Otter Tail Power Company v. Federal Power Commission

473 F.2d 1253
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 21, 1973
Docket72-1088
StatusPublished
Cited by9 cases

This text of 473 F.2d 1253 (Otter Tail Power Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otter Tail Power Company v. Federal Power Commission, 473 F.2d 1253 (8th Cir. 1973).

Opinion

STEPHENSON, Circuit Judge.

Otter Tail Power Company appeals from a part of an order of the Federal Power Commission reported at 46 F.P.C. .....(1971). The Commission ordered Otter Tail to permit the Village of Elbow Lake to interconnect its municipal power facilities with Otter Tail’s transmission line for purposes of buying electrical power from Otter Tail.

Section 202(b) of the Federal Power Act (16 U.S.C. § 824a(b)) provides:

(b) Whenever the Commission, upon application of any State commission or of any person engaged in the transmission or sale of electric energy, and after notice to each State commission and public utility affected and after opportunity for hearing, finds such action necessary or appropriate in the public interest it may by order direct a public utility (if the Commission finds that no undue burden will be placed upon such public utility thereby) to establish physical connection of its transmission facilities with the facilities of one or more other persons engaged in the transmission or sale of electric energy, to sell energy to or exchange energy with such persons: Provided, That the *1255 Commission shall have no authority to compel the enlargement of generating facilities for such purposes, nor to compel such public utility to sell or exchange energy when to do so would impair its ability to render adequate service to its customers. The Commission may prescribe the terms and conditions of the arrangement to be made between the persons affected by any such order, including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them.

Otter Tail’s petition objects to the “terms and conditions of the arrangement” with its essential contention being that the terms provided by the order do not constitute “compensation or reimbursement reasonably due” Otter Tail.

Otter Tail is a privately owned utility within the meaning of the Federal Power Act which serves some 460 small communities in Minnesota, North Dakota and South Dakota. Elbow Lake is a village of about 1,500 persons in Minnesota who from 1913 to 1966 was one of the Otter Tail’s electrical energy customers. Otter Tail’s franchise with Elbow Lake expired in 1960 and was not renewed. The village attempted to purchase either Otter Tail’s distribution system in Elbow Lake or electrical power at wholesale from Otter Tail, who refused. In 1962, the voters of Elbow Lake approved a bond issue to finance the construction of a municipal power system. The new system, completed and operating by 1966, consisted of two small diesel generating units (1136 KW nameplate rating each with a two-hour overload capability of 1250 KW) and a distribution system. The record is replete with evidence showing that this municipal adventure was misguided and unfortunate; that isolated diesel generating systems are inefficient and uneconomic; that in the new system’s first year of operations it operated at a loss even though the same rates were charged as before; and that the system had undergone peak hour demands dangerously close to its total capability. Under the circumstances, the system would be unable to satisfy Elbow Lake’s expected future needs for power.

In 1966, Elbow Lake applied to the FPC for an order requiring Otter Tail to furnish it with wholesale electric power, claiming that a shortage of energy was imminent. Following a hearing, the FPC in 1968 ordered a “short term” interconnection under § 202(b) pending further study and hearings. This order required Otter Tail to furnish standby power to Elbow Lake for one year and only in the case of actual need. The order was affirmed by this Court at 429 F.2d 232 (C.A. 8 1970), cert. denied, 401 U.S. 947, 91 S.Ct. 923, 28 L.Ed.2d 230 (1971). Elbow Lake, however, made no effort to make the interconnection with Otter Tail.

