TNA Merchant Projects, Inc. v. Federal Energy Regulatory Commission

616 F.3d 588, 392 U.S. App. D.C. 407, 2010 U.S. App. LEXIS 16482, 2010 WL 3133537
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 10, 2010
Docket08-1201
StatusPublished
Cited by10 cases

This text of 616 F.3d 588 (TNA Merchant Projects, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TNA Merchant Projects, Inc. v. Federal Energy Regulatory Commission, 616 F.3d 588, 392 U.S. App. D.C. 407, 2010 U.S. App. LEXIS 16482, 2010 WL 3133537 (D.C. Cir. 2010).

Opinion

Opinion for the Court filed by Circuit Judge GARLAND.

GARLAND, Circuit Judge:

Chehalis Power Generating, L.L.C., petitions for review of two orders of the Federal Energy Regulatory Commission (FERC). 1 The orders held that the rate schedule Chehalis proposed for supplying reactive power to the Bonneville Power Administration (BPA) constituted a “changed rate” that was subject to the suspension and refund provisions of § 205(e) of the Federal Power Act (FPA), 16 U.S.C. § 824d(e). Chehalis contends that its proposal was for an “initial rate,” not a “changed rate,” and hence was not subject to suspension or refund. Because the Commission failed to respond to Chehalis’ argument that its rate cannot be classified as “changed” since it was not previously filed, we vacate the Commission’s orders and remand the case.

I

The Chehalis facility is a 520 megawatt electric generating plant located in Chehalis, Washington. The plant is interconnected with the BPA electric transmission *590 system. In February 2005, Chehalis and other independent generators entered into a settlement agreement with BPA laying out a process through which they could seek compensation for supplying BPA with reactive power. 2 Pursuant to the settlement, Chehalis submitted a proposed rate schedule to FERC “set[ting] forth Chehalis’ rates for the provision of Reactive Power Service” to BPA. Rate Schedule at 1 (May 31, 2005) (J.A. 10). The letter accompanying the schedule characterized the submitted rates as “initial rates,” stating: “[T]he subject of the submitted rates is a new service offered by Chehalis in that it has never sought to charge for this service before. In addition, BPA is not an existing customer of Chehalis for any purpose.” Letter from Davis Wright Tremaine LLP to FERC at 6 (May 31, 2005) (J.A. 6).

On July 27, 2005, FERC found that Chehalis’ proposed tariff was not an initial rate schedule. “An initial rate schedule,” the Commission said, “must involve a new customer and a new service.” Chehalis Power Generating, L.P., 112 F.E.R.C. ¶ 61,144, at 61,806 (2005) (hereinafter Suspension Order). “Chehalis,” however, “has been providing reactive power to BPA pursuant to an interconnection agreement, albeit without charge. Thus, the proposed rates for reactive power ... are not initial rates, but are changed rates.” Id. at 61,807. This finding was significant because § 205(e) of the FPA authorizes FERC to suspend changed rates and make them effective subject to refund, but does not permit it to do the same for initial rates. 16 U.S.C. § 824d(e); see Southwestern Elec. Power Co. v. FERC, 810 F.2d 289, 291 (D.C.Cir.1987) (holding that § 205 “empowers the Commission to exercise suspension and refund authority only over filings legitimately characterized as changed rates; as to initial rates, the Commission’s ratemaking powers are purely prospective” (citing Middle South Energy, Inc. v. FERC, 747 F.2d 763, 772 (D.C.Cir.1984))). Exercising its authority under § 205(e), FERC accepted Chehalis’ filing, “suspended] it for a nominal period, to become effective August 1, 2005 ... subject to refund,” and established “hearing and settlement judge procedures.” Suspension Order, 112 F.E.R.C. at 61,807.

On August 26, 2005, Chehalis moved for rehearing, arguing that FERC had wrongly characterized the rate schedule as “changed” rather than “initial.” Req. for Reh’g at 4-6. Of particular pertinence to this appeal, Chehalis argued (among other things) that FERC’s § 205(e) authority extends only to rates described in § 205(d), which, in turn, only encompasses changes to rates described in § 205(c). Id. at 5. And § 205(c), Chehalis contended, only covers rates that have been filed with the Commission. Id. Because Chehalis had not previously filed any rates with FERC for providing reactive power to BPA, it contended that the proposed rates fell outside FERC’s authority under § 205(e).

On December 15, 2005, FERC denied Chehalis’ request for rehearing, Chehalis Power Generating, L.P., 113 F.E.R.C. ¶ 61,259 (2005) (hereinafter Rehearing Order), once again ruling that the proposed rate schedule contained changed rates. Id. at 62,025. Emphasizing the “latitude that the Commission has to interpret what constitutes a changed rate versus what *591 constitutes an initial rate,” FERC held that its “well-settled precedent [established] that an initial rate is one that provides for a new service to a new customer.” Id. Applying this definition, FERC determined that, because “prior to [submitting its proposed rate schedule] ... Chehalis had been providing reactive power to BPA pursuant to its interconnection agreement^] ... it is not now providing a new service nor is it now providing service to a new customer.” Id.

This petition for review followed.

II

We have jurisdiction to review FERC’s orders pursuant to § 313(b) of the FPA. 16 U.S.C. § 825i(b). The orders are subject to reversal if they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); see ExxonMobil Gas Mktg. Co. v. FERC, 297 F.3d 1071, 1083 (D.C.Cir 2002). To the extent Chehalis is challenging FERC’s interpretation of the meaning of FPA § 205(e), we review that interpretation under the familiar two-step framework of Chevron U.S.A. Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984); see ExxonMobil Gas Mktg., 297 F.3d at 1083. Under that framework, “[i]f the intent of Congress is clear, ... [a court] must give effect to the unambiguously expressed intent of Congress.” Chevron, 467 U.S. at 842-43, 104 S.Ct. 2778. But “if the statute is silent or ambiguous with respect to the specific issue,” the court must uphold the agency’s interpretation as long as it is reasonable. Id. at 843, 104 S.Ct. 2778.

Chehalis advances a host of grounds for reversing the Commission’s orders. First, it contends that there is “no evidence in the record as to whether Chehalis had been providing any reactive power prior to filing its rate schedule,” and hence no support for regarding the schedule as anything other than “initial.” Pet’r Br. 20. Second, it argues that, regardless of whether it had previously supplied reactive power to BPA, it had “never before charged or collected one cent of revenue for the provision of reactive power,” and “BPA had never been [its] customer ... for any power service.” Id. at 17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
616 F.3d 588, 392 U.S. App. D.C. 407, 2010 U.S. App. LEXIS 16482, 2010 WL 3133537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tna-merchant-projects-inc-v-federal-energy-regulatory-commission-cadc-2010.