Southern California Edison Co. v. Federal Energy Regulatory Commission

717 F.3d 177, 405 U.S. App. D.C. 118, 2013 WL 1920937, 2013 U.S. App. LEXIS 9488
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 10, 2013
Docket11-1471
StatusPublished
Cited by12 cases

This text of 717 F.3d 177 (Southern California Edison Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern California Edison Co. v. Federal Energy Regulatory Commission, 717 F.3d 177, 405 U.S. App. D.C. 118, 2013 WL 1920937, 2013 U.S. App. LEXIS 9488 (D.C. Cir. 2013).

Opinion

Opinion for the Court by Circuit Judge ROGERS.

ROGERS, Circuit Judge:

Before the court is a challenge to the regulatory mechanism for the recovery by an investor-owned public utility of the cost of three transmission projects in its transmission rates. In 2007, the Federal Energy Regulatory Commission granted various rate incentives to encourage the construction of three projects by the *179 Southern California Edison Company (“SoCal Edison”). The beneficial rate treatment included incentives to be added to a base rate of return for the projects. Later that year, SoCal Edison filed revisions to its transmission tariff, pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, to reflect changes to its transmission revenue requirements and rates, implementing the rate incentives and proposing a base return on equity (“ROE”).

The Commission concluded that SoCal Edison’s base ROE should be set at the median, rather than the midpoint as SoCal Edison proposed, of the range established by a proxy group of publicly-traded companies, and that the ROE for the locked-in period (March 1, 2008 to December 31, 2008, when the rate at issue was in effect) should be updated to reflect the most recently available financial data, based on the average yields on ten-year U.S. Treasury bonds. SoCal Edison challenges the Commission’s use of the median as contrary to FPA § 205, its updating without considering proffered evidence as contrary to 5 U.S.C. § 556(e), and both its use of the median and its updating of the ROE for the locked-in period as arbitrary and capricious. We deny the petition as to the Commission’s methodology for measuring the ROE, and we grant the petition and remand in view of the Commission’s failure to comply with 5 U.S.C. § 556(e) when it updated the ROE with information outside the record.

I.

In order to attract capital investment for construction of transmission facilities, a utility must offer a risk-adjusted expected ROE sufficient to attract investors. See Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 293 (D.C.Cir.2001). To calculate the ROE, the Commission “measures the return enjoyed by the company’s equity investors by the discounted cash flow (‘DCF’) model, which assumes that a stock’s price is equal to the present value of the infinite stream of expected dividends discounted at a market rate commensurate with the stock’s risk.” Id. When a utility is not publicly traded, key values needed to calculate the ROE are missing, and the Commission must resort to more roundabout estimations, including relying on the ROEs of comparable publicly-traded companies, termed a proxy group. See Pub. Serv. Comm’n of Ky. v. FERC, 397 F.3d 1004, 1006-07 (D.C.Cir.2005) (“Midwest ISO ”); Canadian Ass’n, 254 F.3d at 293-94. Adjusting that range by applying screens to exclude unrepresentative high or low rates of return, see Canadian Ass’n, 254 F.3d at 294, the Commission assembles a zone of reasonable ROEs on which to base a utility’s ROE. Pursuant to the Energy Policy Act of 2005, the Commission has also established incentive-based rate treatments to further encourage the construction of transmission facilities and replacement of aging transmission infrastructure. See 16 U.S.C. § 824s; Promoting Transmission Investment Through Pricing Reform, Order No. 679, 71 Fed. Reg. 43,294 (July 20, 2006), order on reh’g, Order No. 679-A, 72 Fed. Reg. 1152 (Dec. 22, 2006), order on reh’g, 119 FERC ¶ 61, 062 (2007).

In November 2007, the Commission approved incentive rate treatment for SoCal Edison’s construction of three transmission projects, including rate adders of 0.75% for the Rancho Vista Project, 1.25% for the Devers-Palo Verde II (“DPV2”) and Tehachapi Projects; 0.50% across the board for joining the California Independent System Operator; and 100% recovery for Construction Work In Progress (“CWIP”) for the projects. S. Cal. Edison Co., Order Granting Petition for Declarato *180 ry Order, 121 FERC ¶ 61,168 (2007) (“Incentives Order”), reh’g denied, 123 FERC ¶ 61,293 (2008). The following month, So-Cal Edison filed revisions to its transmission tariff, pursuant to FPA § 205, to implement the Incentives Order and propose a base ROE of 11.5% for the three transmission projects, which were estimated to have capital expenditures of approximately $2.5 billion, see Incentives Order, 121 FERC at ¶ 61,753. SoCal Edison followed the DCF methodology, screened a national proxy group, and proposed a base ROE of 11.5% by reference to the midpoint (12.07%) of that group. It calculated total ROEs, including incentives, that ranged from 12.75% to 13.25%: 12.75% for the Rancho Vista Project and 13.25% for both the DPV2 and Tehachapi Projects.

The Commission accepted the tariff revisions subject to conditions, preliminarily determined (using a different proxy group and screening criteria than in SoCal Edison’s application) that the zone of reasonableness ranged from 7.97% to 13.67% (putting SoCal Edison’s proposed overall ROEs within the upper end), and ordered a paper hearing to allow all parties to “present evidence to rebut the proposed ROE determination.” S. Cal. Edison Co., Order Accepting Tariff Revisions, Subject to Conditions and Establishing Paper Hearing, 122 FERC ¶ 61,187, ¶ 62,069 (2008). The California Public Utilities Commission sought rehearing and, as relevant, also commented in the Paper Hearing that the Commission should update the ROE based upon changes in the ten-year U.S. Treasury bond rate, as it had done in the past. The California Department of Water Resources commented in part that the Commission should use the median, not the midpoint, in determining the ROE. Six California cities urged, in protests, updating and use of the median. SoCal Edison responded that the midpoint, not the median, was consistent with a long line of Commission precedent for determining the ROE for electric utilities and was appropriate for its base ROE, as well as that Commission hints of a change of policy without explanation were arbitrary and capricious. SoCal Edison, offering expert testimony of Dr. Paul T. Hunt, argued that the midpoint emphasizes the range of the proxy group returns, the median causes distortions because it disregards that range, and the median produces lower ROEs thereby undermining the goal of Congress and the Commission of expanding the transmission grid. It also urged the Commission to use proxy group data as of November 30, 2007 and not to use more recent data or update the ROE based upon the ten-year Treasury bond yields.

The Commission was not persuaded by SoCal Edison’s arguments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
717 F.3d 177, 405 U.S. App. D.C. 118, 2013 WL 1920937, 2013 U.S. App. LEXIS 9488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-california-edison-co-v-federal-energy-regulatory-commission-cadc-2013.