Reynolds Metals Company v. Federal Energy Regulatory Commission, (Two Cases)

777 F.2d 760, 250 U.S. App. D.C. 101
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 26, 1985
Docket85-1521, 85-1553
StatusPublished
Cited by16 cases

This text of 777 F.2d 760 (Reynolds Metals Company v. Federal Energy Regulatory Commission, (Two Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds Metals Company v. Federal Energy Regulatory Commission, (Two Cases), 777 F.2d 760, 250 U.S. App. D.C. 101 (D.C. Cir. 1985).

Opinion

SCALIA, Circuit Judge.

Petitioner Reynolds Metals Company, a major industrial customer of Arkansas Power & Light (“AP&L”), alleges that it is threatened with imminent irreparable harm as a result of Opinion No. 234 of the Federal Energy Regulatory Commission (“FERC”), which imposes upon AP&L (and hence upon its ratepayers) a thirty-six percent share of the costs of the Grand Gulf nuclear plant. 31 F.E.R.C. (CCH) 1161,305 (June 13, 1985). Reynolds has placed before us, and we have consolidated here, two petitions seeking to enjoin the present implementation of Opinion No. 234. The confused procedural background of these petitions requires painfully extensive explanation.

Opinion No. 234 was made effective on June 13, 1985, the date of its issuance. On July 3, Reynolds petitioned the Commission for rehearing of the Opinion, and joined with that petition a request for stay of the Opinion or, in the alternative, for inclusion in the Opinion of a refund obligation in the event of reversal on appeal. On August 2, 1985 FERC granted reconsideration of the Opinion, “for the limited purpose of further consideration,” and with the specification that its order “does not ... constitute action, in whole or in part, on the merits of the requests for rehearing.” FERC Docket Nos. ER82-616-000, etc., slip op. at 1 (Aug. 2, 1985) (Order). In the same August 2 order, FERC denied the request for stay and the alternative request for inclusion of a refund obligation in the Opinion.

On August 6, Reynolds petitioned the Commission for rehearing of both these denials. On August 21, it filed the first petition we have before us (Case No. 85-1521), styled an Emergency Petition for Stay under the All Writs Act, but also seeking, in the alternative, judicial imposition of a requirement that Opinion No. 234 contain a refund obligation.

On September 3, while that Emergency Petition was still pending, FERC issued its order denying rehearing of both the re *762 quest for stay and the alternative request for inclusion of a refund obligation in Opinion No. 234. FERC Docket Nos. ER82616-000, etc. (Sept. 3, 1985) (Order). On September 4, Reynolds petitioned this court for review of that order and of the denials in the August 2 order to which it pertained (Case No. 85-1553), and in connection with that appeal filed on September 5 the second request for injunctive action that we have before us, a Motion for Stay Pending Review. It is important to emphasize that the gravamen of Case No. 85-1553 was not Commission Opinion No. 234 (as to which a petition for rehearing was still pending before the Commission) but the Commission’s denial of a stay or refund commitment.

Those portions of both the Emergency Petition (Case No. 85-1521) and the Motion for Stay (Case No. 85-1553) which seek specific relief for the Commission’s refusal (as an alternative to the requested stay) to include a refund obligation in Opinion No. 234 are plainly premature, since at the time they were placed before us that refusal was not yet final. The petition, by Reynolds and others, for reconsideration of Opinion No. 234 had been taken under advisement by the Commission, and until it had been disposed of judicial review of the Opinion was not available. See 16 U.S.C. § 825Z (1982). That statutory limitation upon our powers is not avoidable by the device of petitioning the Commission piecemeal for the inclusion of particular provisions in the Opinion (e.g., a refund obligation) and then — if the Commission is obliging enough to purport to dispose of the provisions piecemeal — seeking immediate review here. The reality of the matter is that at the time Reynolds sought relief Opinion No. 234 was not final and appealable, and that the Commission’s denial of the refund provision was at most a pronouncement that, if and when Opinion No. 234 became final and appealable, that particular feature would not be within it. Besides the purely analytical inappropriateness of the review that Reynolds sought, as a practical matter it would be quite impossible for us to determine the reasonableness of omission of the refund obligation until we could simultaneously examine the final provisions of Opinion No. 234. The fact that Opinion No. 234 has since become final, see FERC Docket Nos. ER82-616-000, etc. (Sept. 26, 1985) (Order denying rehearing), does not retroactively cure the prematurity of these requests for relief. See, e.g., Western Union Telegraph Co. v. FCC, 773 F.2d 375, 378 (D.C.Cir.1985); Industrial Union Department, AFL-CIO v. Bingham, 570 F.2d 965, 968-69 & n. 5 (D.C.Cir.1977).

We turn next to the remaining portion of the Emergency Petition, seeking an injunction against the operative effect of Opinion No. 234. As we recently had occasion to observe, relief under the All Writs Act, 28 U.S.C. § 1651 (1982), is an “extraordinary remedy that may be invoked only if the statutorily prescribed remedy” is “clearly inadequate.” In re GTE Service Corp., 762 F.2d 1024, 1027 (D.C.Cir.1985). And the statutorily prescribed remedy is deemed to include the available interim relief attendant to that remedy, so that an Emergency Petition will not lie where a stay pending appeal (which might be termed the “normal” means of obtaining extraordinary relief) will suffice to prevent the alleged harm. Thus, an All Writs petition filed after the agency order in question is already final and appealable will be summarily dismissed. Id. In the present case, this preliminary condition for All Writs relief was arguably satisfied; since Opinion No. 234 was not yet final, no direct appeal from it yet lay, and a stay pending appeal was not available to prevent irreparable injury that was allegedly occurring.

Besides that preliminary condition distinctive to All Writs relief, however, the Emergency Petition must also satisfy the normal requirements, so to speak, for all extraordinary relief — i.e., the well established requirements that we routinely apply to motions for stay pending appeal, among which is the likelihood of irreparable harm. See Virginia Petroleum Jobbers Association v. FPC, 259 F.2d 921, 925 (D.C.Cir. *763 1958). Here Reynolds alleges “direct, immediate and severe” harm in the form of “huge additional costs” imposed on AP&L (and “ultimately, Reynolds”) which “may not be recouped even if Opinion No. 234 is reversed.” Emergency Petition at 10-11. In essence, Reynolds’ argument is that it is threatened with irreparable harm because Opinion No. 234 contains no commitment to make refunds should the order be set aside on appeal, and because without such a commitment the parties collecting assessments pursuant to the order may be able to claim later that refunds would be inequitable because of their reliance on the overturned opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Facebook, Inc.
District of Columbia, 2023
In re: NTE Connecticut, LLC
26 F.4th 980 (D.C. Circuit, 2022)
TRIAD AT JEFFERSONVILLE I, LLC v. Leavitt
563 F. Supp. 2d 1 (District of Columbia, 2008)
Council Tree Comm v. FCC
Third Circuit, 2007
Virginia Department of Education v. Riley
23 F.3d 80 (Fourth Circuit, 1994)
In Re Committee for Effective Cellular Rules
976 F.2d 45 (D.C. Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
777 F.2d 760, 250 U.S. App. D.C. 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-metals-company-v-federal-energy-regulatory-commission-two-cadc-1985.