Columbia Gas Transmission Corp. v. Federal Energy Regulatory Commission

895 F.2d 791, 282 U.S. App. D.C. 386, 111 P.U.R.4th 306, 1990 U.S. App. LEXIS 1815
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 9, 1990
DocketNos. 88-1701, 88-1808, 88-1825, 89-1052, 89-1086, 89-1140, 89-1186 and 89-1200
StatusPublished
Cited by2 cases

This text of 895 F.2d 791 (Columbia Gas Transmission Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas Transmission Corp. v. Federal Energy Regulatory Commission, 895 F.2d 791, 282 U.S. App. D.C. 386, 111 P.U.R.4th 306, 1990 U.S. App. LEXIS 1815 (D.C. Cir. 1990).

Opinion

Opinion for the court filed by Circuit Judge BUCKLEY.

BUCKLEY, Circuit Judge:

These consolidated cases concern the assertion, by the Federal Energy Regulatory Commission, of the power to approve a retroactive rate increase through exercise of its authority, under section 4(d) of the Natural Gas Act, to waive the thirty days’ notice required by that section. As we find that the Commission lacks such power, we remand seven of the cases for action consistent with this opinion and dismiss the eighth as moot.

I. Background

A. Regulatory Background

In section 110(a) of the Natural Gas Policy Act of 1978, Congress provided that sellers of natural gas could lawfully recover

any costs of compressing, gathering, processing, treating, liquefying, or transporting such natural gas, or other similar costs, borne by the seller and allowed for, by rule or order, by the Commission.

15 U.S.C. § 3320(a). In July 1980, acting pursuant to this rulemaking authority, the Federal Energy Regulatory Commission (“FERC” or “Commission”) informed gas producers that it intended to allow them, as “first sellers” of natural gas, to pass certain field compression and gathering costs through to their pipeline customers (“first purchasers”). Order No. 94, 45 Fed.Reg. 53,099 (1980) (“Order No. 94”). At the same time, the Commission stated that it would not accept applications for the recovery of these costs until it had completed further rulemaking to establish an appropropriate generic allowance for such costs (“deferred costs”). Id. at 53,107-08. The Commission assured the producers that the new regulations would provide a retroactive mechanism by which they could recover the costs that were determined to be allowable, from the effective date of Order No. 94 until the new regulations took effect. Id. The new rules authorizing their recovery were issued almost three years later, in March 1983. Order No. 94-A, 48 Fed.Reg. 5,152 (1983); Order No. 94-B, 48 Fed.Reg. 5,190 (1983).

Under existing procedures, the first purchaser pipelines could recover these deferred charges from their current customers through the purchased gas adjustment [388]*388clauses (“PGA clauses”) authorized by Commission regulations. 18 C.F.R. §§ 154.301-.310 (1988). These clauses, which must be filed with and approved by the Commission, permit pipelines to recover through prospective sales the estimated production-related costs they will be required to reimburse producers. Rather than pursue this method, however, five pipeline companies petitioned FERC for permission to “direct bill” customers who had purchased gas produced during the 1980-83 period (“second purchasers”) for the deferred costs incurred in its production.

The petitioning pipelines noted that buying patterns in the industry had changed significantly during the three years that had elapsed between the issuance of Order No. 94 and Order No. 94-A. As a consequence, it could not be assumed that the current customers who would have to absorb the newly authorized charges prospectively through PGA clauses were in any way representative of those who, during those three years, had purchased the gas that was subject to the deferred costs. The pipelines argued that considerations of equity required that those who had purchased that gas pay its true cost through a system of direct billing surcharges based on past purchases.

B. Procedural Background

After the Commission approved each of these petitions,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
895 F.2d 791, 282 U.S. App. D.C. 386, 111 P.U.R.4th 306, 1990 U.S. App. LEXIS 1815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-transmission-corp-v-federal-energy-regulatory-commission-cadc-1990.