Otter Tail Power Company v. Federal Power Commission, and Village of Elbow Lake, Minnesota

429 F.2d 232
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 24, 1970
Docket19628_1
StatusPublished
Cited by10 cases

This text of 429 F.2d 232 (Otter Tail Power Company v. Federal Power Commission, and Village of Elbow Lake, Minnesota) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otter Tail Power Company v. Federal Power Commission, and Village of Elbow Lake, Minnesota, 429 F.2d 232 (8th Cir. 1970).

Opinion

VOGEL, Circuit Judge.

Following a hearing before the Federal Power Commission, Otter Tail Power Company petitions this court under § 313(b) of the Federal Power Act (16 U.S.C.A. § 824, et seq.) to review and set . aside an order requiring interconnection between petitioner and Elbow Lake, a municipal power company, issued pursuant to § 202(b) of the Act. Otter Tail maintains, inter alia, that this case is not governed by § 202(b), that the order is a deprivation of property without due process of law, and is not supported by the evidence. We disagree and affirm.

Otter Tail Power Company is an investor-owned utility serving primarily small towns located in western Minnesota and eastern North and South Dakota. Its business is almost exclusively retail as opposed to the wholesale transfer of power. Through the years Otter Tail has established a large integrated ■'System running the full gamut from initial production to final sale of electrical power combined with pool arrangements supplying emergency reserves.

In contrast, Elbow Lake is a small municipally-owned power producer serving only the limits of its political entity. Until 1966 Otter Tail served Elbow Lake, at which time the latter went into both production and sale of electrical power. Otter Tail opposed Elbow Lake’s decision in both the state and federal courts. 1

Elbow Lake supplies its consumers from two generators, each capable of producing 1250 KW’s, including a ten percent overload capacity. One generator is used while the other is idle. The peak load for the first year of operation was 1120 KW’s and the second year 1245. Thus Elbow Lake was dangerously close to eroding its firm power supply since any figure over the actual overload capacity would require the simultaneous use of both generators, causing a possi *234 ble loss of service should one malfunction during a peak period.

On these facts, the Federal Power Commission ordered installation of a temporary connection between Otter Tail and Elbow Lake for use only in case of such emergency. The connection, which was to last for one year, after final adjudication of this case, was to be made at Elbow Lake’s expense and the power paid for at wholesale rates. From this order Otter Tail takes exception.

Otter Tail first maintains the Federal Power Commission is without jurisdiction to order the connection under the Act. Their argument follows two separate but equally unacceptable paths. Petitioner first contends any proceedings in the instant case must be dealt with in compliance with § 202(c) of the Act rather than § 202(b), and secondarily argues that municipalities are not protected under § 202(b) of the Act. 2 *****8 We examine each contention separately.

Otter Tail argues § 202(b) only applies to permanent connections and a temporary connection may only be ordered under § 202(c). Otter Tail further contends that since Elbow Lake faces no emergency, its request to the Federal Power Commission for a temporary connection falls outside the range of authority granted the Commission by Congress under § 202(c). The contention fails to impress us. On its face, § 202(c) enables the Commission to react to a war or national disaster and order immediate interconnection of the facilities to maintain electrical service during such emergency. As such, the section enables the Commission to proceed without notice or hearing. On the other hand, § 202(b) applies to a crisis which is likely to develop in the foreseeble future but which does not necessitate immediate action on the part of the Commission. In the case at hand, Elbow Lake’s first year’s peak load was 1120 KW’s which increased to 1245 KW’s in its second year, just 5 KW’s short of their generators’ maximum overload capacity. In short, the present case is just the type of situation to fit into a § 202 (b) hearing rather than § 202(c). Otter Tail's argument that § 202(b) applies only to permanent and not temporary connections is not well taken. Suffice it to say that § 202(b) merely enumerates connections ordered by the Commission but does not specify either type or duration.

Otter Tail next challenges the Commission’s right to order any interconnection between a municipality and a private company under § 202(b) of the Act. The argument bottoms itself on the definitional section of the Act contained in Part I of the statute (16 U.S.C.A. § 796 (3) (4)) combined with the precise wording of § 202(b) and (f) of the Act (16 U.S.C.A. § 824a(b), 824a(f)). Otter Tail maintains that § 3(3) of the Act defines corporation to specifically exclude municipalities, while § 3(4) limits the definition of person to individuals or corporations. Otter Tail then points *235 to the fact that § 202(b) only mentions connections between “persons”, which implicitly excludes municipalities. Lastly, § 201(f) is alleged to plainly remove all political entities from coverage of Part II of the Act. 3

Petitioner finally directs our attention to legislative history to support its analysis. During the hearings on the Act both the Commissioner of the PPC and its solicitor testified that Part II of the Act would not require private companies to be forced to allow governmental agencies to use their facilities. Thus petitioner maintains any ambiguities in the language of the statute are clarified by the history.

The Fifth Circuit recently considered and rejected an identical argument. See, Florida Power Corporation v. Federal Power Commission, (May 1, 1970) 425 F.2d 1196. That court concluded that § 201(f) only limits the Federal Power Commission’s right to order wheeling by a private utility for a public entity. 4 That court, after examination of the entire legislative history, stated:

“ * * * we can find no support for the conclusion that municpalities which generate their own power were to be treated differently from non-generating municipalities concerning anything other than ‘wheeling’.”

The Fifth Circuit also relied upon New England Power Co. v. Federal Power Commission, 1 Cir., 1965, 349 F.2d 258, which case Otter Tail invites us to distinguish or disagree with. Therein, Judge Maris, with Chief Judge Aldrich and then Circuit Judge Burger concurring, stated for the court at page 262 of 349 F.2d:

“The contention that the Town of Shrewsbury is not a ‘person engaged in the * * * sale of electricity’ within the meaning of that phrase as used in section 202(b) is based upon the definition of ‘person’ in section 3 of Part I of "the Act, 16 U.S.C.A. § 796, which when read with the definition of ‘corporation’ in that section appears to exclude municipalities. The petitioners also rely on section 201(f) which states that ‘No provision in this Part shall apply to, or be deemed to include, the United States, a State or any political subdivision of a State, or any agency, authority, or instrumentality of any one or more of the foregoing, * * * unless such provision makes specific reference thereto.’ 16 U.S.C.A. § 824(f).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
429 F.2d 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otter-tail-power-company-v-federal-power-commission-and-village-of-elbow-ca8-1970.