Tarpon Transmission Company v. Federal Energy Regulatory Commission, Trunkline Gas Co., Sun Exploration and Production Co., Intervenors

860 F.2d 439, 273 U.S. App. D.C. 354, 1988 U.S. App. LEXIS 14700
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 25, 1988
Docket88-1052
StatusPublished
Cited by31 cases

This text of 860 F.2d 439 (Tarpon Transmission Company v. Federal Energy Regulatory Commission, Trunkline Gas Co., Sun Exploration and Production Co., Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tarpon Transmission Company v. Federal Energy Regulatory Commission, Trunkline Gas Co., Sun Exploration and Production Co., Intervenors, 860 F.2d 439, 273 U.S. App. D.C. 354, 1988 U.S. App. LEXIS 14700 (D.C. Cir. 1988).

Opinion

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

STEPHEN F. WILLIAMS, Circuit Judge:

We deal here with a novel effort by a pipeline and its principal customer to provide for retrospective adjustment of rates to reflect current information about the cost of service and the amount and expected lifetime of the reserves to be transported. Finding the Federal Energy Regula *440 tory Commission not to have supported its interpretation of the controlling contract provision with any plausible theory, we grant the petition for review for want of reasoned decisionmaking and remand for further consideration by the Commission.

sjc Sj! SjS Sfc Hi

Tarpon Transmission Company owns 40.4 miles of pipeline located in the waters of the Outer Continental Shelf, off the Louisiana shore. The pipeline links reserves primarily owned by Trunkline Gas Company with the latter’s offshore pipeline, and Trunkline has been Tarpon’s principal customer since Tarpon began transporting natural gas in June 1978. 1 A Transportation Agreement, effective since February 15, 1977, specifies the terms of the relationship between Tarpon and Trunkline and, with its amendments, serves as Tarpon’s Tariff with the Commission.

The Agreement sets out to modify some of the conventional principles of cost-based ratemaking. Under the traditional approach, rates are based on projected volumes, with the aim that if service in fact proceeds at those volumes the projected revenue will cover the projected costs. For a pipeline in service, the estimation is derived from experience over a “test-year,” with certain adjustments. See 18 C.F.R. § 154.63(e)(2) (1988) (explaining the test-year methodology and adjustments). Where application of this method calls for a change in rates, the change is prospective only. Thus, if it appears in the third year of a project that the throughput has been and will likely be only half the anticipated level, entailing a higher unit rate (so long as all other things are unchanged), no adjustment will be made to enable the pipeline owner to catch up for the under-recovery of costs during the past period. Equally, of course, no retrospective adjustments will be made for excess recoveries due to unexpectedly high volumes. The rates for future volumes transported will, however, reflect the new information.

Article X of the Agreement establishes a special methodology. Section 10.1 establishes a “life-of-the-reserves” method for setting the “initial unit rate.” The total cost of service for the estimated life of the reserves (including operating and maintenance expenses, taxes, depreciation and return on investment) is estimated and then divided by the estimated total reserves. This yields the initial rate per thousand cubic feet (“Mcf”). It is not clear whether this aspect of the parties’ arrangement differs significantly from what FERC would typically require, and in any event it is not in dispute.

The clear innovation lies in Section 10.5, which governs changes in rates:

10.5 Rate Adjustment. Trunkline or Tarpon upon the giving of ninety (90) days written notice to the other prior to the end of the second (2nd), fourth (4th), sixth (6th) and eighth (8th) years of the primary term hereof, may request that the unit rate currently being utilized to determine the monthly charge and other charges or credits be decreased or increased to reflect changes in costs and/or gas reserves connected to the system. Such rate redetermination shall be based upon a cost of service for the entire life of the reserves transported and to be transported pursuant to this Agreement and other agreements Tarpon may enter into for the utilization of subject facilities, taking into consideration actual revenues collected to date or to be collected prior to the effective date of such unit rate charge; and such rate shall be calculated in the same manner as used in the calculation of the initial unit rate hereunder.

When Tarpon began operations in 1978, reserves were estimated to have a life of 8.25 years and a volume of 103,573,000 Mcf. These figures and other data as to *441 Tarpon’s costs yielded an initial rate of 31.64 cents per Mcf. The Commission approved the rate but required Tarpon to initiate a new rate proceeding within three years. See Tarpon Transmission Co., 59 FPC 1516, 1519 (1977).

Accordingly, in 1981 Tarpon and Trunk-line set a new rate of 18.10 cents per Mcf. For no apparent reason, they did not employ Section 10.5, but rather the traditional test-year method. The Commission approved the new rate but again required Tarpon to file a notice of rate change within three years.

On May 25, 1984 Tarpon filed a notice of a rate change with FERC, proposing to reduce its rate to 16.88 cents per Mcf. Again Tarpon used the test-year approach rather than that of Section 10.5. Joint Appendix (“J.A.”) 473. 2 On this occasion, however, the Commission found that Tarpon had not demonstrated that the proposed rate was just and reasonable as required by the Natural Gas Act, 15 U.S.C. § 717c(a) (1982). It allowed the rate to take effect on July 10, 1984, subject to a refund if Tarpon could not prove the rate was just and reasonable in subsequent rate proceedings. Tarpon Transmission Co., 28 FERC H 61,027 (1984). Dispute over details in the application of the traditional method were mooted, however, when all concerned concluded that Section 10.5 of the Agreement should control. 3

An administrative law judge accepted the interpretation of Section 10.5 advanced by Tarpon and ruled that the proposed rate of 16.88 cents was just and reasonable. Tarpon Transmission Co., 32 FERC ¶ 63,020 (1985). Although the Section 10.5 approach (as construed by Tarpon) yielded a rate of about 25 cents per Mcf, 4 Tarpon claimed only the rate originally asserted in its 1984 Notice of Rate Change, and accordingly that was what the AU approved. Here, too, Tarpon claims only the 16.88 cents.

The Commission’s staff filed exceptions to the AU’s decision, and the Commission reversed. Tarpon Transmission Co., 41 FERC If 61,044 (1987). Although the Commission agreed that the rate should be determined according to Section 10.5, it accepted the staff’s interpretation of the contract provision. Id. at 61,136. Under this interpretation, Tarpon’s proposed rate was not just and reasonable, and FERC ordered Tarpon to recalculate the rate using the staff’s interpretation. That approach yielded a rate of 4.02 cents per Mcf.

The Commission denied Tarpon’s motion for a rehearing, Tarpon Transmission Co., 42 FERC 11 61,050 (1988), and this appeal followed.

Scope of Review

Although the interpretation of Section 10.5 is a matter of contract law, we nonetheless owe deference to the Commission’s view. In National Fuel Gas Supply v. FERC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fairless Energy, LLC v. FERC
77 F.4th 1140 (D.C. Circuit, 2023)
Midland Cogn Vntrs v. FERC
133 F.3d 34 (D.C. Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
860 F.2d 439, 273 U.S. App. D.C. 354, 1988 U.S. App. LEXIS 14700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tarpon-transmission-company-v-federal-energy-regulatory-commission-cadc-1988.