United Gas Pipe Line Company v. Federal Energy Regulatory Commission

597 F.2d 581, 1979 U.S. App. LEXIS 13745
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 22, 1979
Docket78-1091
StatusPublished
Cited by13 cases

This text of 597 F.2d 581 (United Gas Pipe Line Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Gas Pipe Line Company v. Federal Energy Regulatory Commission, 597 F.2d 581, 1979 U.S. App. LEXIS 13745 (5th Cir. 1979).

Opinion

JOHN R. BROWN, Chief Judge:

In this case United Gas Pipe Line Company (United) and various intervenors 1 contend that the Federal Energy Regulatory Commission (FERC) has acted arbitrarily in denying recovery of costs that they "should reasonably be able to pass on to their customers. We agree that the challenged Commission action 2 is unreasonable and, therefore, reverse.

The Commission Sets The Stage: Background

This dispute began when — in the context of a critical natural gas shortage — the Commission 3 issued Order 410, 4 which announced the initiation of its advance payment program. Under this program interstate pipeline companies advanced funds, interest free, to producers for exploration and development of natural gas reserves. The producers, in turn, committed the gas to be developed with those funds to the individual pipeline companies that had made the advances and thus to the interstate market. To encourage the pipelines to participate and to offset the resultant costs of the program, the Commission allowed them to include the costs of the advance payments in their rate base. 5

In doing so the Commission explained that this method of accounting would have “encouraging effects” on gas supply. 44 FPC at 1143. It further stated that,

particularly at the present time when there are indications of a natural gas shortage, it is not in the public interest for pipeline companies to bear the costs of assuring themselves and their customers a future supply of natural gas. We believe that, when it is necessary for pipeline companies to make advance payments in order to contract for gas supplies, it is equitable that the companies should earn on the amounts advanced.

Id. at 1144. 6 Order 410 and its companion *583 orders, 7 which governed the program from its inception through December 28, 1972, were affirmed by the Circuit Court of Appeals for the District of Columbia as a “justifiable experiment in the continuing search for solutions to our Nation’s critical shortage of natural gas.” Public Serv. Comm’n of New York v. FPC, 1972, 151 U.S.App.D.C. 307, 317, 467 F.2d 361, 371 (New York Comm’n I). 8

In late December of 1972 the Commission issued its Order 465, 9 which extended the advance payment program for one year, up to Dec. 31, 1973, and made specific changes regarding which costs could appropriately be included in rate base and the schedule for repayment of advances. Following a round of comments from various producers, pipelines, and affiliated companies, the Commission again extended the program, up to Dec. 31, 1975, in its Order 499. 10 It also announced a general policy to deny rate base treatment for advances “in excess of costs for exploration and development, and production incurred by the producer within a reasonable time from the date such amounts advanced are included in the pipeline’s rate base.” 11 Before Order 499 the only guidance the Commission had offered provided that advances would be allowed in rate base if found reasonable and appropriate. 12

Upon review of Orders 465 and 499 the District of Columbia Circuit held that the Commission’s action did not “amoun[t] to the kind of evaluation of the experience under the programs [required] to discharge [its] responsibility ‘to determine [as instructed in New York Comm’n I, 467 F.2d at 371] whether its justifying objectives are being satisfactorily met at an acceptable level of ultimate economic cost to the nation’s gas consumers.’ ” 167 U.S.App.D.C. at 110, 511 F.2d at 348. 13 The Court thus *584 remanded the proceeding for further consideration, but allowed the advance payment program to remain in effect pending Commission action on remand. In response to the District of Columbia’s mandate, the Commission issued its Order on Remand, 14 terminating the program prospectively as of December 31, 1975.

The Star Makes Her Entrance: United’s Case

United participated in the Commission’s advance payment program 15 and, in various rate proceedings, applied for rate base treatment of the costs of making advances. The proceedings in question here concerned costs incurred from April 6, 1974, through May 19, 1975 (the period). Settlement negotiations among United, the Commission staff, and United’s customers ultimately resulted in a Stipulation and Agreement pursuant to which United’s rates and refunds were based on United’s actual operating experience during such period. 16 After reviewing the settlement agreement, the Commission issued Order No. 815, 17 in which it approved the agreement, but only with the addition of significant modifications. One of these was the denial of rate base treatment for $23,380,650 of the $79,238,960 of outstanding advances United carried during the period. Reasoning that all advances spent more than 30 days after inclusion in rate base (front-end advances) were “presumptively extravagant” 18 the Commission found that it would be unjust and unreasonable to pass the costs on to United’s customers.

United sought rehearing on Opinion No. 815, thus prompting the Commission’s issuance of Opinion No. 815-A. In response to United’s argument that the Commission had elevated its “presumption” to a retroactively applied legal standard, the Commission merely stated that

[o]ur conclusion that a portion of United’s advance payments at issue in this proceeding are unreasonable and inappropriate costs for rate making purposes reflects nothing more than our judgment on the record that the carrying cost of the advances challenged in this case should not be borne by United’s consumers. The Commission has not announced a new rule and applied it retroactively.

Apparently distinguishing between the meaning of “reasonable” in regulatory and business contexts, the Commission further added that

[t]he ‘reasonable and appropriate’ standard applied here is simply a restatement of this Commission’s statutory obligation to review all pipeline expenditures in order to determine their prudence. We do not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Soffar v. Dretke
391 F.3d 703 (Fifth Circuit, 2002)
Office of Consumers' Counsel v. Federal Energy Regulatory Commission, Great Plains Gasification Associates, Tennessee Gas Pipeline Co., Columbia Gastransmission Corp., Transcontinental Gas Pipe Line Corp., Natural Gas Pipelineco. Of America, Madison Gas and Electric Co., Wisconsin Power and Light Co., u.s.department of Energy, Michigan Wisconsin Pipeline Co., General Motors Corp.,public Service Commission of New York, Intervenors. General Motors Corporation v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Columbia Gas Transmission Corp., Transcontinentalgas Pipeline Corp., Natural Gas Pipeline Co. Of America, Madison Gas Andelectric Co., Wisconsin Power and Light Co., U. S. Department of Energy,michigan Wisconsinpipeline Co., Public Service Commission of New York, Office of Consumers'counsel of Ohio, Gas Research Institute, Great Plains Gasification Associates,intervenors. The Public Service Commission of the State of New York v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Columbia Gas Transmission Corp., Transcontinentalgas Pipe Line Corp., Natural Gas Pipeline Co. Of America, Madison Gas Andelectric Co., Wisconsin Power and Light Co., U. S. Department of Energy,general Motors Corp.,michigan Wisconsin Pipeline Co., Office of Consumers' Counsel of Ohio, Gasresearch Institute, Great Plains Gasification Associates, Intervenors. The State of Michigan v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Columbia Gas Transmission Corp., Transcontinentalgas Pipe Line Corp., Natural Gas Pipeline Co. Of America, Madison Gas Andelectric Co., Wisconsin Power and Light Co., U. S. Department of Energy,michigan Wisconsinpipeline Co., General Motors Corp., Public Service Commission of New York,office of Consumers' of Ohio, Gas Research Institute, Great Plains Gasificationassociates, Intervenors
655 F.2d 1132 (D.C. Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
597 F.2d 581, 1979 U.S. App. LEXIS 13745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-gas-pipe-line-company-v-federal-energy-regulatory-commission-ca5-1979.