Pennsylvania Electric Company v. Federal Energy Regulatory Commission, Pennsylvania Public Utility Commission Penntech Papers, Inc., Intervenors

11 F.3d 207, 304 U.S. App. D.C. 163, 1993 U.S. App. LEXIS 33054
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 21, 1993
Docket92-1408, 92-1542
StatusPublished
Cited by21 cases

This text of 11 F.3d 207 (Pennsylvania Electric Company v. Federal Energy Regulatory Commission, Pennsylvania Public Utility Commission Penntech Papers, Inc., Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Electric Company v. Federal Energy Regulatory Commission, Pennsylvania Public Utility Commission Penntech Papers, Inc., Intervenors, 11 F.3d 207, 304 U.S. App. D.C. 163, 1993 U.S. App. LEXIS 33054 (D.C. Cir. 1993).

Opinion

Opinion for the court filed by Circuit Judge RANDOLPH.

RANDOLPH, Circuit Judge:

Pennsylvania Electric Company (“Pene-lec”) entered into a Transmission Services Agreement with Penntech Papers, Inc. and submitted it to the Federal Energy Regulatory Commission for filing on March 11, 1991. One year later FERC accepted the Agreement for filing on condition that Pene-lec charge Penntech a different, and lower, rate for providing transmission service than that set forth in the Agreement. Pennsylvania Elec. Co., 58 F.E.R.C. ¶ 61,278 (1992). Penelec now petitions for review of FERC’s original order; FERC’s order denying Pene-lec’s rehearing request, 60 F.E.R.C. ¶ 61,034 (1992); and FERC’s notice rejecting Pene-lec’s further request for rehearing, 60 F.E.R.C. ¶ 61,244 (1992).

Penelec is a public utility providing electric service in central, western and northern Pennsylvania to retail customers under rates regulated by the Pennsylvania Public Utility Commission and to wholesale-for-resale customers under rates regulated by FERC under the Federal Power Act, which requires that rates be “just and reasonable.” 16 U.S.C. §§ 824d & 824e.

Penntech is the owner of a cogeneration facility located about seven miles from Pene-lec’s transmission system. A cogeneration facility generates electricity from steam or other forms of energy “used for industrial, commercial, heating, or cooling purposes.” 16 U.S.C. § 796(18)(A); 18 C.F.R. § 292.-202(c). Penntech entered into a contract, on October 31, 1988, with Niagara Mohawk Power Corporation to sell to Niagara in New York that portion of its electrical output Penntech did not need for its industrial operation. The New York Public Service Commission approved Niagara’s purchase.

Penntech had two options for delivering its power to Niagara: (1) build a 7.5-mile, 115 KV line connecting Penntech’s cogeneration facility with a Penelec substation and then have Penelec deliver — “wheel”—the power to Niagara over Penelec’s 115 KV transmission line; or (2) build a 58-mile, 115 KV line running from Penntech’s cogeneration facility directly to Niagara. Penntech decided to pursue option 1 and, to this end, negotiated the Agreement with Penelec that is the subject of this case.

The Penelec-Penntech Agreement submitted to FERC stated that in return for Pene-lec’s transmission service, Penntech would pay a rate made up of three components. The first component was the rate Penelec charged its existing, or native load, customers — the standard firm transmission rate, or as it is sometimes called, the standard embedded-cost transmission rate. Under the Agreement, this component (currently $1,629 per kilowatt per month), which reflects the average costs of the transmission system, would generate yearly charges of $1.2 million. The second component, which Penelec called an “increased energy cost component,” was of a different sort. Estimated to be approximately $200,000 per year, this component was designed as a means of reimbursing Penelec, and ultimately its native load customers, for lost savings. Penelec explained that it had been using its transmission system to transfer “economy” electric energy from sources to its west, energy costing less than that Penelec or its affiliates generated. These transfers enabled Penelec to lower its costs of serving its wholesale and retail customers. In view of the capacity of its trans *209 mission system, however, Penelec would sometimes have to forego transferring economy energy if it provided firm transmission service to Penntech. The parties agreed to cap this “increased energy cost component” at $1.362/kW/month, representing Penelec’s cost of expanding its transmission system sufficiently to eliminate this constraint. The third component included administrative and other costs; it is not at issue and we will disregard it.

