Pseg Energy Resources & Trade v. Ferc

CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 23, 2011
Docket10-1103
StatusPublished

This text of Pseg Energy Resources & Trade v. Ferc (Pseg Energy Resources & Trade v. Ferc) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pseg Energy Resources & Trade v. Ferc, (D.C. Cir. 2011).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 22, 2011 Decided December 23, 2011

No. 10-1103

PSEG ENERGY RESOURCES & TRADE LLC AND PSEG POWER CONNECTICUT LLC, PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

ISO NEW ENGLAND INC., ET AL., INTERVENORS

On Petition for Review of Orders of the Federal Energy Regulatory Commission

John Lee Shepherd, Jr. argued the cause for petitioner. With him on the briefs were Kenneth R. Carretta and Sally Brown Richardson.

Jennifer S. Amerkhail, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief was Robert H. Solomon, Solicitor.

Kerim P. May and Sherry A. Quirk were on the brief for intervenor ISO New England Inc. 2

John S. Wright and Michael C. Wertheimer, Assistant Attorneys General, Office of the Attorney General for the State of Connecticut, and Joseph A. Rosenthal and Randall L. Speck were on the brief for intervenors George C. Jepsen, Attorney General, et al.

Before: GARLAND and KAVANAUGH, Circuit Judges, and WILLIAMS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge GARLAND.

GARLAND, Circuit Judge: In this petition for review, PSEG Energy Resources & Trade LLC and PSEG Power Connecticut LLC (collectively, PSEG) challenge orders of the Federal Energy Regulatory Commission (FERC) accepting the results of an auction for electric generation capacity conducted by ISO New England Inc. In those orders, FERC approved ISO New England’s determination that, unlike other resources in the region, PSEG’s resources in Connecticut could not reduce their capacity supply obligation because doing so would endanger the system’s reliability. Importantly, it also held that ISO New England could reduce the per unit price paid to PSEG for that capacity. Because the latter holding was based on tariff provisions that the Commission thought were clear but now concedes are ambiguous, and because in the course of construing those provisions it failed to respond to PSEG’s facially legitimate objections, we grant the petition and remand the orders for further consideration.

I

PSEG is one of many generators that participate in New England’s “forward capacity market.” In this market, electricity providers purchase from generators options to buy quantities of 3

energy three years in advance. NRG Power Mktg., LLC v. Me. Pub. Utils. Comm’n, 130 S. Ct. 693, 697 (2010). In setting prices, the market eschews the traditional regulatory approach, which sets utility rates based on the cost of production, in favor of an auction. Managing the auction is the responsibility of ISO New England, which is a “‘private, non-profit entity [that] administer[s] New England energy markets and operate[s] the region’s bulk power transmission system.’” Blumenthal v. FERC, 552 F.3d 875, 878 (D.C. Cir. 2009) (quoting NSTAR Elec. & Gas Corp. v. FERC, 481 F.3d 794, 796 (D.C. Cir. 2007)). ISO New England’s tariff implements the market’s auction mechanism, which originated in a FERC-approved settlement among more than 100 stakeholders. See Blumenthal, 552 F.3d at 879; ISO New England Inc., 119 FERC ¶ 61,045, 61,162 (2007).

Under the settlement and tariff, a descending auction sets the price that capacity suppliers like PSEG receive. The basic mechanism is straightforward. After the auctioneer, ISO New England, announces a starting price, suppliers respond with bids for how much capacity they are willing to provide at that price. The auctioneer gradually reduces the price, and suppliers reduce their capacity bids accordingly. The auction ends when the suppliers’ bids just equal the amount of capacity that ISO New England has determined to be necessary to maintain the reliability of the regional system. This amount is known as the “installed capacity requirement,” or ICR. Each supplier is then committed to provide capacity equal to its bid. See Conn. Dep’t of Pub. Util. Control v. FERC, 569 F.3d 477, 480 (D.C. Cir. 2009).

But the forward capacity market has a twist: a price floor that halts the auction if the floor is reached. The problem is that the auction may reach the price floor at a point where the suppliers’ capacity bids still exceed the ICR; hence, absent 4

correction, purchasers would end up buying too much power. The capacity market’s solution is proration. The basic idea is that each supplier has its capacity obligation, and the payment it receives, reduced proportionally. The Proration Rule of ISO New England’s tariff implements this solution in a somewhat roundabout way. See Tariff § III.13.2.7.3(b) (J.A. 178); infra note 1. Although the rule’s full complexity need not detain us, the key mechanism is as follows: the rule calculates the “total payment cap” by multiplying the floor price by the ICR, then proportionately reduces the amount each supplier receives so that the total does not exceed the cap (“price proration”), and then gives each supplier the option to reduce its capacity obligation an equivalent amount (“quantity proration”). For example, if the ICR were 50 units, and two suppliers each bid 30 units at a floor price of $1, the total payment cap would be $50. Each supplier would receive a proportionate amount of $25 (price proration), and each could then reduce its capacity obligation to 25 units (quantity proration).

In 2007, without specific comment, FERC approved ISO New England’s addition of the following caveat as a new last sentence of the Proration Rule: “Any proration shall be subject to reliability review.” Tariff § III.13.2.7.3(b); see ISO New England Inc., 122 FERC ¶ 61,016, 61,049 (2008); see also ISO New England Inc., FERC No. ER07-1388, Various Revisions to FCM Rules, attach. 1 at 1st Rev. Sheet No. 7314Q (Aug. 31, 2007) (J.A. 239). This case is about the meaning of that caveat. In ISO New England’s view, it means that when it determines that a supplier’s resources are needed for local reliability, it can bar quantity proration but force the supplier to accept price proration. Thus, the supplier is effectively required to accept a per unit price lower than the floor price. In the example above, this would require a supplier to provide the full 30 units but still accept only $25, an effective price of $0.83 per unit rather than $1.00. PSEG -- whose attempt to prorate the capacity of its 5

Connecticut resources was barred as a consequence of the reliability review for the 2008 New England auction -- believes that it should receive the full (unprorated) floor price for all its resources that it could not prorate. In the example above that would be $30, which PSEG says cashes out to an extra $2.8 million in this case.1

1 The full Proration Rule, with the reliability caveat italicized, states as follows:

The Capacity Clearing Price shall not fall below 0.6 times CONE [Cost of New Entry]. Where the Capacity Clearing Price reaches 0.6 times CONE, offers shall be prorated such that no more than the Installed Capacity Requirement is procured in the Forward Capacity Auction, as follows: the total payment to all listed capacity resources during the associated Capacity Commitment Period shall be equal to 0.6 times CONE times the Installed Capacity Requirement applicable in the Forward Capacity Auction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Power Commission v. Texaco Inc.
417 U.S. 380 (Supreme Court, 1974)
Transtn Hosp Corp LA v. Shalala, Donna E.
222 F.3d 1019 (D.C. Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Pseg Energy Resources & Trade v. Ferc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pseg-energy-resources-trade-v-ferc-cadc-2011.