Towns of Concord and Wellesley, Massachusetts v. Federal Energy Regulatory Commission, Boston Edison Company, Intervenor

844 F.2d 891
CourtCourt of Appeals for the First Circuit
DecidedMay 4, 1988
Docket87-1247
StatusPublished
Cited by6 cases

This text of 844 F.2d 891 (Towns of Concord and Wellesley, Massachusetts v. Federal Energy Regulatory Commission, Boston Edison Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Towns of Concord and Wellesley, Massachusetts v. Federal Energy Regulatory Commission, Boston Edison Company, Intervenor, 844 F.2d 891 (1st Cir. 1988).

Opinion

JOHN R. BROWN, Senior Circuit Judge:

This case arises from an effort on the part of the Towns of Concord and Welles-ley, Massachusetts (collectively, “the Towns”) to alter the electric power service they received from the Boston Edison Company (Edison). Edison made a new rate filing with the Federal Energy Regulatory Commission (FERC, or “Commission”) on behalf of itself and the Towns, seeking approval for the change in service sought by the Towns. The Towns opposed that filing before FERC. That filing was, after amendment, accepted by FERC over the Towns’ protest, and the Towns then appealed to this court. 1 The Towns contend, as they did before the Commission, that Edison’s filing was invalid (i) because it was deficient under the Commission’s own regulations and because (ii) it violated the terms of an earlier settlement agreement, which the Towns contend was still in force between themselves and Edison. Finally, the Towns contend (iii) that even if the new rate filing was otherwise valid, the waiver of the usual 60-day notice requirement requested by Edison so that the new rate could take effect as of July 1, 1985 was improperly granted. We reject each of these contentions, and affirm the decision of the Commission in all respects.

The 1980 Settlement Agreement Its Formation and Duration

Prior to 1985, the Towns had been purchasing electric power from Edison under “all-requirements service,” meaning that Edison committed itself to supply 100% of the Towns’ electric power needs and the Towns committed themselves to take electric power only from Edison. This preexisting relationship between the Towns and Edison was governed by the Federal Power Act 2 and the regulations of the Commission made under that Act but also by the provisions of an agreement between Edison and the Towns (the “1980 Settlement Agreement”), which they entered into in April, 1980 to resolve “all issues between them in [a set of eight cases then pending before FERC].” Boston Edison Co., 11 FERC 1163,035 (1980). The same agreement also settled as between Edison and the Towns two pending District Court cases and six pending appeals to the First Circuit, all arising from the same transac *893 tions as the eight FERC cases. That Settlement Agreement 3 had been “accepted” 4 by FERC in a letter-order dated June 26, 1980, in Docket No. ER79-216.

Edison mailed a letter 5 to each of the Towns on February 24, 1984, to terminate Article 5.1 of the 1980 Settlement Agreement, as required by the terms of Article 5.1 itself. 6 The Towns made no contemporaneous protest.

Towns’ Purpose to Purchase NYPA Power

Long after termination of the 1980 Settlement Agreement, the Towns sent separate letters to Edison, on June 26 and June 28, 1985. Each town stated that on July 1, 1985, it would no longer purchase all its power requirements from Edison, but rather would purchase a portion of its power requirements from Edison and the remainder from the New York Power Authority (NYPA). 7

Edison’s rate schedules Nos. 47 and 51, then in effect between Edison and the Towns, provided that the rates specified therein were “applicable only to all-requirements service and to partial-requirements service subject to all the conditions set forth in the 1980 Settlement Agreement.” Neither the rate schedules nor the 1980 *894 Settlement Agreement itself established partial-requirements service for the Towns, however. On the contrary, those rate schedules provided that the Towns would “take or pay for ... all of ... [their] requirements of electricity” at the rates specified in those schedules (emphasis added).

The electric power service that Edison provides to the Towns is subject to FERC jurisdiction, 8 and cannot be terminated or revised without FERC approval. 9 In the absence of FERC approval of a change, the all-requirements relationship between Edison and the Towns would have had to be continued without change. Accordingly, on August 22, 1985, acting in response to the Towns’ declared intentions to take NYPA power, Edison sent a letter to FERC 10 which Edison “tender[ed] ... as a filing of an interim rate schedule supplement [and] which it ask[ed] become retroactively effective on July 1, 1985, to authorize the Company to provide the NYPA energy credit to the two Towns.”

On September 11, 1985 the Towns by motion requested FERC to reject the August 22, 1985 filing. The Towns stated that the filing was “patently deficient and should be rejected ... until a full proper filing is made.” Based in part on the Towns’ protest, FERC issued an order on October 17, 1985, rejecting the August 22, 1985 filing. Edison then began compiling from various sources the information and data for the “full proper filing” which the Towns had demanded in their protest to the August 22, 1985 filing.

On June 26, 1986, Edison filed with FERC a second letter, describing and documenting more completely the same set of rate schedule changes it had filed on August 22,1985. Under the scheme for which that filing provided, (i) the Towns would pay to Edison the purchase price of only that power which the Towns actually purchased from Edison itself; (ii) the power the Towns purchased from NYPA would be transmitted to them over Edison’s power lines, for which service the Towns would pay Edison a transmission fee pursuant to a tariff already in existence; and (iii) the Towns would pay slightly more to Edison per unit of power purchased from Edison because of an “adder,” 11 which operated to reflect the fact that the Towns’ share of certain fixed costs Edison passes through to its municipality customers would be spread over fewer units of power purchased from Edison by the Towns. Otherwise, the Towns would pay the same price for their power as before: under both the *895 old and new rate schedules the basic rate per month — consisting of the customer charge, the base demand charge, and the energy charge — remained the same for those services provided under both the old and new schedules. 12

Paradoxically, however, the Towns again by motion requested FERC to reject Edison’s filing. The Towns contended that Edison’s filing was invalid because (i) it was “indistinguishable” from the previous filing which the Commission had found to be deficient under the Commission’s own regulations and because (ii) it violated the terms of the 1980 Settlement Agreement, which the Towns contended was still in force between themselves and Edison.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
844 F.2d 891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/towns-of-concord-and-wellesley-massachusetts-v-federal-energy-regulatory-ca1-1988.