Cities of Carlisle & Neola v. Federal Energy Regulatory Commission

741 F.2d 429, 239 U.S. App. D.C. 207, 1984 U.S. App. LEXIS 19677
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 10, 1984
DocketNo. 82-1146
StatusPublished
Cited by9 cases

This text of 741 F.2d 429 (Cities of Carlisle & Neola v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cities of Carlisle & Neola v. Federal Energy Regulatory Commission, 741 F.2d 429, 239 U.S. App. D.C. 207, 1984 U.S. App. LEXIS 19677 (D.C. Cir. 1984).

Opinion

Opinion for the Court filed by Circuit Judge WILKEY. .

WILKEY, Circuit Judge:

Petitioners, the Cities of Carlisle and Neola, Iowa (Cities), seek review of two orders 1 of the Federal Energy Regulatory Commission (FERC) accepting without suspension a rate filing by the Iowa Power and Light Company2 (IP & L). We affirm the Commission’s orders.

I. Facts

Iowa Power and Light submitted proposed rates in two abbreviated filings made on 8 September 1981.3 The Cities petitioned FERC either to reject the filing on the ground that inadequate cost-of-service data had been provided or to suspend the rate filing for five months.4 The Commission then notified IP & L that additional data would be required before the rates could be accepted for filing; Iowa Power and Light provided additional cost-of-service information on 28 October 1981.5 The Cities continued to argue that the rate filing should be rejected or suspended pend[209]*209ing investigation because the information provided was distorted.6

In a letter order the Commission summarily terminated the docket based on only preliminary analysis, and allowed the proposed rates to go into effect without suspension. The failure to suspend was based on a misreading of the record by the Commission. Believing erroneously that the Cities had not specifically challenged the level of the increased rates, the Commission treated the case as a “consent filing” and stated that its acceptance of the filing did not constitute approval of the rate.7

The Cities promptly objected to the Com-' mission’s failure to address their challenge to the reasonableness of the rates. On rehearing the Commission acknowledged that it had overlooked a supplementary pleading filed by the Cities. FERC then found on the basis of the pleadings that the rates were not excessive, and that no hearing need be held because the rates would not be unjust and unreasonable even if the Cities could prove every factual allegation made. Because the Commission found the rates justified, it found that there was no reason to suspend them.8

The Cities appealed FERC’s rulings to this Court. The Cities argued that (1) the decision was not supported by substantial evidence; (2) they were entitled to more than a paper hearing so that they could engage in discovery and develop a record to challenge the reasonableness of the rates; and (3) FERC had not adequately addressed their objections.

In the first hearing of this case this Court believed from the record and from the agency’s statements at oral argument that the agency had acted under § 205 of the Federal Power Act, 16 U.S.C. § 824d (1982), had merely failed to suspend the rate, and thus had not yet issued a final order in the case. The court thus dismissed the case because no reviewable order had been entered by the agency.9

After the prior opinion issued, FERC asserted that it had acted under § 206 of the Act, 16 U.S.C. § 824e (1982), and that its actions were final and reviewable. This case was scheduled for rehearing.

II. Analysis

A. Paper Hearing

In this case the Commission granted no hearing, choosing instead to decide the case on the filings. Petitionérs argue that this was an abuse of discretion. The Commission has broad discretion in deciding whether to grant a hearing, and this court previously has upheld the power of the Commission to dispose of cases on a “paper hearing.” 10 In those cases there was “no need for more than a paper hearing” because the Commission was able to consider fully the issues without recourse to more formal procedures.11

In this case, as in those cases, the Commission had the power to resolve the issues based on only a paper hearing. The Cities had no right to a formal hearing or trial-like procedures. At the same time, however, the Cities were entitled to have their objections considered by the Commission. The issue thus becomes whether the Commission adequately addressed the issues raised by the Cities.

B. Merits

The Federal Power Act provides that “[t]he finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive.” 16 U.S.C. § 825i(b) (1982). The courts must “examine the [210]*210manner in which the Commission has employed the methods of regulation which it has itself selected, and must decide whether each of the order’s essential elements is supported by ' substantial evidence.”12 Agency orders will be sustained where the agency’s path can be discerned.13 In no case may the court “substitute its judgment for that of the agency.”14

While the record in this case is not so well developed as might be desired, neither is it so lacking in specificity that the path taken by the agency cannot be discerned. The agency adequately considered each major objection raised by the Cities, and the Cities have not carried their heavy burden of showing that the agency erred in its determinations.

The Cities raised several cost-of-service issues in their supplement to the motion to reject, and in their application for rehearing. These issues included various efficiencies and savings related to the coming online of the Ottumwa Generating Station (OGS), and possible improvements in the company’s cash flow position and capital requirements due to the Economic Recovery Tax Act of 1981.

In its Order Denying Rehearing, the Commission considered the claims raised by the Cities. It first found that while the Cities had not quantified their objections, the context in which the objections arose made it “highly unlikely” that any adjustments flowing from the Cities’ objections could reduce IP & L’s revenue requirements to the point that the proposed rates would be excessive. The Commission underscored this by observing that the Cities had exaggerated the “potential magnitude of any adjustments” by erroneously asserting that some upward adjustments in revenue had not been taken into account. The Commission carefully assessed the specific claims made by the Cities:

For example, the pro forma increase in plant investment due to the addition of the Ottumwa unit was partially offset by an associated change in accumulated reserve for depreciation. IP & L used a single net adjustment to rate base rather than increasing gross plant and the reserve account separately. Another example is the offset Cities propose through revenues from off-system sales that might be made possible by the availability of an additional 560 MW of generating capacity. Although the net effect of the adjustment was a reduction in sales revenues, increases in off-system sales revenues from certain customers were reflected in the pro forma adjustment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
741 F.2d 429, 239 U.S. App. D.C. 207, 1984 U.S. App. LEXIS 19677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cities-of-carlisle-neola-v-federal-energy-regulatory-commission-cadc-1984.