deny the petitions for review.

I

The Altresco Agreements

Altresco-Pittsfield Limited Partnership1 operates a 165 MW cogeneration plant located adjacent to a General Electric facility in Pittsfield, Massachusetts. In 1988, the Altresco plant was certified as a "qualifying facility" under the Public Utility Regulatory Policies Act of 1978 (PURPA). See 16 U.S.C. ss 824a-3(j) and 796(17) & (18). Altresco's certifica- tion as a qualifying facility allows it to compel electric utilities to purchase the power it generates and to require intercon- nection with those purchasing utilities in order to facilitate such sales. See 18 C.F.R. s 292.303(a) & (c).

Beginning in 1989, Altresco entered into a series of con- tracts with WMECO under which Altresco would intercon- nect with WMECO's transmission grid. The purpose of the

__________ 1 Altresco-Pittsfield is now known as Pittsfield Generating Com- pany, L.P. For the sake of consistency with the Commission's orders in this case, we will continue to refer to it as Altresco.

interconnection was to enable WMECO to transmit Altresco- generated power across its grid to the New England Power Company (NEPCO); WMECO would not itself purchase any of Altresco's output. The agreements set out the terms and conditions under which WMECO was to construct, operate, and maintain the interconnection. The interconnection itself was to be accomplished by means of a radial line from Altresco's generating facility to a point on WMECO's grid. According to studies performed by WMECO, the Altresco interconnection required certain lines and substations on the grid to be upgraded in order to preserve the grid's reliability. Altresco was to bear the $3.9 million2 cost of the interconnec- tion, including the cost of the upgrades to WMECO's grid.

Believing that the Altresco interconnection agreements would be subject to state rather than federal regulatory authority, WMECO filed the agreements with the Massachu- setts Department of Public Utilities rather than with the Commission. In 1989 and 1990, WMECO negotiated trans- mission service agreements with NEPCO under which WMECO would wheel Altresco-generated power to NEPCO. These transmission agreements were filed with the Commis- sion. The Commission responded on April 24, 1992, with an order setting the transmission rates for hearing and also asserting jurisdiction over the interconnection agreements themselves. See Western Massachusetts Elec. Co., 59 F.E.R.C. p 61,091, at 61,343 (1992).

WMECO requested a rehearing on the question of the Commission's jurisdiction over the interconnection agree- ments, arguing that PURPA gives state authorities jurisdic- tion over interconnections between utilities and qualifying facilities. It further argued that the agreements did not fall within the Commission's jurisdiction because they involved facilities rather than services, because they were all pre- operational, and because they did not involve the interstate transmission of power.

__________ 2 This figure includes $2.98 million for grid upgrades, $510,000 for the radial line connecting Altresco to the WMECO grid, and $450,000 for feasibility and engineering studies.

In a November 1992 order, the Commission rejected WMECO's arguments and denied its request for rehearing on the question of jurisdiction. See Western Massachusetts Elec. Co., 61 F.E.R.C. p 61,182 (1992). The Commission relied on s 205(c) of the Federal Power Act, 16 U.S.C. s 824d(c), and on 18 C.F.R. s 292.303, the regulation setting out the obligation to interconnect. Section 205(c) provides for Commission jurisdiction over "all contracts which in any manner affect or relate to [transmission] rates, charges, classifications, and services, [which are subject to the jurisdic- tion of the Commission]." 16 U.S.C. s 824d(c). The agree- ments "relate to" transmission rates, the Commission held, because the purpose of the interconnection was to facilitate transmission of Altresco-generated power to NEPCO. Therefore the agreements fell within the Commission's juris- diction under s 205(c).

The Commission also held that the regulation assigning jurisdiction over interconnections to state authorities did not apply in this case because WMECO had no obligation to interconnect under s 292.303. WMECO was providing only transmission service; it was not purchasing any of Altresco's output. As the Commission saw it, s 292.303 does not extend the obligation to interconnect "to utilities located between the buyer and the seller that provide transmission service." 61 F.E.R.C. at 61,662. When there is no obligation to intercon- nect, the regulation providing for state regulatory authority over interconnections, 18 C.F.R. s 292.306(a), does not apply. The Commission concluded, therefore, that these agreements were fully within its jurisdiction.

The Commission's orders of April and November 1992 asserting jurisdiction and denying rehearing are the subject of WMECO's December 1992 petition for review in this Court, No. 92-1665.

The Commission ordered an evidentiary hearing before an administrative law judge to determine the "justness and reasonableness" of assigning to Altresco all costs associated with the interconnection agreements. Western Massachu- setts Elec. Co., 63 F.E.R.C. p 61,039, at 61,197 (1993). In the

hearing, WMECO argued that the entire cost, including the cost of the grid upgrades, was directly related to the intercon- nection and therefore could properly be assigned to Altresco. The Commission staff countered that only the $510,000 cost of the radial line from Altresco's plant to the WMECO grid was assignable to the interconnection itself. The remaining amount, in the staff's view, should be allocated to system upgrades, upgrades that should be rolled into the rate base and recovered from all WMECO customers.

The ALJ ruled that the statute did not support the Com- mission's interpretation of what constitutes interconnection costs. See Western Massachusetts Elec. Co., 64 F.E.R.C. p 63,028, at 65,127 (1993). According to the ALJ, nothing in PURPA or in the Commission's regulations implementing PURPA limits interconnection costs to the cost of radial lines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Larionoff
431 U.S. 864 (Supreme Court, 1977)
Robertson v. Methow Valley Citizens Council
490 U.S. 332 (Supreme Court, 1989)
Auer v. Robbins
519 U.S. 452 (Supreme Court, 1997)
Bowles v. Seminole Rock & Sand Co.
325 U.S. 410 (Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
We MA Elec Co v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/we-ma-elec-co-v-ferc-cadc-1999.