Duke Power Co. v. Federal Energy Regulatory Commission

864 F.2d 823, 275 U.S. App. D.C. 1, 1989 U.S. App. LEXIS 88
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 6, 1989
DocketNo. 87-1781
StatusPublished
Cited by1 cases

This text of 864 F.2d 823 (Duke Power Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duke Power Co. v. Federal Energy Regulatory Commission, 864 F.2d 823, 275 U.S. App. D.C. 1, 1989 U.S. App. LEXIS 88 (D.C. Cir. 1989).

Opinion

Opinion for the Court filed by Circuit Judge MIKVA.

MIKVA, Circuit Judge:

The issues presented by this case are whether the respondent Federal Energy Regulatory Commission (“FERC” or “Commission”) properly interpreted certain agreements between petitioner and intervenors and whether the Commission properly retained jurisdiction to decide the dispute despite an arbitration clause in the agreements.

Petitioner Duke Power Co. (“Duke”) seeks review of Commission orders granting summary judgment for intervenors, 40 F.E.R.C. If 61,138 (1987), and denying rehearing, 41 F.E.R.C. 1161,060 (1987). Intervenors North Carolina Municipal Power Agency No. 1 (“Power Agency”), Piedmont Municipal Power Agency (“Piedmont”), North Carolina Electric Membership Corp. (“NCEMC”), and Saluda River Electric Cooperative, Inc. (“Saluda”) (collectively “complainants”) had alleged that Duke had improperly charged them costs booked to Account 407 of the Commission’s Uniform System of Accounts, 18 C.F.R. Part 101, Account 407. The Commission, relying in part on its policy not to allow such costs without prior approval, held that the charges were unauthorized and ordered Duke to refund the improperly charged amounts.

In this petition, Duke contends that the Commission should have submitted the dispute to arbitration, should not have granted summary judgment for complainants, and retroactively applied to Duke its policy regarding Account 407 costs. Because we find that the interconnection agreements (“agreements”) between Duke and complainants, on their face, do not permit recovery of Account 407 costs, we conclude that the Commission’s interpretation of the agreements was reasonable. We also hold that the Commission’s acceptance for filing of an agreement containing an arbitration [3]*3clause does not disable the Commission from the enforcement of filed rate schedules and that therefore the Commission properly retained jurisdiction in this case to resolve the instant dispute. Because our holdings do not depend on whether the Commission properly relied on its policy regarding Account 407 costs, we do not reach Duke’s retroactivity argument. Accordingly, we deny Duke’s petition for review.

I. Background

In 1978 and 1980, Duke and complainants entered into separate but substantially similar interconnection agreements relating to the supply of supplemental and reserve capacity and energy from Duke’s Catawba Nuclear Generating Station. The agreements, entered into after extensive negotiations, were part of larger overall arrangements among the companies for ownership and utilization of certain nuclear power facilities. The power exchange provisions in the agreements became effective on various dates between July 1983 and June 1985.

The agreements contain formula rate schedules that detail the methodology used to calculate the charges for capacity and energy sold under the agreements. The costs that Duke may recover for the services sold to complainants are contained in numerous exhibits that refer to specific accounts under the Commission’s Uniform System of Accounts. Costs properly charged by Duke to the specified accounts are recoverable from complainants; costs charged by Duke to accounts not so specified are not recoverable.

The agreements also contain an arbitration clause, which provides in relevant part:

any unresolved dispute arising out of or relating to the matters set forth in this Agreement shall be settled by arbitration in accordance with the procedures set forth in this Article * * *. In addition, disputes relating to the arbitration provisions of this Agreement, including without limitation disputes as to the applicability of such provisions to a particular dispute, shall be submitted for arbitration.

Duke Power Company/North Carolina Power Agency Number 1, Restated Interconnection Agreement § 24.1 (June 21, 1982) (emphasis added), Joint Appendix (“J.A.”) at 249.

The agreements were filed with the Commission and accepted by letter order. From the commencement of service to each complainant, Duke included charges for costs booked to Account 407 (“Amortization of property losses, unrecovered plant and regulatory study costs”) in its calculation of rates for supplemental and reserve capacity. These charges represented a share of the amortization of certain losses incurred by Duke, primarily in 1982 and 1983, in connection with its cancelled Perkins and Cherokee nuclear generating projects.

In 1983, when Power Agency first began to receive power under its interconnection agreement with Duke and Duke began to charge Power Agency for costs booked to Account 407, Power Agency objected on the ground that the agreement did not provide for the recovery of such costs. In January 1987, after unsuccessfully attempting to resolve the dispute informally, Power Agency filed a complaint and motion for summary judgment with the Commission, alleging that Duke violated the filed rate doctrine by improperly including Account 407 costs in its charges to Power Agency under their interconnection agreement.

In March 1987, Piedmont and NCEMC filed similar complaints and motions for summary judgment against Duke. In April 1987, Saluda, arguing that its interconnection agreement with Duke was identical in all material respects to those of Power Agency, Piedmont, and NCEMC, moved to intervene and join with the three complainants as a co-complainant in their respective complaint proceedings.

On August 3, 1987, the Commission consolidated the complaints and held that, because Commission policy was that Account 407 expenses were not recoverable absent prior Commission approval, and because [4]*4Duke had failed to obtain such approval, “submitting the instant dispute to arbitration would be a waste of time and resources and would only serve to delay our resolution of the matter.” 40 F.E.R.C. If 61,138, at 61,404 (1987). The Commission also found that “[t]he agreements are clear and unambiguous, and Duke’s formula rates do not provide for recovery of amounts booked to Account No. 407.” Id. Accordingly, the Commission declined to order arbitration, granted complainants’ motions for summary judgment, and ordered Duke to refund, with interest, the unauthorized charges — over $36 million — to complainants.

• On October 22, 1987, the Commission denied Duke’s petition for rehearing. 41 F.E.R.C. ¶ 61,060, at 61,174 (1987). This petition for review followed.

II. Discussion

The central issue in this case is whether Duke was authorized to recover from complainants costs booked to Account 407. Because we find that the Commission properly concluded that Duke was not so authorized, we deny Duke’s petition for review without ruling on the Commission’s policy regarding Account 407 costs and the attendant retroactivity issue.

A. Account 407 Costs

The Commission’s interpretation of a utility contract subject to its jurisdiction is entitled to deference if reasonable — i.e., if “amply supported both factually and legally.” Vermont Department of Public Service v. FERC, 817 F.2d 127, 134 (D.C.Cir.1987) (quoting Kansas Cities v. FERC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
864 F.2d 823, 275 U.S. App. D.C. 1, 1989 U.S. App. LEXIS 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duke-power-co-v-federal-energy-regulatory-commission-cadc-1989.