Tennessee Valley Municipal Gas Association v. Federal Power Commission, Alabama-Tennessee Natural Gas Company, Intervenor

470 F.2d 446, 152 U.S. App. D.C. 298, 1972 U.S. App. LEXIS 7036
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 25, 1972
Docket71-1698, 71-1728
StatusPublished
Cited by19 cases

This text of 470 F.2d 446 (Tennessee Valley Municipal Gas Association v. Federal Power Commission, Alabama-Tennessee Natural Gas Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Valley Municipal Gas Association v. Federal Power Commission, Alabama-Tennessee Natural Gas Company, Intervenor, 470 F.2d 446, 152 U.S. App. D.C. 298, 1972 U.S. App. LEXIS 7036 (D.C. Cir. 1972).

Opinion

WILKEY, Circuit Judge:

This is a proceeding to review, orders of the Federal Power Commission in two related rate cases. 1 Since the rates involved have been under continuous challenge since 7 June 1966, there has been ample opportunity to develop procedural complexity defying easy summary. However, a limited number of FPC orders constitute the focus of the substantial disputes in this case.

On 17 October 1969 the FPC dismissed a complaint under Section 5(a) of the Natural Gas Act, 2 claiming that existing rates for natural gas were excessive, brought by the Tennessee Valley Municipal Gas Association (“Association”) against its supplier, Alabama-Tennessee Natural Gas Company (“AT”). Dismissal was on the grounds that the record was too “stale” to form the basis for a prospective ruling and that it appeared “highly conjectural that initiation of a new Section 5 proceeding at this time would be in the public interest.” 3

Apparently motivated by a desire to avoid judicial review, 4 on 6 February *450 1970 the FPC vacated its dismissal and reopened the proceedings to update the record and compile figures from a more recent test period. 5 This Section 5 proceeding was finally resolved on 5 May 1971. 6

While in one sector defending in the Section 5 proceeding, in another AT went over to the offensive by filing for a rate increase under Section 4 of the Act (based on its cost of service during the 12 months ending 31 May 1970). Under the authority of Section 4 increased rates went into effect, contingent on a refund to the extent that they were later found to be excessive, on 17 March 1971. By stipulation of the parties, the rate of return decision in the Section 5 ease was incorporated in the Section 4 proceeding by an FPC order of 18 May 1971. 7

I. Retroactivity

The Association’s primary contention is that the FPC erred in its dismissal of the Section 5 action on 17 October 1969, and further, that whatever rate is found legal must be applied retroactively as of the day that error was made. We agree that the dismissal on 17 October 1969 was erroneous; we disagree with the Association as to the appropriate measure of retroactive relief.

A. Legal Error

The Commission’s action on 17 October really consisted of two distinct steps. First, the FPC decided that it could not, in 1969, set fair prospective rates on the basis of a test period from 1966. While the FPC has in the past based rate decisions on aged records, and time alone does not automatically render a record “stale,” 8 we cannot say that there was legal error in the decision that the record would have to be updated to reflect, at least, changes in the money market. Although the first examiner had actually considered this factor, his decision preceded that of the Commission by more than a year. Thus, while the other reasons given by the Commission for its decision on staleness are less persuasive, 9 we disagree with the Association’s argument that the FPC should have decided solely on the basis of the three-year-old record presented at that time. 10

The second part of the FPC’s action on 17 October 1969 was its decision to dismiss the Section 5 proceeding rath *451 er than to reopen the matter for further investigation and updating of the record. Reopening for further hearings was precisely what the Commission later chose tp do when its decision was challenged in this court. We hold that failure to do so on 17 October 1969 was legal error.

In its order of 5 May 1971 the FPC says that the “predicate of the Association’s request for retroactive rate reduction has not been established [1] “because we do not confess to have committed legal error in ordering the dismissal, and [2] because the first examiner’s decision issued in this proceeding contained the finding that Alabama-Tennessee’s rates were not excessive.” 11 However, as to [1], the dismissal, the Commission’s vacation of its dismissal seems to us very close to an admission that it did err in refusing to order reopening and updating, of an admittedly stale record, on 17 October 1969.

The error here is further established by the FPC’s own articulated ground [2] for the dismissal. In its order, the Commission noted that reopening would require such extensive updating as to approximate an entire new proceeding. It went on to say that it appeared “highly conjectural” that such a new proceeding would be in the public interest. 12 This latter finding could only have been based on the Commission’s conclusion that AT’s rates were in fact fair, an approval of the examiner’s finding. Since we cannot believe the FPC omniscient, that conclusion must have been founded on the very record which the Commission neither adopted nor rejected and which it in fact held not to form a valid basis for any decision at all! While it may be ingenious to rely on a record, and ignore it as stale, all within the terms of the same order, it is also clear legal error to do so.

B. Mootness and Reviewability

AT counters with the contention that, no matter how erroneous, the dismissal on 17 October 1969 cannot be reviewed here because it was in fact vacated by the FPC and that action was appealed to this court. It is true that this court dismissed the Association’s petition for review of the dismissal once a reopened investigation had begun.

However, that petition to this court, on 16 January 1970, was based exclusively on a challenge to the FPC’s ruling that the record could not be updated. Once the Commission started an updating proceeding, that claim necessarily became moot. Quite distinct is the further claim now advanced here: that the FPC erred in not ordering (in its 5 May and 18 May 1971 orders) retroactive application of the just rate to put the Association in the position it would have held absent the Commission’s first error. This latter claim could not even be properly raised until the Commission entered a final and reviewable order in the rate proceeding itself. This court’s dismissal of the first petition to review could not, therefore, have either dealt with a claim for retroactive relief or established that such a claim was mooted by the FPC’s vacation of its own dismissal of the Section 5 claim.

As this court had given leave to do, the Association on 15 April 1971 moved to reinstate its petition (of 16 January 1970) to review the 17 October 1969 dismissal on the ground that the FPC had not expedited its decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farmland Industries, Inc. v. Kansas Corporation Comm'n
37 P.3d 640 (Court of Appeals of Kansas, 2001)
Kansas Pipeline Partnership v. Kansas Corporation Comm'n
941 P.2d 390 (Court of Appeals of Kansas, 1997)
Transwestern Pipeline Company v. Federal Energy Regulatory Commission, the Public Utilities Commission of the State of California, Process Gas Consumers Group, Southern California Gas Company, El Paso Natural Gas Company, Pacific Gas and Electric Company, Texas Eastern Transmission Corporation, the Kansas Power and Light Company, Southwest Gas Corporation, Williams Natural Gas Company, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Southern California Gas Company, Southwest Gas Corporation, Pacific Gas and Electric Company, Williams Natural Gas Company, Public Utilities Commission of the State of California, El Paso Natural Gas Company, Citizens Energy Corporation, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Pacific Gas & Electric Company, Psi, Inc., Texas Eastern Transmission Corp., Southwest Gas Corp., Intervenors. Public Utilities Commission of the State of California v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Pacific Gas & Electric Company, Psi, Inc., Southwest Gas Corp., Transwestern Pipeline Company, Intervenors. Kansas Power & Light Company v. Federal Energy Regulatory Commission, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Pacific Gas & Electric Company, Public Utilities Commission of the State of California, Southern California Gas Company, Psi, Inc., Transwestern Pipeline Company, Intervenors
897 F.2d 570 (D.C. Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
470 F.2d 446, 152 U.S. App. D.C. 298, 1972 U.S. App. LEXIS 7036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-valley-municipal-gas-association-v-federal-power-commission-cadc-1972.