Delmarva Power & Light Company v. Federal Energy Regulatory Commission, Cities of Newark and New Castle, Delaware, Intervenors

770 F.2d 1131, 248 U.S. App. D.C. 218, 1985 U.S. App. LEXIS 21250
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 16, 1985
Docket84-1033
StatusPublished
Cited by8 cases

This text of 770 F.2d 1131 (Delmarva Power & Light Company v. Federal Energy Regulatory Commission, Cities of Newark and New Castle, Delaware, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delmarva Power & Light Company v. Federal Energy Regulatory Commission, Cities of Newark and New Castle, Delaware, Intervenors, 770 F.2d 1131, 248 U.S. App. D.C. 218, 1985 U.S. App. LEXIS 21250 (D.C. Cir. 1985).

Opinion

BORK, Circuit Judge:

Delmarva Power & Light Company petitions for review of a decision of the Federal Energy Regulatory Commission refusing to include the annualized costs of a new generating plant in Delmarva’s test period rate base. Our jurisdiction is based on 16 U.S.C. § 825Z (b) (1982).

Delmarva had the burden of establishing that the annualization method it chose resulted in a test-year estimate reasonable when made. The Commission’s Administrative Law Judge (“ALJ”) held that Delmarva had not carried its burden, and the Commission summarily affirmed that aspect of the ALJ’s decision. For the reasons that follow, we conclude that this decision constitutes an unexplained departure from controlling precedent. Accordingly, we vacate and remand to the Commission for explanation of its policy in the matter of selective annualization.

I.

On April 30, 1980, Delmarva filed a revised tariff increasing its wholesale electric rates in two phases. The Phase I rates were in large part intended to take account of a major expansion in Delmarva’s operating plant — the addition of a new generating unit, Indian River No. 4 (“IR4”), which was expected to begin commercial operation on or about September 1, 1980. The Phase II rates were intended to take account of the addition to plant in service of Delmarva’s 7.41% share of Salem Generation Station Unit No. 2, a new nuclear generating facility which was expected to begin commercial operation in late 1980. Only the Phase I increase is at issue in the case.

FERC regulations require that rate filings include information as to the filing utility’s cost of service for two yearly periods. The “Period I” year is the most recent year for which actual data are available. 18 C.F.R. § 35.13(d)(3)(i) (1980). In Delmarva’s case, the Period I data showed Delmarva’s actual cost of service for the year ending September 30, 1979. No dispute over the Period I portion of Delmarva’s filing is before us. This litigation involves only Period II, which the regulation defines as

any period of twelve consecutive months after the end of Period I that begins:

(A) No earlier than nine months before the date on which the rate schedule change is proposed to become effective; and
(B) No later than three months after the date on which the rate schedule change is proposed to become effective.

18 C.F.R. § 35.13(d)(3)(ii) (1980). Because filed rates can become effective only prospectively, the Period II data invariably requires an estimate of cost of service for at least part of the test year selected by the utility. We upheld the validity of this departure from an approach based exclusively on historic costs in American Public Power Association v. FPC, 522 F.2d 142 (D.C.Cir.1975).

*1133 Delmarva proposed to make its Phase I rates effective on July 1, 1980. Joint Appendix (“J.A.”) at 1. Under this proposed effective date, it is clear that Delmarva could have chosen a twelve-month period throughout all or nearly all of which IR4 could be expected to be in service as its Period II test year. 1 Delmarva chose not to do so. Instead, Delmarva selected calendar year 1980 as the test year. In testimony filed before the hearing, Delmarva explained this choice on the grounds that “[s]ince Delmarva develops corporate budgets only for the coming calendar year, the forecasted year 1980 is our best available data upon which to set rates.” Testimony of Mr. Gerritson, Tr. at 1269, J.A. at 274. It is uncontested that Delmarva was free to make this choice of a test year under the regulation.

Normally, when a utility supplies a test period estimate, the utility must be prepared to show that its estimate was “reasonable when made” in the sense that it represented a reasonable forecast of the test period itself. See, e.g., Villages of Chatham v. FERC, 662 F.2d 23, 29-30 (D.C.Cir.1981). In this case, Delmarva knew that the IR4 unit would not be in service for more than four months during calendar year 1980. Had Delmarva followed ordinary practice, it would therefore have calculated the cost of the IR4 unit for 1980 based on the average of thirteen monthly balances, commencing with the month prior to the test period. Use of this method would have meant that only four-thirteenths of IR4’s estimated cost during IR4’s first year of commercial service would have been included in the test period cost of service — because IR4 was expected to be in operation for only four of the thirteen months in question.

Delmarva did not employ the thirteen monthly balance method in preparing its test year estimate, because Delmarva knew that IR4 would almost certainly be in operation during the entire time the proposed rates were in effect. Accordingly, in order to achieve a test year estimate that would more accurately represent cost of service at the time the filed rates were proposed to become effective, Delmarva annualized the cost of IR4 for calendar year 1980. That is, Delmarva assumed that the IR4 facility would be in operation through the test year. Delmarva made this modification to the Period II data in two steps. First, Delmarva removed all IR4-related items from its Period II cost of service. Second, Delmarv'a replaced each removed IR4-related item with the annualized amount for that item.

The intervenors in this case urged that FERC’s regulations and decisions embodied a per se rule against annualization. 2 The intervenors thought this point so clear that they urged FERC to reject Delmarva’s filing on this ground — a sanction reserved for filings that “are grossly defective in form, or ‘so patently a nullity as a matter of substantive law, that administrative efficiency and justice are furthered by obviating any docket at the threshold rather than opening a futile docket.’ ” Papago Tribal Utility Authority v. FERC, 628 F.2d 235, 239 (D.C.Cir.), cert. denied, 449 U.S. 1061, 101 S.Ct. 784, 66 L.Ed.2d 604 (1980) (quoting Municipal Light Boards v. FPC, 450 F.2d 1341, 1346 (D.C.Cir.1971), cert. denied, 405 U.S. 989, 92 S.Ct. 1251, 31 L.Ed.2d 455 (1972)). The Commission disagreed, see Order Accepting for Filing and Suspending Revised Tariff and Proposed Increased Rates, Docket No. ER 80-363 (June 30, 1980) (hereinafter “Order Accepting for Filing”), at 3, J.A. at 18, and, in a *1134

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
770 F.2d 1131, 248 U.S. App. D.C. 218, 1985 U.S. App. LEXIS 21250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delmarva-power-light-company-v-federal-energy-regulatory-commission-cadc-1985.