South Dakota Public Utilities Commission v. Federal Energy Regulatory Commission

668 F.2d 333
Court of Appeals for the Eighth Circuit·Decided November 25, 1981·No. No. 79-2020·Published·Cited by 6 cases

Opinions

HEANEY, Circuit Judge, with whom LAY, Chief Judge, and BRIGHT and McMILLIAN, Circuit Judges, join.

This matter is before the Court en banc on the petition of the South Dakota Public Utilities Commission to review an order of the Federal Energy Regulatory Commission (FERC). The order permitted the Northern Natural Gas Company (Northern) to depreciate certain equipment over a period of time shorter than its physical life on the theory that Northern’s supplies of natural gas would be exhausted prior to the time the equipment became obsolete. When the matter was first before a panel of this Court, 643 F.2d 504, we affirmed. We now reverse. We hold that the depreciation rates fixed by FERC are neither within the zone of reasonableness nor supported by substantial evidence. The rates appear to have been developed to support settlement rates agreed to by Northern and its wholesale customers rather than on the basis of natural gas reserves that are or will become available to Northern. The FERC substantially underestimated the natural gas reserves in Northern’s traditional supply areas, significantly understated the share of future reserves from those areas that Northern can be expected to purchase, and failed to give any weight to the fact that Northern has entered into several agreements which reasonably insure that it will receive substantial supplies of natural gas from nontraditional supply areas during the physical life of its equipment.

We reverse and remand to the FERC.

I. FACTUAL AND PROCEDURAL BACKGROUND

Northern is a major interstate transporter of natural gas with revenues exceeding [335]*335one billion dollars per year. Its pipelines move natural gas from the producing areas of Texas, Oklahoma and Kansas northward to Nebraska, Iowa, South Dakota, Minnesota and Wisconsin. Northern also owns producing and gathering equipment offshore in the Gulf of Mexico, in Montana and in Wyoming. For the purpose of computing depreciation, Northern’s properties are divided into four components, two of which are of primary importance here. The first is referred to as the South End supply area. The South End links Northern’s traditional major supply fields — the Hugoton-Anadarko and the Permian Basins — to the rest of the Northern system. The second major component is referred to as the Market Area which consists of the equipment north of the Kansas-Nebraska border.1

The primary issues in the proceedings below were whether the FERC properly estimated the reserves of natural gas available in areas capable of supplying Northern, and what share of those estimated reserves Northern would be able to acquire. The depreciation rates developed by the Staff were determined by a modified unit of production method which allocates depreciation costs on the basis of the volume of gas that is expected to flow through the facility (its useful life) rather than its physical life. The higher the estimates of natural gas supplies, the lower the depreciation rates should tend to be because it is more likely that the pipeline system will be a useful asset throughout its physical life. Conversely, the lower the estimated supplies, the higher depreciation rates should be because the pipeline system may become useless before it has physically deteriorated to the point where abandonment would be required. For example, in this case, under the FERC staff’s estimates, Northern’s facilities will be useful until approximately the year 2000. The physical life of the equipment, however, will not end until about the year 2011. In these circumstances, the FERC concluded that an increased rate of depreciation was appropriate. Therefore, the gravamen of this litigation, and the subject of nearly 7,000 pages in this voluminous record, is how much natural gas Northern can reasonably expect to have available to it for purchase between now and 2011.

The FERC2 order approved settlement agreements in two related rate cases filed by Northern. The first, RP 76-89, was filed on April 22, 1976. It requested rate increases of $71.7 million per year. The second, RP 77-56, was filed about a year later, while the earlier case was still pending. It requested additional rate increases of $109 million per year. Both were requests for general rate increases that eventually were narrowed to the single issue of proper rates of depreciation.3

[336]*336Negotiations between the FERC and Northern in RP 76-89 began in August, 1976. Thirty-one petitions for leave to intervene were granted; most of the petitioners were local utilities. Several state regulatory agencies were also represented including the South Dakota Public Utilities Commission and the Iowa State Commerce Commission. In October, 1976, the FERC approved Northern’s settlement rates, setting the composite depreciation rate at 4.48 percent and providing for rate increases of $57 million per year. South Dakota filed adverse comments on the settlement proposal. The FERC rejected South Dakota’s arguments. On application for rehearing, the Commission reversed itself, finding that the settlement was not supported by substantial evidence and remanded the case to the presiding administrative law judge for a hearing on the depreciation rates. A three-day hearing was held in January and February, 1978. In June, the ALJ found that neither the settlement rates nor those proposed by South Dakota were supported by substantial evidence. He held that Northern’s preexisting rates would remain in effect.

Meanwhile, RP 77-56 had reached a similar stage. Following discussions among Northern and other parties, a settlement was reached providing for increases of $63.6 million per year. South Dakota again opposed the settlement rates. A hearing was held in April of 1978. The parties agreed to waive the ALJ’s initial decision; and upon completion of the hearing, the proposed settlement and the record were certified to the FERC. Thus, the two cases consisting of identical parties and similar issues were pending before the FERC. In August, 1979, the Commission issued its order consolidating the two dockets and approving the settlement rates calling for increases of $120.6 million per year. South Dakota made an application for rehearing which was denied on October 4, 1979. This appeal followed.4

II. STANDARDS AND SCOPE OF REVIEW

The Natural Gas Act of 1938 provides the authority and the relevant standards to guide the FERC in its administrative function. Section nine of the Act, 15 U.S.C. § 717h, authorizes the FERC to determine “proper and adequate rates of depreciation” for natural gas companies within its jurisdiction. Section four, 15 U.S.C. § 717c, requires that the depreciation rates set by the FERC pursuant to section nine must be “just and reasonable.” See Memphis Light, Gas and Water Division v. Federal Power Commission, 504 F.2d 225, 230 n.19 (D.C.Cir.1974). A final Commission decision on a contested settlement must be supported by substantial evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

South Dakota Public Utilities Commission v. Federal Energy Regulatory Commission, 668 F.2d 333 (8th Cir. 1981).

668 F.2d 333 (South Dakota Public Utilities Commission v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related