Green Development, LLC v. FERC

77 F.4th 997
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 28, 2023
Docket22-1108
StatusPublished
Cited by1 cases

This text of 77 F.4th 997 (Green Development, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green Development, LLC v. FERC, 77 F.4th 997 (D.C. Cir. 2023).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 20, 2023 Decided July 28, 2023

No. 22-1108

GREEN DEVELOPMENT, LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

NEW ENGLAND POWER COMPANY, D/B/A NATIONAL GRID, INTERVENOR

Consolidated with 22-1161

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Omar Bustami argued the cause for petitioner. With him on the briefs was Anthony P. Campau.

Matthew W.S. Estes, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. 2 MaryAnn T. Almeida argued the cause for respondent- intervenor New England Power Company, d/b/a National Grid. With her on the brief was David M. Gossett.

Before: HENDERSON, PILLARD and KATSAS, Circuit Judges.

Opinion for the Court filed by Circuit Judge HENDERSON.

KAREN LECRAFT HENDERSON, Circuit Judge: Petitioner Green Development, LLC (Green Development) is a developer of solar generation facilities located in Rhode Island. To connect the projects to the electricity grid, Green Development sought interconnection with the distribution system of Narragansett Electric Company (Narragansett), a public utility. Accommodation of the increased flows of electricity required certain upgrades to the transmission system owned by Respondent-Intervenor New England Power Company d/b/a National Grid (NE Power) in order to ensure the continued safe and reliable service of Narragansett’s load.

As the transmission owner, NE Power assigned the costs of the transmission system upgrades directly to Narragansett, the transmission customer, pursuant to the ISO New England Tariff, which governs the provision of transmission service in New England. The newly assigned costs were reflected in a revised transmission service agreement (TSA) that NE Power and Narragansett filed for approval by the Federal Energy Regulatory Commission (Commission or FERC). Green Development protested the revised TSA, objecting to the “direct assignment facility” charge for the upgrades because under a separate, state-jurisdictional interconnection agreement governing the solar projects, Narragansett will pass through to Green Development any costs of the transmission system upgrades paid by Narragansett. The Commission 3 denied Green Development’s protest and concluded that the upgrades’ costs are properly assigned to Narragansett, the sole benefitting transmission customer, rather than spread across all customers as “network upgrades.”

Green Development petitions for review of the relevant FERC orders. Respondent FERC defends the underlying orders as reasonable, as does Intervenor NE Power. As detailed infra, each of Green Development’s four grounds for vacatur lacks merit. Accordingly, we deny the petitions for review.

I. Background

The Federal Power Act (FPA) grants FERC exclusive jurisdiction of the transmission and wholesale sale of electricity in interstate commerce. See 16 U.S.C. § 824(b). To enforce the FPA’s requirements that charges made in connection with the jurisdictional transmission of electric energy be “just and reasonable” and not unduly discriminatory, see id. § 824d(a)– (b), section 205 requires that utilities file tariffs reflecting their rates and service terms with the Commission for review, id. § 824d(c). The Commission has exclusive jurisdiction of transmission facilities but not of distribution facilities. See id. § 824(b)(1). 1

“In order to foster a more competitive, efficient market for electricity,” FERC issued Order No. 888, requiring

1 “FERC has jurisdiction over both the interstate transmission of electricity and the sale of electricity at wholesale in interstate commerce.” Niagara Mohawk Power Corp. v. FERC, 452 F.3d 822, 824 (D.C. Cir. 2006) (citing 16 U.S.C. § 824(b)(1)). “States retain jurisdiction over retail sales of electricity and over local distribution facilities.” Id. “Thus transmission occurs pursuant to FERC- approved tariffs; local distribution occurs under rates set by a state’s public service commission.” Id. 4 transmission providers to “open their networks to transmission customers.” Entergy Servs., Inc. v. FERC, 391 F.3d 1240, 1243 (D.C. Cir. 2004); see Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Services by Public Utilities, 61 Fed. Reg. 21540 (May 10, 1996) (Order No. 888). “To effectuate this introduction of competition, FERC required public utilities to ‘functionally unbundle’ their wholesale generation and transmission services by stating separate rates for each service in a single tariff and offering transmission service under that tariff on an open- access, non-discriminatory basis.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1364 (D.C. Cir. 2004) (citing New York v. FERC, 535 U.S. 1, 11 (2002)). Order No. 888 encouraged the creation of independent service operators (ISOs) to “assume operational control—but not ownership—of the transmission facilities owned by its member utilities” in order to “provide open access to the regional transmission system to all electricity generators at rates established in ‘a single, unbundled, grid-wide tariff that applies to all eligible users in a non-discriminatory manner.’” Id. (quoting Order No. 888, 61 Fed. Reg. at 21596). As relevant here, ISO New England Inc. is the private, non-profit entity authorized by FERC “to administer New England energy markets and operate the region’s bulk power transmission system.” NSTAR Elec. & Gas Corp. v. FERC, 481 F.3d 794, 796 (D.C. Cir. 2007); see generally Emera Me. v. FERC, 854 F.3d 9, 16 (D.C. Cir. 2017). It sets forth its rates for access to the transmission system in the ISO New England Transmission, Markets and Services Tariff (Tariff). ISO New England Inc., 178 FERC ¶ 61,115 at PP 3–4 (2022) (February 2022 Order); see J.A. 192. The Tariff establishes a two-tier transmission arrangement that integrates regional service, provided by ISO New England, with local network service, provided by participating transmission owners (here, NE Power) under its Schedule 21. February 2022 Order, 178 FERC ¶ 61,115 at P 3. 5 “When power generators build new facilities or update their existing facilities, they need to connect those facilities to the power grid. That connection in turn often requires transmission owners to upgrade their power lines to accommodate the power influx.” Am. Clean Power Ass’n v. FERC, 54 F.4th 722, 723–24 (D.C. Cir. 2022) (citing Ameren Servs. Co. v. FERC, 880 F.3d 571, 572 (D.C. Cir. 2018)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tenaska Clear Creek Wind, LLC v. FERC
108 F.4th 858 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
77 F.4th 997, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-development-llc-v-ferc-cadc-2023.