"Complex" Consolidated Edison Co. of New York, Inc. v. Federal Energy Regulatory Commission

165 F.3d 992, 334 U.S. App. D.C. 205, 1999 U.S. App. LEXIS 2088
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 12, 1999
Docket97-1554, 97-1560, 97-1580 and 97-1590
StatusPublished
Cited by18 cases

This text of 165 F.3d 992 ("Complex" Consolidated Edison Co. of New York, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
"Complex" Consolidated Edison Co. of New York, Inc. v. Federal Energy Regulatory Commission, 165 F.3d 992, 334 U.S. App. D.C. 205, 1999 U.S. App. LEXIS 2088 (D.C. Cir. 1999).

Opinion

Opinion for the Court filed PER CURIAM.

PER CURIAM:

Tennessee Gas Pipeline Company (“Tennessee”) owns and operates a “long-line” interstate natural gas pipeline system running from the Texas gulf coast to New Hampshire. In 1991, Tennessee made a general rate filing pursuant to section 4 of the Natural Gas Act. 15 U.S.C. § 717c (1994). A number of Tennessee’s customers brought challenges. Most issues were resolved at various points in -the ensuing rate proceedings, with the exception of those raised by the petitioners here. Petitioners now seek review of several rulings issued by the Federal Energy Regulatory Commission (“FERC” or the “Commission”). See Tennessee Gas Pipeline Co., 76 F.E.R.C. ¶ 61,022 (1996) (“Opinion 406”) (“Tennessee II”), reh’g denied, Tennessee Gas Pipeline Co., 80 F.E.R.C. ¶ 61,389 (1997) (“Opinion 406-A”) (“Tennessee III”). For the reasons set forth in Parts I, II, and III, we deny each of the petitions for review. 1

Part I: The NET/T-180 Facilities

JMC Power Projects and the New England Power Company (jointly “JMC Power”) petition for review of several FERC rulings, in the relevant portions of which the Commission approved a Tennessee proposal to continue recovering the costs of a series of facility expansions, collectively referred to as the NET/T-180 facilities, on an incremental basis. 2 Petitioners claim that, in accepting the proposed incremental rate treatment, FERC unjustifiably departed from both its own precedent and prior decisions of this court, and unlawfully utilized quantitative measures in assessing the potential costs and benefits of the expansion facilities to preexisting customers. We conclude that Opinions 406 and 406-A clearly clarified the Commission’s historic test for determining the propriety of rolled-in versus incremental pricing of expansion facilities’ costs, and that FERC provided a reasoned explanation for a modest shift from its strictly two-tiered Battle Creek test 3 towards a standard that examines additional relevant factors. Because *996 FERC supplied a sufficient explication for this clarification which, as intended, brought FERC policy into accord with this court’s Natural Gas Act jurisprudence, we deny JMC Power’s petition for review.

A. Background

Between 1988 and 1992, FERC approved the construction of seven separate projects (collectively the “NET/T-180 facilities”) 4 by Tennessee, whose costs were initially to be recovered through incremental pricing. 5 In its 1991 general rate filing pursuant to section 4 of the Natural Gas Act (“NGA”), 15 U.S.C. § 717c, 6 Tennessee proposed to continue the existing incremental pricing of the NET/T-180 facilities. 7 FERC accepted the rate filing subject to refund, and set the matter for evidentiary hearing before an Administrative Law Judge (“ALJ”). Tennessee and its customers later reached an agreement settling most of the contested issues, which FERC then approved on October 29, 1993. See Tennessee Gas Pipeline Co., 65 F.E.R.C. ¶ 61,142. The remaining issues were assigned to the ALJ.

In the ensuing series of evidentiary hearings, JMC Power sought rolled-in treatment for the NET/T-180 facilities by arguing that the facilities were fully integrated into the Tennessee pipeline system and provided various operational and financial benefits to Tennessee and its pre-expansion customers. In particular, its primary witness testified that, in his estimation, the NET/T-180 facilities produced between $28.85 and $79.45 million in total levelized annual benefits 8 to preexisting Tennessee customers, with a mid-case value of $46.53 million. He also asserted that the annual levelized costs of rolled-in treatment would amount to $22.73 million. *997 See Tennessee Gas Pipeline Co., 72 F.E.R.C. ¶ 63,005, at 65,077 (1995) (“Tennessee /”). A number of Tennessee’s preexisting customers challenged these claims, questioning the existence of each alleged benefit, as well as the statistical models upon which JMC Power had assessed their value. According to the ALJ’s initial decision, the weight of the evidence favored the conclusion that the NET/T-180 facilities provided neither operational benefits nor additional reliability to Tennessee’s system customers. In addition, the ALJ found that rolling-in the costs of the NET/T-180 facilities to Tennessee’s general rate base would cause a rate increase for pré-expansion customers in excess of 5%. See id. at 65,084-86. On the basis of these findings, he concluded that both the Battle Creek test and FERC’s Pricing Policy Statement 9 mandated incremental pricing. Accordingly, he approved the Tennessee proposal to continue the existing incremental treatment. See id. at 65,086.

JMC Power filed exceptions to the ALJ’s initial decision with the Commission, alleging that the judge had misinterpreted both FERC and D.C. Circuit precedent, and had misapplied the Battle Creek test in assessing the proper pricing scheme for the NET/T-180 facilities. JMC Power further contended that the ALJ had misconstrued the evidence before him, as the testimony presented (in JMC Power’s view) fully established that the NET/T-180 facilities were both integrated into the Tennessee pipeline and provided significant benefits to pre-existing customers. These alleged benefits included: increased interruptible service; increased peak capacity due to both nonsynchronous demand and the fuel switching capabilities of the primary NET/T-180 customers; avoided facilities costs for future expansions; the encouragement of price competition through increased access to Canadian gas suppliers; fuel savings stemming from the greater efficiency of the new compressors; contribution to Tennessee’s take-or-pay costs through the payment of the volumetric surcharge established by the Cosmic Settlement; 10 potential contributions to stranded investment and new facilities costs; potential contributions to gas supply realignment (“GSR”) costs; and general environmental and national security benefits. Finally, JMC Power claimed that the ALJ had miscalculated the rate impact of rolling-in the contested facilities; according to JMC Power’s calculations, rolled-in treatment would only result in a 4.9% rate increase, below the 5% presumption established in the Pricing Policy Statement. The parties who had presented contrary evidence before the ALJ filed briefs opposing JMC Power’s exceptions.

*998

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BNSF Railway Co. v. Surface Transportation Board
453 F.3d 473 (D.C. Circuit, 2006)
Muni Def Grp v. FERC
170 F.3d 197 (D.C. Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
165 F.3d 992, 334 U.S. App. D.C. 205, 1999 U.S. App. LEXIS 2088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/complex-consolidated-edison-co-of-new-york-inc-v-federal-energy-cadc-1999.