PPL Wallingford Energy LLC v. Federal Energy Regulatory Commission

419 F.3d 1194, 368 U.S. App. D.C. 97, 2005 U.S. App. LEXIS 16587, 2005 WL 1868947
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 9, 2005
Docket03-1292, 04-1062
StatusPublished
Cited by60 cases

This text of 419 F.3d 1194 (PPL Wallingford Energy LLC v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PPL Wallingford Energy LLC v. Federal Energy Regulatory Commission, 419 F.3d 1194, 368 U.S. App. D.C. 97, 2005 U.S. App. LEXIS 16587, 2005 WL 1868947 (D.C. Cir. 2005).

Opinion

Opinion for the Court filed by Circuit Judge GARLAND.

GARLAND, Circuit Judge.

This case raises the question of whether FERC’s rejection of a PPL-ISO-NE RMR agreement covering CTs in a NE-POOL DCA violates the APA because FERC ignored PPL’s objections to FERC’s PUSH and LMP assumptions. 1 We conclude that it does. For those not fluent in the language of FERC, a translation follows.

I

Petitioners PPL Wallingford Energy, LLC and PPL EnergyPlus, LLC (collectively, “PPL”) challenge orders of the Federal Energy Regulatory Commission (FERC) that rejected PPL’s agreement with ISO New England, Inc. (ISO-NE) to provide electric power on a eost-of-service basis. PPL also challenges FERC orders rejecting similar agreements between Devon Power, LLC and ISO New England. Because PPL was not a party to the latter agreements, it lacks standing to challenge the orders that relate to them. PPL does have standing to challenge the orders rejecting its own agreement, however, and we conclude that those orders violate the Administrative Procedure Act (APA). We therefore vacate the orders relating to PPL and remand the case to the Commission for further proceedings.

II

The Federal Power Act gives FERC jurisdiction over the transmission and sale of electric energy at wholesale in interstate commerce. See 16 U.S.C. § 824(b)(1). The Act requires public utilities to file schedules with FERC showing, among other things, the rates they will charge for the transmission or sale of energy. Id. § 824d(c). If, after a hearing, FERC “flnd[s] that any rate ... collected by any public utility for any transmission or sale subject to [its] jurisdiction ... is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate ... and shall fix the same by order.” Id. § 824e(a).

ISO New England, Inc. is an “independent system operator” that runs the New England electricity market, known as the New England Power Pool (NEPOOL). See New England Power Pool, 79 F.E.R.C. ¶ 61,374 (1997), order on reh’g, 85 F.E.R.C. ¶ 61,242 (1998). It acts as a middleman, matching bids (offers to sell power) by generators with requests from customers. See New England Power Pool & ISO New England, Inc., 100 F.E.R.C. ¶ 61,287, at 62,261, order on reh’g, 101 F.E.R.C. ¶ 61,344 (2002),- order on reh’g, 103 F.E.R.C. ¶ 61,304, order on reh’g, 105 F.E.R.C. ¶ 61,211 (2003).

In 2002, FERC proposed the creation of “standard market designs” (SMDs) to standardize the sale of electric power, with the goal of creating “ ‘seamless’ wholesale power markets that allow sellers to transact easily across transmission grid boundaries and that allow customers to receive the benefits of lower-cost and more reliable electric supply.” Remedying Undue Discrimination Through Open Access Transmission Service & Standard Electricity Market Design, Notice of Proposed Rulemaking, 100 F.E.R.C. ¶ 61,138, ¶ 9 (2002). In response to FERC’s proposal, ISO New England, along with the NE-POOL Participants Committee, submitted *1196 an SMD for the New England region. FERC approved the SMD, with certain modifications not relevant here. See New England Power Pool, 100 F.E.R.C. ¶ 61,-287.

In “chronically constrained” regions identified as “Designated Congestion Areas” (DCAs), the New England SMD created a complex system of compensation for generators under what was known as Market Rule 1. See id. at 62,262. First, the SMD attempted price reduction — “mitigation” in FERC parlance — by setting a price cap “based on the estimated price to recover the annual cost of a new combustion turbine unit (CT) for the region over the number of hours it is expected to operate during the year.” Devon Power LLC, 103 F.E.R.C. ¶ 61,082, at 61,267 n. 3 (2003). This estimated price was known as the “CT Proxy.” Id. Second, to mitigate the impact of mitigation, under certain circumstances the SMD allowed the highest bid accepted in a particular area to set the price, called the “Locational Marginal Price” (LMP), for all bids accepted in that area. See New England Power Pool, 100 F.E.R.C. ¶ 61,287, at 62,271.

