New England Power Company v. Federal Power Commission

349 F.2d 258, 1965 U.S. App. LEXIS 4830
CourtCourt of Appeals for the First Circuit
DecidedJuly 21, 1965
Docket6434
StatusPublished
Cited by8 cases

This text of 349 F.2d 258 (New England Power Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Power Company v. Federal Power Commission, 349 F.2d 258, 1965 U.S. App. LEXIS 4830 (1st Cir. 1965).

Opinion

MARIS, Circuit Judge.

This is a proceeding in which New England Power Company (hereinafter called NEPCO) and Massachusetts Electric Company (hereinafter called Mass. Electric) have petitioned for the review of an order of the Federal Power Commission which requires NEPCO to enter into a contract with and to sell electric energy to the Municipal Light Department of the Town of Shrewsbury, Massachusetts, and cancels the contract under which such service has heretofore been rendered by Mass. Electric. NEPCO and Mass. Electric are subsidiaries of New England Electric System (hereinafter called NEES) and both are public utilities subject to the jurisdiction of the Federal Power Commission under Part II of the Federal Power Act, 16 U.S.C.A. § 824 et seq.

The Town of Shrewsbury, a municipal corporation of the Commonwealth of Massachusetts, has no generating facilities and has heretofore purchased electric energy from Mass. Electric for resale and distribution within the town through its own electric distributing system. Mass. Electric, which likewise owns no generating capacity, buys electric energy from NEPCO and sells it both at wholesale and retail in Massachusetts. The energy which Mass. Electric has heretofore sold to Shrewsbury has thus been received by Mass. Electric from NEPCO. The delivery has taken place at NEPCO’s substation in the Town of Shrewsbury where energy is received over NEPCO’s 69 kv lines, transformed down to 13.8 kv and delivered at NEPCO’s 13.8 kv terminals to Mass. Electric. The energy then passed into Mass. Electric’s adjacent switch station where it was delivered to Shrewsbury’s taps and carried by Shrews-bury across an alley to its new Worthing-ton Avenue substation. The total dis *260 tance between the 13.8 kv terminals of NEPCO from which the energy was delivered to Mass. Electric and Shrews-bury’s taps at which the town received the energy from Mass. Electric is less than 50 feet.

In 1962 the Town of Shrewsbury through its Municipal Light Department filed a complaint with the Federal Power Commission alleging that since 1958 it had been making efforts to obtain direct service from NEPCO without success and requesting the Commission to direct NEPCO to supply electric energy to the town on a nondiscriminatory basis. NEPCO filed an answer and motion to dismiss the complaint. The motion asserted that the Town of Shrewsbury was not a proper party to initiate the proceedings under Section 202(b) of the Federal Power Act nor a “person engaged in the transmission or sale of electric energy” within the meaning of that subsection and that it was neither necessary nor appropriate to order an additional interconnection since Shrewsbury was already physically interconnected with NEPCO through Mass. Electric. On May 2,1963 the Commission denied the motion to dismiss.

Hearings were then held before an examiner whose initial decision was filed on February 13, 1964. On July 27, 1964 the Commission filed its opinion and order. A concurring opinion was filed by two members of the Commission. The examiner had held that NEPCO should sell and deliver energy to Shrewsbury at 69 kv. The Commission upheld the examiner’s decision to the extent that it required NEPCO to' sell to Shrewsbury but ordered that delivery of energy be continued at 13.8 kv rather than 69 kv. The Commission concluded that direct sales by NEPCO to Shrewsbury would save the town over $42,000 a year and directly benefit its customers. Moreover, purchasing at NEPCO rates, the town would be able to compete for industrial loads with the surrounding areas where Mass. Electric was selling to industries at the same rate it was selling to Shrewsbury, and in some cases at lower special contract rates.

The Commission could see no reason why the middleman, Mass. Electric, should not be eliminated, noting that prevailing industry practice is for generating utilities to avoid resale middlemen where customers can be served directly. It found that Mass. Electric’s loss of income, which it regarded as of questionable relevance, would be relatively small, and Mass. Electric would be compensated by NEPCO for any continued use of its facilities. On the other hand NEPCO’s revenues would increase as a result of selling directly to Shrewsbury. In weighing these considerations the Commission concluded that a direct sale by NEPCO was dictated by the public interest.

In declining to order the delivery of energy at 69 kv the Commission recognized that the 69 kv connection would provide firm power, thus freeing Shrews-bury from any possible dependence upon back-up from Mass. Electric’s 13.'8 kv cables. It considered, however, that the existing interconnection was also adequate and, therefore, in the interests of economy and flexibility it ordered NEP-CO to serve Shrewsbury at 13.8 kv leaving it to NEPCO, as a matter of management judgment, to decide whether to arrange with Mass. Electric to use its existing facilities or to make a direct connection.

In reaching its conclusion the Commission stated that it was not determining whether other resale customers which Mass. Electric supplied with energy received from NEPCO were entitled to direct service from NEPCO. Any such request, it believed, would have to be considered on its own merits with particular reference to the functions of NEPCO and Mass. Electric in the NEES system and on a record not then before the Commission.

Concluding that the Town of Shrews-bury was a “person” within the meaning of Section 202(b) of the Federal Power Act and accordingly entitled to the benefits of that subsection the Commission *261 ordered NEPCO to sell electric energy to Shrewsbury under its standard wholesale rate at 13.8 kv and to enter into a standard form of contract with Shrews-bury for such service. The Commission’s order further provided that in effecting such sale NEPCO may employ the present facilities of Mass. Electric but shall be responsible for providing firm service in accordance with good utility practice and shall meet any costs necessary to do so. Shrewsbury was required to meet any costs necessary to increase the capacity of its facilities on a firm basis needed to effect the sale thus ordered. Also the Commission’s order cancelled the existing contract under which Shrewsbury had been receiving service from Mass. Electric. Finally, the Commission directed that jurisdiction of the proceeding be retained so that if Shrewsbury should experience delays in the future in obtaining any necessary increments of power or a higher voltage when necessary, which the experience of the past indicated might occur, an application to modify the order might be entertained and appropriate action taken promptly to assure adequate service.

On August 26,1964 NEPCO and Mass. Electric filed a joint application for rehearing. On the same day they submitted to the Commission proposals, to be effective October 1, 1964, for (1) a reduced NEPCO wholesale Rate W-4, (2) a new NEPCO Rate R-l, more expensive than W-4, for resale customers connected di-, reetly with NEPCO affiliates which received their energy from NEPCO, this rate being specifically made available to Shrewsbury, (3) the release by Mass. Electric of these customers from their present contracts upon the commencement of service by NEPCO, and (4) the providing by Mass. Electric to NEPCO of the use of capacity to make deliveries under Rate R-l and an agreement by NEPCO to compensate Mass. Electric for the value of the facilities utilized, which included $16,685.00 a year for the Shrewsbury facilities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
349 F.2d 258, 1965 U.S. App. LEXIS 4830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-power-company-v-federal-power-commission-ca1-1965.