Delmarva Power & Light Co. v. Federal Energy Regulatory Commission

671 F.2d 587, 217 U.S. App. D.C. 81, 1982 U.S. App. LEXIS 21664
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 19, 1982
DocketNos. 80-2102, 80-2585, 81-1089
StatusPublished
Cited by22 cases

This text of 671 F.2d 587 (Delmarva Power & Light Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delmarva Power & Light Co. v. Federal Energy Regulatory Commission, 671 F.2d 587, 217 U.S. App. D.C. 81, 1982 U.S. App. LEXIS 21664 (D.C. Cir. 1982).

Opinion

Opinion for the Court filed by Circuit Judge WILKEY.

WILKEY, Circuit Judge:

In this action petitioner-intervenor Delmarva Power & Light Company (“Delmarva”) and intervenor-petitioners City of Newark, Town of Smyrna, and Mayor and Council of the City of New Castle, all of Delaware (“the municipalities”), seek review of three orders of respondent Federal Energy Regulatory Commission (“FERC” or “the Commission”). However, we find FERC’s actions here to be nonreviewable, and accordingly dismiss the petitions of Delmarva and the municipalities.

I. BACKGROUND

On 30 April 1980 Delmarva filed a proposed rate increase, which would be implemerited in two phases.1 The Phase I increase was to reflect both Delmarva’s generally higher operating costs due to inflation (this part of the increase is called a new “tariff”), and the capital costs and operating expenses associated with the anticipated opening of Delmarva’s Indian River Unit #4 generating plant. The Phase II increase was to reflect the costs and expenses associated with the opening of the Salem Unit #2 generating plant.2

The three orders issued by FERC in response to Delmarva’s filing were promulgated on 30 June, 22 August, and 1 October 1980, respectively.

The 30 June order3 accepted Delmarva’s rates for filing and suspended the effective dates of the rate increases. The new tariff was suspended for one day, from the proposed effective date of 1 July 1980 to 2 July 1980. The balance of the Phase I rate increase was suspended for three months from the in-service date of Indian River # 4. The Phase II increase was suspended for five months from the in-service date of Salem # 2. The 30 June order also set the entire filing matter for hearing.

The 22 August order4 denied the rehearing Delmarva had requested5 on the 30 June order.

The 1 October order6 denied Delmarva’s motion for a stay of the suspensions,7 which motion Delmarva had filed following the Commission’s 22 August order. However, the 1 October order also modified the 30 June suspensions, leaving the suspension of the Phase II increase in place, but requiring that the Phase I suspension begin running on 1 July for five months rather than for [84]*84three months from the in-serviee date of Indian River # 4.

II. PETITIONERS’ CHALLENGES TO FERC’s ORDERS

Delmarva’s argument against FERC is twofold. First, it challenges as “unreasonable” the 1 October order lengthening the Phase I suspension period since “the rationale for such action is flatly inconsistent with the Commission’s prior Orders . ...”8 Second, it challenges as unlawful “those portions of the Commission’s Orders which suspend Phase II of Delmarva’s new rate filing for longer than the five months maximum established by the Federal Power Act » 9

The municipalities attack the Commission’s 30 June order accepting Delmarva’s rates for filing and, in the alternative, argue that if we decline to require the rejection of Delmarva’s filing, we should set aside the order of 1 October and affirm the two earlier orders. The municipalities challenge Delmarva’s filing — and thus the Commission’s acceptance of the filing — as violative of the Federal Power Act since (1) it did not state plainly the time when the rate increases would go into effect; (2) it sought voluntarily to postpone implementation of a filed rate; and (3) it sought to include in the rate base a utility plant, Salem Unit # 2, which was not yet “used and useful” for service to ratepayers.10

The municipalities’ alternative argument that the 1 October order is “clearly erroneous” and should be set aside is based on two allegations: first, that the Commission based its order on the incorrect assumption that the municipalities were party to agreements with Delmarva reserving to the utility the right to file an early rate increase, and second, that even if they were party to these agreements the Commission misinterpreted them.11

None of Delmarva’s or the municipalities’ challenges, however, renders reviewable the orders issued by FERC.

III. NONREVIEWABILITY OF FERC’s ORDERS

A. Controlling Cases

The framework within which questions of the reviewability or nonreviewability of agency ratemaking and filing acceptance must be analyzed is laid out in Papago Tribal Utility Authority v. FERC12 (“Papa-go"), Aeronautical Radio, Inc. v. FCC13 (“Aeronautical Radio"), Southern Railway Co. v. Seaboard Allied Milling Corp.14 (“Southern Railway”), and Arrow Transportation Co. v. Southern Railway Co.15 (“Arrow Transportation”). Together these four cases, two from this court and two from the Supreme Court, lead ineluctably to our conclusion that the Commission’s orders here are not reviewable.

Most on point is Papago. That case involved, as ours does, a challenge to a Commission decision accepting a rate filing by an electric power wholesaler. Petitioner, a customer of the wholesaler, alleged that the rate filing had “patent defects requiring rejection on its face.” 16 Nonetheless, the court held:

The reviewability of an order must . . . be determined by reference to its practical function and consequences in the rele[85]*85vant statutory scheme. We must ask first whether the order is final; second whether, if unreviewed, it would inflict irreparable injury on the party seeking review; and third whether judicial review at this stage of the administrative process would invade the province reserved to the discretion of the agency.17

The court concluded that acceptance of a rate filing was not final, that petitioner would not suffer irreparable injury in the absence of review, and that review would be an invasion of FERC’s province. The court cited extensively from Arrow Transportation and Southern Railway, and held the Sierra-Mobile doctrine inapplicable.18

In Aeronautical Radio we held that the FCC’s decision to accept a tariff filing from AT&T was similarly nonreviewable. Petitioners there claimed that one of the FCC’s rules required supporting economic data to be filed with proposed tariff changes and that the rule’s waiver by the FCC was an abuse of discretion. However, the court stated:

The decision of the FCC to accept the AT&T tariff filing satisfies the [three-part] Papago criteria of unreviewability. The acceptance is non-final because it is the initiation of an administrative proceeding. The [FCC] merely accepted the tariff and did not rule on the lawfulness of the rates to be paid .... The act of acceptance creates no irreparable harm because investigatory hearings are available for examination of the filing on the merits....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Colorado Springs v. Chao
587 F. Supp. 2d 1185 (D. Colorado, 2008)
Exxon Pipeline Co. v. United States
725 F.2d 1467 (D.C. Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
671 F.2d 587, 217 U.S. App. D.C. 81, 1982 U.S. App. LEXIS 21664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delmarva-power-light-co-v-federal-energy-regulatory-commission-cadc-1982.