Montana-Dakota Utilities Company v. Federal Energy Regulatory Commission

631 F.2d 557, 39 P.U.R.4th 287, 1980 U.S. App. LEXIS 14699
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 21, 1980
Docket79-1915
StatusPublished
Cited by5 cases

This text of 631 F.2d 557 (Montana-Dakota Utilities Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montana-Dakota Utilities Company v. Federal Energy Regulatory Commission, 631 F.2d 557, 39 P.U.R.4th 287, 1980 U.S. App. LEXIS 14699 (8th Cir. 1980).

Opinion

HEANEY, Circuit Judge.

The Montana-Dakota Utilities Company (MDU) petitions for review of a decision of the Federal Energy Regulatory Commission denying MDU’s request for a rate increase. The effect of that decision is to exempt MDU’s three jurisdictional customers from paying their small share of increased purchased gas costs even though they benefit from the purchased gas. We hold that the decision is contrary to law, is not supported by' substantial evidence on the record as a whole and is unjust and unreasonable.

I

MDU began its corporate existence in the 1930’s as a collection of small separate gas systems in Minnesota, Montana, North Dakota, South Dakota and Wyoming. Over the years, MDU has directly connected all but two of these systems by means of its certificated interstate pipeline. The system serving Sheridan, Wyoming, and the towns around it is one of these two. 1 Traditionally, MDU purchased gas for use in the Sheridan system from Northern Utilities, Inc., who, in turn, purchased gas from the Atlantic Richfield Company (ARCO). In 1974, however, Northern Utilities notified MDU that it would terminate the existing gas sales contract upon its expiration on March 31, 1975. This action was taken because MDU had acquired, for use in its interstate system, the rights to the ARCO gas.

Because MDU could not supply the Sheridan system directly from its interstate pipeline, MDU arranged a gas exchange agreement with Northern Utilities and its affiliate, Northern Gas Company. Under this arrangement MDU agreed to sell gas from its interstate system to Northern Gas Company. In'return, Northern Utilities agreed to continue to supply the Sheridan system with an equivalent amount of gas from its intrastate system. The exchange agreement took effect on April 16,1975, pursuant to a temporary certificate of public convenience and necessity issued by the Federal Power Commission, the predecessor agency of the Federal Energy Regulatory Commission (FERC or Commission). In 1975 and 1976, nearly all of Sheridan’s needs were met by the interstate system pursuant to the exchange agreement. In July of 1976, MDU secured, from the so-called “Powell II Unit” in Wyoming, another intrastate source of gas. Through an intrastate exchange agreement with Northern Utilities, *559 intrastate gas was then made available to the Sheridan system. On February 25, 1977, the Commission issued a permanent certificate for the interstate exchange agreement between MDU and Northern Gas Company. This certificate (No. CP75-227), however, authorized the exchange only to the extent necessary to make up deficiencies in the intrastate supplies available for use in the Sheridan system. Because the Powell II source has been more than sufficient to meet the Sheridan system’s needs since 1976, except for minor interruptions, no further substantial MDU-Northern Gas Company exchanges have been necessary. Current projections indicate, however, that significant exchanges will be required in future years.

The current problem arose because the price of the Powell II gas, which is not subject to federal regulation, increased at a substantially greater rate than the price of interstate gas. 2 In 1978, if this price increase had been absorbed by customers on the Sheridan system alone, their rates would have increased by seventy-nine cents per thousand cubic feet (Mcf). By contrast, if the increase had been spread to all of MDU’s customers, the rate increase would have been only ten cents per Mcf. As a consequence, MDU proposed to spread the cost of the high-priced intrastate gas among all its customers. 3 In order to accomplish this, MDU tendered for filing with the Commission a proposed Purchased Gas Adjustment (PGA) increase in the rates to be charged MDU’s customers within the Commission’s jurisdiction. After suspending them for one day, the Commission permitted MDU’s proposed rate increases to go into effect, subject to refund should they be found to be unlawful. 4 MDU’s subsequent PGA filings have been treated similarly by the Commission.

Following an investigation and hearing, an administrative law judge issued an initial decision determining that MDU should not be permitted to spread among its interstate jurisdictional customers the cost of the intrastate gas used in Sheridan, and ordered refunds of the increased amounts already collected by MDU. The judge gave two reasons for holding that MDU was not entitled to a PGA increase based on the price of gas used in Sheridan: (1) MDU’s interstate customers receive insufficient benefit from the high-priced Powell II gas to justify allocating the cost of that gas among all customers; and (2) MDU’s tariff permits only costs incurred by MDU’s “integrated system” to be charged to its interstate customers, and the Sheridan system is not part of that “integrated system.”

The Commission affirmed the initial decision for the two reasons stated by the administrative law judge. MDU challenges both of these grounds. In addition, MDU argues that the Commission was without power to order refunds in this case. 5

*560 II

Before we detail MDU’s specific challenges to the Commission decision, it is necessary to consider the scope of review that governs our decisions in cases of this type. The Commission argues that its determination of a just and reasonable cost allocation, and its interpretation of the terms of natural gas tariffs, are ordinarily “entitled to a considerable amount of deference.” Public Serv. Co. v. FERC, 600 F.2d 944, 954 (D.C.Cir.), cert. denied, 444 U.S. 990, 100 S.Ct. 520, 62 L.Ed.2d 419 (1979). We do not disagree. Even the opinions cited by the Commission, however, recognize that deference to the Commission’s expertise does not preclude all review. The Commission decision still must be supported by substantial evidence. See id.; State Corp. Comm’n v. Federal Power Comm'n, 206 F.2d 690, 698 (8th Cir. 1953), cert. denied, 346 U.S. 922, 74 S.Ct. 307, 98 L.Ed. 416 (1954). We turn now to consider whether the evidence of record supports the Commission findings.

1. Benefit to jurisdictional customers.

The administrative law judge found that allocating the costs of the Powell II gas systemwide would not be just and reasonable and would subject the jurisdictional customers to undue prejudice or disadvantage. The basis of the judge’s finding was that the jurisdictional customers received insufficient benefit from the Powell II gas to justify imposing its high price on all customers. In support of this position, the judge noted that MDU’s interstate system was not burdened with the Sheridan system load prior to issuance of the CP75-227 certificate authorizing the gas exchange. Nor has the interstate system been burdened by the Sheridan load since Powell II gas became available. “Returning MDU’s interstate system to the status quo ante,"

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Moorhead v. Minnesota Public Utilities Commission
343 N.W.2d 843 (Supreme Court of Minnesota, 1984)
Northern States Power Co. v. Hagen
314 N.W.2d 278 (North Dakota Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
631 F.2d 557, 39 P.U.R.4th 287, 1980 U.S. App. LEXIS 14699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montana-dakota-utilities-company-v-federal-energy-regulatory-commission-ca8-1980.