Indiana & Michigan Electric Company v. Federal Power Commission, Richmond Power and Light of the City of Richmond, Indiana,intervenors

502 F.2d 336, 163 U.S. App. D.C. 334
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 14, 1974
Docket72-2168
StatusPublished
Cited by76 cases

This text of 502 F.2d 336 (Indiana & Michigan Electric Company v. Federal Power Commission, Richmond Power and Light of the City of Richmond, Indiana,intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indiana & Michigan Electric Company v. Federal Power Commission, Richmond Power and Light of the City of Richmond, Indiana,intervenors, 502 F.2d 336, 163 U.S. App. D.C. 334 (D.C. Cir. 1974).

Opinions

WILKEY, Circuit Judge:

Indiana & Michigan Electric Company (hereinafter I&M) filed proposed changes in its tariff schedule with the Federal Power Commission on 13 June 1972. By letter of 3 July 1972, the Secretary of the Commission acknowledged I&M’s filing and advised the company that “[t]he earliest effective date for the increase consistent with [Section 35.13(b) (4) (i)] of the Regulations would be August 13, 1972.”1 This section of the Commission’s regulations2 requires that, whenever a filing calls for a rate increase, certain cost-of-service data and a summary of the proposed rates be filed 60 days prior to the date the rates are to take effect. On 18 July 1972 I&M applied to the Commission for an order making its new rate schedule effective as of 14 July, or 31 days after' the date on which I&M had previously filed. On 11 August 1972 the Commission accepted I&M’s rates for filing but designated 13 August as their effective date; it then suspended their use for five months thereafter, or until 13 January 1973.3 By order dated 6 October 1972 the Commission denied I&M’s application for rehearing.4

[339]*339I&M’s petition for review of the Commission’s order was originally consolidated with petitions by two of I&M’s customers, Richmond Power and Light and Anderson Power and Light. On 25 May 1973 this court held that I&M’s rate filing was unlawful with respect to Richmond and Anderson because it violated the terms of their contracts with I&M.5 However, since the parties here have represented to the court that I&M’s contract with at least one of its other 22 customers 6 7is' different from the Rich: mond and Anderson contracts, I&M’s petition to have the effective date of its new rate schedule retroactively altered to 14 July 1972 remains viable.1

Because the Commission lacked statutory authority to delay the effective date of I&M’s filing until 13 August 1972 and to suspend the new rates until 13 January 1973, we vacate the Commission’s order of 11 August 1972 and remand to the Commission with instructions that I&M’s 13 June rate filing be given effect as of 14 July 1972.8

I. JURISDICTION OF THE COURT TO CONSIDER THE VALIDITY OF THE COMMISSION’S 60-DAY REGULATION

The liminal question here is whether this court can, consistent with section 313(b) of the Federal Power Act, consider I&M’s contention that the Commission’s 60-day prefiling regulation is invalid. Section 313(b) provides, in relevant part: “No objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the application for rehearing unless there is reasonable ground for failure so to do.” 9

While I&M did not expressly raise the legality of the 60-day regulation in its application for rehearing, it did challenge the Commission’s statutory authority to set an effective date 60 days after I&M’s filing.10 The Commission characterized I&M’s position in seeking a rehearing as follows: “I&M asserts that the Commission has no authority to require a notice in excess of the thirty days specified in Section 205(d) of the Federal Power Act.”11 Apparently perceiving I&M’s position as a challenge to the 60-day regulation, the Commission devoted two of the five pages of its order denying rehearing to an attempted justification of the regulation.12 Commissioner Moody joined issue with the majority and attacked the validity of the regulation in his dissent.13 Clearly, then, I&M brought sufficient attention to the issue to stimulate the Commission’s consideration of it.

[340]*340The rationale of the requirement that an aggrieved party exhaust its administrative remedies, as provided by section 313 of the Federal Power Act, is “ ‘that orderly procedure and good administration require that objections to the proceedings of an administrative agency be made while it has an opportunity for correction . . . 14 I&M gave the Commission an opportunity to correct its alleged error in setting the effective date of I&M’s rates. Furthermore, I&M suggested the possibility that the 60-day regulation is invalid by inviting the Commission to construe the regulation in a manner “compatible with the Commission’s statutory authority.”15 The Commission declined to correct its alleged error and explicitly defended the validity of its regulation. Thus, I&M should be permitted to assert the regulation’s invalidity in this court.

II. THE COMMISSION’S 60-DAY PREFILING REGULATION

The Commission delayed the effective date of I&M’s rate filing pursuant to section 35.13(b) (4) (i) of its regulations.16 This section requires that if a proposed rate schedule calls for in-, creased rates, the utility must file with the Commission “a statement showing its cost of the service to be supplied under the new rate schedule,” “a summary statement of [the] proposed increased rate,” and certain material on sales and revenue under the old rates and the proposed rates, all “60 days prior to the date that such changed rate is proposed to become effective.” 17 Much of the data required presupposes the existence of a completed rate schedule. Obviously, a “summary statement of [the] proposed increased rate” cannot be filed unless the thing to be summarized, the rate schedule itself, has been prepared. Included in the cost-of-service items required are “the percentage rate of return claimed,”18 “the maximum demands of the service under the proposed rate schedules,”19 and “revenues under the proposed rates.” 20 Accurate calculation of these items would be difficult, if not impossible, in the absence of a detailed schedule of the proposed rates. Similarly, a detailed schedule is a prerequisite to calculation of “[a] statement comparing sales and services and revenues therefrom . . . under both the rate schedule proposed to be superseded or supplemented and the proposed changed rate schedule.”21 Finally, section 35.13(b) (5) further requires that “the filing utility shall submit with its rate increase filing 60 days prior to the proposed effective date of such increased rates, testimony and exhibits of such composition, scope and format that they would serve as thé company’s case-in-chief in the event the matter is set for hearing.”22 Again, preparation of such information depends upon the existence of the completed rate schedule.

It seems clear, then, that in order to comply with the requirements of section 35.13(b), a utility must be prepared to make a complete filing of its new rate schedule. Thus, the practical effect of the section is to impose a de facto 60-day notice requirement on utilities seeking to increase their rates. Such a requirement contravenes the [341]*341terms of section 205(d) of the Federal Power Act, which provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BEECHWOOD RESTORATIVE CARE CENTER v. Thompson
494 F. Supp. 2d 181 (W.D. New York, 2007)
Centerpoint Energy Entex v. Railroad Commission
208 S.W.3d 608 (Court of Appeals of Texas, 2006)
Bonilla v. United States
653 F. Supp. 749 (District of Columbia, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
502 F.2d 336, 163 U.S. App. D.C. 334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indiana-michigan-electric-company-v-federal-power-commission-richmond-cadc-1974.