Williams Natural Gas Co. v. Federal Energy Regulatory Commission

3 F.3d 1544, 303 U.S. App. D.C. 260
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 21, 1993
DocketNos. 90-1545, 91-1543
StatusPublished
Cited by1 cases

This text of 3 F.3d 1544 (Williams Natural Gas Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Natural Gas Co. v. Federal Energy Regulatory Commission, 3 F.3d 1544, 303 U.S. App. D.C. 260 (D.C. Cir. 1993).

Opinion

Opinion for the court filed by Circuit Judge BUCKLEY.

BUCKLEY, Circuit Judge:

In late 1988 and early 1989, Williams Natural Gas Company, a pipeline, paid $18.7 million to its suppliers under four separate settlement agreements. Williams sought to obtain full recovery of these costs by including them in its purchased gas adjustment (“PGA”) filings. The Federal Energy Regulatory Commission determined, however, that two of the settlements included amounts paid to buy out Williams’s take-or-pay liabilities, and hence that the $9.4 million in costs attributable to these settlements could not be recovered through the PGA mechanism. Williams now challenges the Commission’s ruling on a number of grounds. We hold that FERC properly interpreted the disputed settlements as including both purchased gas and take-or-pay buyout costs, that FERC’s policy of denying PGA recovery for the full amount of such settlements when the contract does not specifically state the portion allocable to purchased gas is consistent with section 601(c) of the Natural Gas Policy Act and Commission precedent, and that FERC’s policy may be applied retroactively to Williams’s settlements. Accordingly, we deny the petitions for review.

I. BACKGROUND

A. Legal Framework

At the core of the present dispute is the difference between two mechanisms through which natural gas pipelines may recover their costs: the PGA procedure and Order No. 500.

The Federal Power Commission (“FPC”), FERC’s predecessor, devised the PGA procedure in 1972 “to reduce the administrative burdens of dealing with rapid fluctuations in the prices that natural gas producers were charging pipelines.” Laclede Gas Co. v. FERC, 997 F.2d 936, 938 (D.C.Cir.1993); see Purchased Gas Cost Adjustment Provision in Natural Gas Pipeline Companies’ FPC Gas Tariffs, 47 F.P.C. 1049 (1972). It enables pipelines to alter the rates they charge their customers without having to undergo a full rate proceeding under section 4 of the Natural Gas Act (“NGA”), 15 U.S.C. § 717c (1988). If a PGA clause is included in a pipeline’s tariff, the pipeline must document its purchased gas costs in periodic filings with the Commission. Any changes in these costs may then be passed along in the form of higher or lower rates. For purposes of the present case, the critical fact about the PGA procedure is that it enables pipelines to obtain full (i.e., 100 percent) recovery of their purchased gas costs.

Order No. 500 was designed to address a different problem. Specifically, it is common for contracts between pipelines and natural gas producers to contain take-or-pay clauses. These require the pipeline to take a designated amount of gas at a specified price, or pay for the gas (or a specified percentage thereof) even if it elects not to take the full amount. Due in part to FERC’s encouragement, many pipelines were locked into long-term, high-price gas purchase contracts including take-or-pay provisions in the early 1980s when the price of gas declined dramatically. See Associated Gas Distribs. v. FERC, 824 F.2d 981, 995-96, 1021 (D.C.Cir.1987). Accordingly, the pipelines sought to “buy out” or “buy down” their take-or-pay liabilities by entering into settlement agreements with their suppliers. Under Order No. 500’s “equitable sharing mechanism,” pipelines may pass these take-or-pay buyout costs along to their customers, but only if they agree to absorb between 25 and 50 percent of the costs. See Regulation of Natural Gas Pipelines After Partial Wellhead Decontrol, 52 Fed.Reg. 30,334, 30,338, 30,341 (Aug. 14, 1987); see also Public Utilities Comm’n of Cal. v. FERC, 988 F.2d 154, 157-[1547]*154758 (D.C.Cir.1993); Associated Gas Distribs. v. FERC, 893 F.2d 349, 353 (D.C.Cir.1989).

The fact that there are two distinct cost recovery mechanisms can create classification problems for certain types of settlement payments. It is clear that settlement payments relating solely to take-or-pay liabilities must be recovered under Order No. 500, see Regulatory Treatment of Payments Made in Lieu of Take-or-Pay Obligations, 50 Fed. Reg. 16,076, 16,077 (Apr. 24, 1985) (declaring that take-or-pay buyout payments do not qualify as the type of “purchased gas costs” that may be recovered under the PGA regulations), while payments that are exclusively intended to settle disputes over the price of gas already taken are eligible for PGA recovery, see Columbia Gas Transmission Corp., 30 F.E.R.C. ¶ 61,224, at 61,444 (1985).

Difficulties arise, however, in cases involving broader settlements that resolve disputes over both. take-or-pay liabilities and purchased gas pricing issues. The Commission first addressed the issue of such “comprehensive” settlements in a series of decisions issued in 1989, one of which involved Williams. These decisions made clear that “[a]ll onetime, nonreeoupable costs to reform or terminate producer-supplier problem contracts that include, but are not necessarily limited to, the modification or elimination of take-or-pay provisions are eligible for passthrough under the procedures established by Order No. 500.” El Paso Natural Gas Co., 47 F.E.R.C. ¶ 61,149, at 61,460 (1989); see also Williams Natural Gas Co., 47 F.E.R.C. ¶ 61,155, at 61,504 (1989).

The Commission’s 1989 rulings left open the question whether comprehensive settlement payments, or at least the portion relating specifically to purchased gas pricing issues, could be included in a pipeline’s PGA filings. A year later, however, the Commission did address that issue in ANR Pipeline Co., 50 F.E.R.C. ¶ 61,372 (1990). In ANR, the Commission permitted a pipeline to include in its PGA filings an amount that was paid in a comprehensive settlement, but which was “separately identified” in the contract as being intended to settle a pricing dispute concerning gas already taken. See id. at 62,125. FERC cautioned, however, that it would not permit PGA passthrough in cases in which the amount paid for purchased gas was not separately stated; instead, “the costs of settling pricing disputes in such contexts are recoverable exclusively through Order No. 500 filings.” Id. The Commission reasoned that, when the amounts are not identified on the face of the contract, “it is not possible to distinguish reliably between the costs of settling pricing disputes and the costs of settling take-or-pay liabilities or reforming contracts.” Id. We will refer to the principle announced in this decision as the “ANR rule.”

B. The Facts

In December 1988 and January 1989, Williams executed four separate settlement agreements under which it paid its suppliers a total of $18.7 million. After a series of preliminary disputes that are not relevant here, Williams amended its March 1, 1990, PGA filing to include the payments made under the settlement agreements as purchased gas costs. Williams asserted that inclusion of the settlement costs in the PGA filings was consistent with ANR

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
3 F.3d 1544, 303 U.S. App. D.C. 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-natural-gas-co-v-federal-energy-regulatory-commission-cadc-1993.