Dynegy Midwest Generation, Inc. v. Federal Energy Regulatory Commission

633 F.3d 1122, 394 U.S. App. D.C. 225, 2011 U.S. App. LEXIS 3183, 2011 WL 476614
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 11, 2011
Docket09-1306, 09-1308
StatusPublished
Cited by10 cases

This text of 633 F.3d 1122 (Dynegy Midwest Generation, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynegy Midwest Generation, Inc. v. Federal Energy Regulatory Commission, 633 F.3d 1122, 394 U.S. App. D.C. 225, 2011 U.S. App. LEXIS 3183, 2011 WL 476614 (D.C. Cir. 2011).

Opinion

Opinion for the court filed by Senior Circuit Judge WILLIAMS.

WILLIAMS, Senior Circuit Judge:

The petitioners own and operate power generation facilities that are part of the Midwest Independent System Operator (“ISO”), a regional transmission organization. The generators supply two kinds of power: (1) “real power” of the sort we are all familiar with and use for running motors, lighting lamps, etc.; and (2) “reactive power,” a support service used to maintain adequate voltages to transmit real power, and to prevent damage such as overheating of generators and motors. See FERC Staff Report, AD05-1-000, Principles for Efficient and Reliable Reactive Power Supply and Consumption 17-20 (2005), available at http://www.ferc.gov/ eventcalendar/files/20050310144430-02-0405-reactive-power.pdf. Inadequacies in reactive power can cause voltage collapse and blackouts. Id. at 20. Real power is sold to regular customers; reactive power is sold to the Midwest ISO and the cost passed on to transmission owners and operators. Midwest ISO Open Access Transmission and Energy Markets Tariff, Schedule 2, III. A & C.

Before the orders in dispute here, generators within the Midwest ISO were compensated for all reactive power with cost-based rates, pursuant to Schedule 2 of the ISO’s tariff. In the challenged orders, FERC accepted a tariff amendment under which any transmission owner could elect an alternative rule of compensation, Schedule 2-A. Under that schedule, the transmission owner would provide no compensation for reactive power produced within a specified range (the so-called “deadband” 1 *1125 ). (Transmission owners electing Schedule 2-A would continue to pay for reactive power outside the deadband, though on a basis somewhat different from that of Schedule 2.) A transmission owner’s election between the two schedules would govern its compensation of all generators in its zone (and, in case of a multi-zone transmission owner, all its zones), affiliated and unaffiliated generators alike.

The petitioners challenge the orders. Them primary contention is that allowance of the Schedule 2-A option was unduly discriminatory, as it would cause generators in different zones to be compensated differently, entirely at the untrammeled choice of each zone’s transmission owners, even though Midwest ISO generators compete with each other across zonal borders. Second, they contend that transmission owners were not authorized to file the new tariff under § 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d. We grant the petitions for review on the first objection but reject the second.

Historically, vertically integrated utilities could recover the costs for providing both real and reactive power through a single rate charged to customers. In 1996, FERC required utilities to functionally unbundle them generation and transmission functions and to provide access to their transmission grid to customers on a nondiscriminatory basis. See Promoting Wholesale Competition Through Open-Access Non-Discriminatory Transmission Services by Public Utilities, Order No. 888, 61 Fed.Reg. 21,540 (May 10, 1996). The Commission ordered public utilities to offer ancillary services necessary for a reliable system (including reactive power supply), required transmission customers to purchase those services, id. at 21,580-82, and ordered that the rates paid to generators for reactive power be cost-based, id. at 21,590.

In two orders issued in 2003 and 2004, the Commission created the opportunity for transmission owners to select among alternative bases of compensation. First it found that, as a general matter, a generator should not be compensated for providing reactive power within a specified range, the deadband, “since it is only meeting its obligation [to do so].” See Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 68 Fed.Reg. 49,846 at 49,891 (P 546) (Aug. 19, 2003) (“Order No. 2003”). But the Commission allowed ISOs and Regional Transmission Organizations to deviate from this principle. Id. at 49,891 (P 548). On rehearing it made clear that if a transmission owner continued to pay its own or affiliated generators for reactive power service, the principle of “comparability” would require it to pay unaffiliated generators similarly. See Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003-A, 69 Fed.Reg. 15,932 at 15,964 (P 416) (Mar. 26, 2004) (“Order No. 2003-A”).

The Midwest ISO is a regional transmission organization to which many of the public utilities in the Midwest transferred operational control over their transmission facilities. Midwest Independent Transmission System Operator, Inc., 97 FERC ¶ 61,326 (2001). It has designated certain transmission pricing zones within its footprint which generally correspond to the boundaries of the transmission facilities of each participating transmission owner. Midwest ISO Transmission Owners, 122 FERC ¶ 61,305, P 1 & n. 4 (2008) (“Initial Order”). Transmission rates in different transmission zones may vary, but for a sale to any purchaser throughout the Midwest ISO, the transmission rate will be simply the price for the purchaser’s zone. Id.; Midwest ISO, 84 FERC ¶ 61,231 at 62,166 (1998) (explaining that the single rate is “based on the costs of the local *1126 service area where the point of delivery is located”).

In October 2007, certain transmission owners in the Midwest ISO proposed a change in the ISO’s tariff that in effect exercised the option they believed had been created by Orders Nos. 2003 and 2003-A. Each transmission owner (or all transmission owners in a zone in the case of such multiple owners) could choose between Schedule 2 (cost-based compensation for all reactive power) and Schedule 2-A (no compensation for reactive power in the deadband, and somewhat different compensation for reactive power outside). Initial Order, P 1. FERC rejected a claim — raised only secondarily before us— that even if transmission owners in each zone compensated all the generators in their zone, affiliated and unaffiliated, on a comparable basis, granting transmission owners the right to choose would violate the comparability requirement developed in Orders Nos. 2003 and 2003-A. Midwest ISO Transmission Owners, 129 FERC ¶ 61,041, P 78 (2009) (“Rehearing Order”). It paid virtually no attention to petitioners’ independent argument that its order allowed undue discrimination in violation of § 205(b) of the FPA, see, e.g., Request for Rehearing of Exelon Corporation at 5-12, treating it as merely a claim that some generators might be economically disadvantaged. See Rehearing Order, PP 91-97.

The petitioners object that comparability and absence of undue discrimination are not synonymous, and urge us to declare FERC’s orders to be in violation of § 205(b)’s antidiscrimination provision, as well as arbitrary and capricious and unsupported by substantial evidence. 5 U.S.C. § 706(2)(A), (E).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
633 F.3d 1122, 394 U.S. App. D.C. 225, 2011 U.S. App. LEXIS 3183, 2011 WL 476614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynegy-midwest-generation-inc-v-federal-energy-regulatory-commission-cadc-2011.