Gainesville Utilities Department v. Florida Power Corp.

402 U.S. 515, 91 S. Ct. 1592, 29 L. Ed. 2d 74, 1971 U.S. LEXIS 114
Supreme Court of the United States·Decided May 24, 1971·No. 464·Published·Cited by 29 cases

Opinion

Me. Justice Brennan

delivered the opinion of the Court.

Under the Federal Power Act, an order of the Federal Power Commission that directs one electric utility “to establish physical connection of its transmission facilities with the facilities of” another utility “may prescribe the terms and conditions of the arrangement to be made . . . including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them.” Federal Power Act §202 (b), 49 Stat. 848, 16 U. S. C. § 824a (b). 1 The Commission order *517 which directed respondent Florida Power Corp. to interconnect its electric system with that of petitioner Gaines-ville Utilities Department did not contain a term or condition sought by respondent requiring petitioner to pay an annual standby charge of approximately $150,000 for the emergency or backup service provided by the interconnection, 40 F. P. C. 1227 (1968); 41 F. P. C. 4 (1969). The Court of Appeals for the Fifth Circuit held that, because of the omission of such a term or condition, “the terms of the interconnection do not adequately satisfy the statutory requirements because they do not provide Florida Power with the ‘reimbursement reasonably due’ it. . . . Thus we deny enforcement of this order insofar as no provision for the reasonable compensation of Florida Power is made.” 425 F. 2d 1196, 1203 (1970) (footnote omitted). We granted the petition for certiorari of Gainesville Utilities Department in No. 464, and of the Federal Power Commission in No. 469, 400 U. S. 877 (1970). We reverse the judgment of the Court of Appeals insofar as it denied enforcement of the Commission’s order and remand for the entry of a new judgment enforcing the Commission’s order in its entirety.

I

The demand upon an electric utility for electric power fluctuates significantly from hour to hour,' day to day, *518 and season to season. For this reason, generating facilities cannot be maintained on the basis of a constant demand. Rather, the utility’s generating capability must be geared to the utility’s peak load of demand, and also take into account the fact that generating equipment must occasionally be out of service for overhaul, or because of breakdowns. In consequence, the utility builds certain “reserves” of generating capacity in excess of peak load requirements into its system. 2 The practice of a utility that relies completely on its own generating resources (an “isolated” system in industry jargon) is to maintain equipment capable of producing its peak load requirements plus equipment that produces a “reserve” capacity equal to the capacity of its largest generating unit.

The major importance of an interconnection is that it *519 reduces the need for the “isolated” utility to build and maintain “reserve” generating capacity. 3 An interconnection is simply a transmission line connecting two utilities. Electric power may move freely through the line up to the line’s capacity. Ordinarily, however, the energy generated by each system is sufficient to supply the requirements of the system’s customers and no substantial amount of power flows through the interconnection. It is only at the times when one of the connected utilities is unable for some reason to produce sufficient power to meet its customers’ needs that the deficiency may be supplied by power that automatically flows through the in *520 terconnection from the other utility. To the extent that the utility may rely upon the interconnection to supply this deficiency, the utility is freed of the necessity of constructing and maintaining its own equipment for the purpose.

The Gainesville Utilities Department is a municipally owned and operated electric utility serving approximately 17,000 customers in a 22-square-mile area covering the city of Gainesville and adjacent portions of Alachua County, Florida. In 1965, Gainesville's “isolated” system had a total generating capability of 108.4 megawatts (mw) while its peak load was 51.1 mw. Gainesville’s generating capacity in 1965 consisted of five steam electric generating units ranging from five to 50 mw. Thus Gainesville’s generating capacity of 108.4 mw gave it a reserve capacity of 57.3 mw over its annual peak load of 51.1 mw — a reserve adequate to cover the shutdown of the system’s largest generating unit of 50 mw. Gaines-ville’s peak load was projected to be doubled to 102 mw by 1970. Its 1970 capacity, however, was projected to increase to only 138.4 mw through the addition in 1968 of two 15-mw gas-turbine generators. Thus an interconnection was necessary if Gainesville was to avoid having to make a still greater investment in generating equipment.

Florida Power Corporation operates a major electric generation, transmission, and distribution system serving 370,000 retail customers in a 20,600-square-mile system serving 32 counties in central and northwest Florida, including Alachua County. It also supplies power at wholesale to 12 municipal distribution systems and 9 REA cooperatives. In 1966, Florida Power had an aggregate generating capability of 1595 mw and experienced a peak load of 1232 mw. At the time of the hearing before the Commission, Florida Power was building a 525-mw generating unit to begin service in December 1969, and *521 anticipated a 1970 generating capability of 2114 mw and a 1970 peak load of 1826 mw. Thus the anticipated excess of capacity over peak load, 288 mw, is less than the size of its largest generating unit, 525 mw. However, the deficiency is provided for by interconnections which Florida Power has with four other Florida utilities. See n. 3, supra. All five of these utilities constitute the Florida Operating Committee, which, though informal in nature, serves as a medium through which the technical operations of its members are coordinated. As a result of the sharing of reserves made possible by the interconnection of the Committee’s members, each utility is able to reduce the reserve generating capacity that would be required if it were electrically isolated. Specifically, each of the Florida Operating Committee members maintains generating capacity equal to 115% of its annual peak load.

For several years prior to 1965, Gainesville sought to negotiate an “interconnection” with Florida Power and with another member of the Florida Operating Committee, Florida Power & Light. When those efforts failed, Gainesville, in 1965, filed an application with the Commission seeking an order under § 202 (b) directing Florida Power to interconnect with Gainesville. 4

II

Section 202 (b) authorizes the Federal Power Commission to order a utility to interconnect with another, and to “prescribe the terms and conditions of the arrangement . . . ,” if the Commission “finds such action *522

Free access — add to your briefcase to read the full text and ask questions with AI

Gainesville Utilities Department v. Florida Power Corp., 402 U.S. 515, 91 S. Ct. 1592, 29 L. Ed. 2d 74, 1971 U.S. LEXIS 114 (1971).

402 U.S. 515 (Gainesville Utilities Department v. Florida Power Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vecchione v. Wohlgemuth
377 F. Supp. 1361 (E.D. Pennsylvania, 1974)
Petition of Green Mountain Power Corporation
305 A.2d 571 (Supreme Court of Vermont, 1973)
Otter Tail Power Co. v. United States
410 U.S. 366 (Supreme Court, 1973)
Otter Tail Power Company v. Federal Power Commission
473 F.2d 1253 (Eighth Circuit, 1973)
Colonial Stores Inc. v. Federal Trade Commission
450 F.2d 733 (Fifth Circuit, 1971)