Natural Gas Pipeline Company of America v. Federal Energy Regulatory Commission

590 F.2d 664
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 13, 1979
Docket77-1958
StatusPublished
Cited by10 cases

This text of 590 F.2d 664 (Natural Gas Pipeline Company of America v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natural Gas Pipeline Company of America v. Federal Energy Regulatory Commission, 590 F.2d 664 (7th Cir. 1979).

Opinion

HARPER, Senior District Judge.

This is a proceeding to review two unreported orders of the Federal Power Commission (Commission) issued in Natural Gas Pipeline Company of America, Docket No. RP73-110: “Order Modifying Initial Decision”, issued June 3, 1977 (R. 355-360), and “Order on Rehearing and Denying Intervention”, issued on August 11,1977 (R. 397-404), excluding from rate base treatment certain advance payments made by appellant to various producers of natural gas. The procedural history of this appeal is as follows:

On September 4, 1974, a settlement agreement governing the rates of Natural Gas Pipeline Company of America (Natural) in Docket No. RP73-110 was approved by Commission order. Articles V and XI of that settlement agreement permitted Natural to make periodic rate changes during the period the RP73-110 rates were in effect (December 1, 1973, through November 30, 1974) and to reflect in its rate changes the level of advance payments for gas made by Natural to producers. Such advance payment “tracking” filings were to become effective without suspension, but subject to refund as to advances not conforming to the relevant rulemaking orders of the Commission on advance payments.

On July 18,1974, Natural tendered such a tracking filing to become effective September 1, 1974, which reflected among other things three advances to Burmah Oil Development, Inc. (Burmah) totalling $4,699,-000.00 and one advance to Mitchell Corporation (Mitchell) of $2,000,000.00.

On October 4, 1974, the Commission issued an order setting for hearing the question of whether these advances could properly be included in Natural’s rates. A hearing was held on March 17,1975. The Initial Decision of Presiding Administrative Law Judge Benken was issued June 18, 1975. This decision allowed rate base treatment only for advances expended by the producer as of the effective date of Natural’s rate change. Natural filed exceptions to the initial decision.

On June 3, 1977, the Commission issued an order that only advances expended by the producer within thirty days after the effective date of the rate change could be reflected in Natural’s rate. Application of this rule had the effect of excluding from rate base treatment all but $992,000.00 of the approximately seven million dollars in advances made by Natural to the gas producers, Burmah and Mitchell.

*666 On July 1, 1977, Natural applied for rehearing of the June 3rd order. By order issued August 1, 1977, the Commission denied rehearing.

The court’s jurisdiction of this matter is founded upon Section 19 of the Natural Gas Act, 15 U.S.C. § 717r.' Section 19 provides for review of orders of the Commission by filing a petition for review in the Court of Appeals, in which the natural gas company to which the order relates is located, within sixty days after the Commission order on rehearing is issued. Natural is a natural gas company subject to the jurisdiction of the Commission having its principal place of business in Chicago, Illinois. The orders in the proceeding below related to natural gas rates charged by Natural which are subject to the Commission’s jurisdiction. Natural duly applied for rehearing. The Commission’s order on rehearing was issued August 1, 1977, and Natural filed its petition for review September 21, 1977, thus complying with the sixty-day requirement.

Section 19(b) of the Natural Gas Act provides that in review of Commission orders by the courts of appeals “[t]he finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive.” 15 U.S.C. § 717r(b) (1970).

In the Permian Basin Area Rate Cases, 390 U.S. 747, 791-2, 88 S.Ct. 1344, 1373, 20 L.Ed.2d 312, the Supreme Court defined the responsibilities of reviewing courts charged with the duty of applying the substantial evidence standard:

“It follows that the responsibilities of a reviewing court are essentially three. First, it must determine whether the Commission’s order, viewed in light of the relevant facts and of the Commission’s broad regulatory duties, abused or exceeded its authority. Second, the court must examine the manner in which the Commission has employed the methods of regulation which it has itself selected, and must decide whether each of the order’s essential elements is supported by substantial evidence. Third, the court must determine whether the order may reasonably be expected to maintain financial integrity, attract necessary capital, and fairly compensate investors for the risk they have assumed, and yet provide appropriate protection to the relevant public interests, both existing and foreseeable. The court’s responsibility is not to supplant the Commission’s balance of these interests with one more nearly to its liking, but instead to assure itself that the Commission has given reasoned consideration to each of the pertinent factors.”

We begin with a brief review of the advance payment program. Beginning in 1970, in response to an increasing shortage of natural gas, the Commission published and encouraged a program of advances by interstate pipelines to producers for the purpose of exploration for, and development of additional supplies of natural gas, with the stipulation that under certain conditions the advance payments could be included in the rate base which the pipeline uses to calculate the price that consumers will be charged for the gas.

The first of the five advance payment orders, Order No. 410, was issued by the Commission on October 2, 1970, 44 F.P.C. 1142 (1970). It was followed on January 8, 1971, by Order No. 410-A, which provided interim rate base treatment for “advances by pipelines to independent producers for exploration and lease acquisition costs.” 45 F.P.C. 135 (1971). The third advance payment order, No. 441, was promulgated on November 10,1971, and it modified the two prior orders, with the effect of eliminating rate base treatment for advances made under certain circumstances. 46 F.P.C. 1178 (1971). As an example, the Commission determined that rate base treatment would be denied to all advances for exploration and lease acquisition. 46 F.P.C. at 1180. A second mandate of Order 441 was that the advance payment program was to be limited to the period ending December 31, 1972. 46 F.P.C. at 1180-81.

In March of 1972, the advance payment program received judicial endorsement in the case of Public Service Commission for the State of New York v. F.P.C., 151 U.S. *667 App.D.C. 307, 309, 467 F.2d 361, 363 (1972). The court discussed the theory behind giving the advance payment rates base treatment:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baltimore Gas & Electric Co. v. Public Service Commission
501 A.2d 1307 (Court of Appeals of Maryland, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
590 F.2d 664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natural-gas-pipeline-company-of-america-v-federal-energy-regulatory-ca7-1979.