In its order of March 10, 1992, and its orders denying rehearing, FERC approved the Penelec-Penntech arrangement on condition that the parties agree to a rate consisting of the higher of either the embedded cost rate or the increased energy cost rate capped at the cost of expansion. See 58 F.E.R.C. at 61,873; 60 F.E.R.C. at 61,120-21; 60 F.E.R.C. at 61,816. Before considering the basis of this ruling and Penelec’s challenge to FERC’s rationale, we will address Penelec’s complaint about the manner in which FERC acted.

Penelec’s procedural complaint begins with the observation, made in its opening Brief (at p. 8), that FERC’s “conditional acceptance” of its Agreement with Penntech amounted to a rejection of it. The observation is undoubtedly accurate. But Penelec waited until its Reply Brief (at pp. 5-7) to set forth a legal argument attacking this mode of decisionmaking. Not until then did Penelec contend that under section 205 of the Federal Power Act, FERC’s authority was limited to accepting the rate for filing, suspending it for a maximum of five months and holding an evidentiary hearing to determine its lawfulness. 1 We have said before, and we say again, that ordinarily we will not consider arguments raised for the first time in a reply brief. See, e.g., Herbert v. National Academy of Sciences, 974 F.2d 192, 196 (D.C.Cir.1992); Rollins Envtl. Servs. v. EPA, 937 F.2d 649, 652-53 n. 2 (D.C.Cir.1991). We perceive no reason for relaxing the bar here, particularly since Penelec’s counsel candidly admitted during oral argument that the company’s filing, which presented no factual issues, would not have warranted an evidentia-ry hearing in any event. See Municipal Light Bds. v. FPC, 450 F.2d 1341, 1345-46 (D.C.Cir.1971), cert. denied, 405 U.S. 989, 92 S.Ct. 1251, 31 L.Ed.2d 455 (1972).

This brings us to the substance of the conditions imposed on the Agreement and FERC’s reasons, originally and on rehearing, for imposing them. As FERC saw it, the Agreement posed the issue whether Penelec, in addition to charging its standard embedded-cost rate, could also recover “opportunity costs.” Opportunity costs, FERC explained, “are incurred by a utility when the utility accommodates a third party’s request for transmission service (i.e., wheeling request) and thereby foregoes an‘opportunity to reduce its own costs, to the economic detriment of the utility’s native load customers.” Pennsylvania Elec. Co., 58 F.E.R.C. at 61,-871. FERC has indicated that it might per-’ mit a utility to recover such opportunity costs in addition to the standard rate. From its prior decisions in Northeast Utilities Service Co. (Re Public Service Co. of New Hampshire), 58 F.E.R.C. ¶ 61,070 (1992) (“NUI”), and Northeast Utilities Service Co., 58 F.E.R.C. ¶ 61,069 (1992) (“NU II”),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William Powell v. IRS
D.C. Circuit, 2023
Constellation Mystic Power v. FERC
45 F.4th 1028 (D.C. Circuit, 2022)
State of Texas v. United States
798 F.3d 1108 (D.C. Circuit, 2015)
Prisology v. Federal Bureau of Prisons
74 F. Supp. 3d 88 (District of Columbia, 2014)
King v. District of Columbia
District of Columbia, 2012
Olaniyi v. United States
District of Columbia, 2011
OLANIYI v. District of Columbia
763 F. Supp. 2d 70 (District of Columbia, 2011)
Chowdhury v. Bair
604 F. Supp. 2d 90 (District of Columbia, 2009)
Chowdhury v. Gruenberg
District of Columbia, 2009
United States Ex Rel. Purcell v. MWI Corp.
520 F. Supp. 2d 158 (District of Columbia, 2007)
Flynn v. Veazey Construction Corp.
310 F. Supp. 2d 186 (District of Columbia, 2004)
Davis v. American Society of Civil Engineers
290 F. Supp. 2d 116 (District of Columbia, 2003)
State, Commercial Fisheries Entry Commission v. Carlson
65 P.3d 851 (Alaska Supreme Court, 2003)
We MA Elec Co v. FERC
D.C. Circuit, 1999
Boyd v. Browner
107 F.3d 922 (D.C. Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
11 F.3d 207, 304 U.S. App. D.C. 163, 1993 U.S. App. LEXIS 33054, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-electric-company-v-federal-energy-regulatory-commission-cadc-1993.