To further soften the impact of mitigation, the SMD also allowed certain seldom-used generator units needed to assure system reliability to “be classified as Reliability-MusNRun (RMR) units.” These are units that “must be run” — i.e., that ISO New England can compel to run — “during certain periods to alleviate transmission congestion.” Id. at 62,262. This designation entitled the generator to apply for an “RMR Cost-of-Service Agreement” if the unit could not recover its costs under the CT Proxy mechanism and would otherwise be shut down. Id. at 62,263. An RMR agreement provides monthly payments to enable the unit to recover its costs plus a reasonable return on investment. See PSEG Power Connecticut, LLC, 110 F.E.R.C. ¶ 61,020, ¶ 30 (2005). In its order upholding the SMD, FERC confirmed that “ISO-NE has the authority to negotiate individual RMR agreements as are required to maintain and/or improve system reliability.” New England Power Pool, 100 F.E.R.C. ¶ 61,287, at 62,268. FERC further stated that “such agreements are to be filed with the Commission in accordance with the Commission’s rules and regulations, and, as such, may be subject to the review of the Commission.” Id.

PPL built a generating station consisting of five natural gas combustion turbines in the southwest Connecticut DCA, from which it began selling power in December 2001. The units were relatively high-cost “peaking” units, intended to run only during times of peak demand or system need. On January 16, 2003, PPL submitted a request for FERC approval of an RMR agreement negotiated with ISO New England to cover four of the five units. While the RMR request was pending, PPL filed an application with ISO New England to temporarily deactivate the four units for economic reasons. The deactivation application was denied, on the ground that the units were necessary for reliability purposes, and PPL was required to continue operating the units regardless of economic considerations. In February 2003, Devon Power, LLC and three affiliated entities (collectively, “Devon”) submitted a similar request for FERC approval of four RMR agreements for their Connecticut units.

FERC ruled on Devon’s RMR request first, denying it in an April-25 order that significantly changed the existing compensation scheme. First, it found that “RMR contracts suppress market-clearing prices, increase uplift payments, and make it difficult for new generators to profitably enter the market,” and that “extensive use of RMR contracts undermines effective market performance.” Devon Power LLC, 103 F.E.R.C. ¶ 61,082, at 61,270 (2003) {Devon *1197 Order). Fearing that it would face a proliferation of RMR agreements, the Commission held that such agreements “should be a last resort.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healthy Gulf v. Haaland
District of Columbia, 2025
Evergreen Shipping Agency (America) Corp. v. FMC
106 F.4th 1113 (D.C. Circuit, 2024)
3M Company and Subsidiaries
U.S. Tax Court, 2023
Gulf Restoration Network v. Debra Haaland
47 F.4th 795 (D.C. Circuit, 2022)
Belmont Municipal Light Department v. FERC
38 F.4th 173 (D.C. Circuit, 2022)
In re: NTE Connecticut, LLC
26 F.4th 980 (D.C. Circuit, 2022)
Cloud v. United States
District of Columbia, 2019
State of Connecticut v. Zinke
District of Columbia, 2019
State v. U.S. Dep't of the Interior
363 F. Supp. 3d 45 (D.C. Circuit, 2019)
Accrediting Council for Indep. Colls. & Sch. v. Devos
303 F. Supp. 3d 77 (D.C. Circuit, 2018)
Butte County, California v. Hogen
197 F. Supp. 3d 82 (District of Columbia, 2016)
Sierra Club v. Jewell
177 F. Supp. 3d 91 (District of Columbia, 2016)
Solvay USA Inc. v. Environmental Protection Agency
608 F. App'x 10 (D.C. Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
419 F.3d 1194, 368 U.S. App. D.C. 97, 2005 U.S. App. LEXIS 16587, 2005 WL 1868947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ppl-wallingford-energy-llc-v-federal-energy-regulatory-commission-cadc-2005.