The Presiding Examiner in 1971 ordered Otter Tail to sell energy at specified wholesale rates to Elbow Lake and to allow the village to establish a long-term interconnection with Otter Tail’s transmission line. The Presiding Examiner and the Commission found that Otter Tail with its modern steam plants was fully capable of absorbing the village’s full requirements without the necessity of enlarging its facilities, and that the long-term interconnection was necessary and appropriate in the public interest. 1 See § 202(b). Otter Tail does not appeal from this portion of the Commission’s order. 2

*1256 THE TERMS AND CONDITIONS OF THE INTERCONNECTION

The Presiding Examiner and the Commission ordered the sale of Elbow Lake’s entire energy requirements on a firm basis. 3 The Commission directed Otter Tail to permit Elbow Lake to make physical connection with Otter Tail’s transmission line, with the village to install and pay for the facilities necessary for the interconnection. The rate paid to Otter Tail was to be based upon Otter Tail’s fully-allocated cost of firm, wholesale service. The Commission, however, also accepted its staff’s recommendation and ordered that Otter Tail must credit against Elbow Lake’s monthly billing “one-twelfth of the annual interest plus principal costs of Elbow Lake’s generating plant, for each month in which Elbow Lake’s existing two diesel generators are in operable condition.” Under this part of the order, Otter Tail is, in essence, assuming Elbow Lake’s bond issue obligations in full for the duration of the long-term interconnection.

Section 202(b) authorizes the Commission, pursuant to an interconnection order, to prescribe the terms and conditions of the arrangement, “including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them [emphasis added].”

Otter Tail assails this provision of the Commission’s order, claiming that this “credit” is not reasonably or appropriately related to any value of the two diesel engines as additional reserves for Otter Tail, and as a consequence denies to Otter Tail the “compensation or reimbursement reasonably due” Otter Tail under § 202(b). .

In considering this contention we are governed by the recent decision of the Supreme Court in Gainesville Utilities Department v. Florida Power Corporation, 402 U.S. 515, 91 S.Ct. 1592, 29 L. Ed.2d 74 (1971). In Gainesville, the Commission had ordered an interconnection on a “standby” basis in order to obviate Gainesville’s need to build and maintain a larger reserve generating capacity. Florida Power claimed that Gainesville should pay $150,000 annually as compensation reasonably due it for the backup service provided since the reserves made available to Florida Power from Gainesville were insignificant. The Fifth Circuit agreed with Florida Power, holding that Gainesville was receiving high benefits but no real obligations, and that Florida Power obtained obtained substantial obligations, but no real benefits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mississippi Industries v. Federal Energy Regulatory Commission, Missouri Public Service Commission, Mississippi Power & Light Company, Louisiana Power & Light Company, City of New Orleans, Louisiana, Mississippi Public Service Commission, State of Arkansas, Union Carbide Corporation, Occidental Chemical Corporation, Arkansas & Missouri Congressional Delegations, Louisiana Public Service Commission, Arkansas Public Service Commission, Jefferson Parish, Louisiana, Arkansas Power & Light Company, Middle South Energy, Inc., Middle South Services, Inc., and Cities of Conway and West Memphis, Arkansas, Intervenors. Mississippi Public Service Commission v. Federal Energy Regulatory Commission, Arkansas Power & Light Company v. Federal Energy Regulatory Commission, Mississippi Power & Light Company v. Federal Energy Regulatory Commission, Louisiana Public Service Commission v. Federal Energy Regulatory Commission, Occidental Chemical Corporation v. Federal Energy Regulatory Commission, Reynolds Metals Company v. Federal Energy Regulatory Commission, Edwin Lloyd Pittman, Attorney General of the State of Mississippi v. Federal Energy Regulatory Commission, Arkansas and Missouri Congressional Delegations v. Federal Energy Regulatory Commission, Arkansas Public Service Commission v. Federal Energy Regulatory Commission, State of Arkansas v. Federal Energy Regulatory Commission, Mississippi Legal Services Coalition v. Federal Energy Regulatory Commission, City of New Orleans v. Federal Energy Regulatory Commission, Missouri Public Service Commission v. Federal Energy Regulatory Commission, Representative Webb Franklin v. Federal Energy Regulatory Commission, Jefferson Parish, Louisiana v. Federal Energy Regulatory Commission
808 F.2d 1525 (D.C. Circuit, 1987)
Towns of Alexandria v. Federal Power Commission
555 F.2d 1020 (D.C. Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
473 F.2d 1253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otter-tail-power-company-v-federal-power-commission-ca8-1973.