Holy Cross College v. Criswell

CourtCourt of Appeals for the Fifth Circuit
DecidedMay 22, 2024
Docket23-30085
StatusUnpublished

This text of Holy Cross College v. Criswell (Holy Cross College v. Criswell) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holy Cross College v. Criswell, (5th Cir. 2024).

Opinion

Case: 23-30085 Document: 85-1 Page: 1 Date Filed: 05/22/2024

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

____________ FILED May 22, 2024 No. 23-30085 Lyle W. Cayce ____________ Clerk

Holy Cross College, Incorporated, doing business as Holy Cross School,

Plaintiff—Appellant,

versus

Deanne Criswell, in her capacity as Administrator of the Federal Emergency Management Agency; Federal Emergency Management Agency,

Defendants—Appellees. ______________________________

Appeal from the United States District Court for the Eastern District of Louisiana USDC No. 2:21-CV-1658 ______________________________

Before Elrod, Willett, and Duncan, Circuit Judges. Per Curiam: * Following Hurricane Katrina, the Federal Emergency Management Agency (“FEMA”) approved public assistance funding to Holy Cross Col- lege so that it could replace its destroyed campus. FEMA later disallowed, or “deobligated,” some of that funding because, in its view, Holy Cross spent

_____________________ * This opinion is not designated for publication. See 5th Cir. R. 47.5. Case: 23-30085 Document: 85-1 Page: 2 Date Filed: 05/22/2024

No. 23-30085

it on ineligible improvements to its campus and failed to follow federal con- tract-procurement requirements. After it lost two agency appeals, Holy Cross filed suit against FEMA and its administrator, Deanne Criswell, in federal court arguing that the agency acted arbitrarily and capriciously. The district court granted summary judgment for FEMA. Because we agree that Holy Cross is not statutorily protected from deobligation, and because FEMA’s decisions were not arbitrary and capricious, we AFFIRM. I Holy Cross is a 174-year-old private middle and high school for boys in New Orleans, Louisiana. In August 2005, flood waters and high winds from Hurricane Katrina destroyed the school’s historic campus in the Ninth Ward. Because of this damage, Holy Cross was eligible for public-assistance grant funding to replace its facilities under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, 42 U.S.C. §§ 5121–5207. Following the storm, FEMA provided public-assistance grant funding to the State of Louisiana Governor’s Office of Homeland Security and Emergency Preparedness (“GOHSEP”). From this grant, private nonprofits like Holy Cross, state agencies, and local governments were eligible to apply for subgrant funding to rebuild their facilities. Holy Cross submitted applications called project worksheets (“PWs”) to FEMA for funding to replace four of the school’s flood-damaged campus buildings: the High School (PW 12965), Middle School (PW 13237), Central Services Plant (PW 13136), and Administration Building (PW 13333). Holy Cross also constructed a temporary campus, which opened in January 2006. FEMA approved these requests and obligated grant funding based on the estimated cost of the eligible scope of work for the project. This obligated money was to be paid on a reimbursement basis, in which Holy Cross would submit eligible costs for reimbursement. In its approval, FEMA explained

2 Case: 23-30085 Document: 85-1 Page: 3 Date Filed: 05/22/2024

the limitations on the uses of federal funding. In its Central Services Plant approval, for example, FEMA explained that the project qualified for “replacement,” meaning that federal funding would cover the reasonable costs to replace the building to its pre-disaster state. The Central Services Plant was not eligible, however, for improvements beyond what was required to replace the original building, and FEMA explained that any costs associated with improvements to the building would become Holy Cross’s responsibility. FEMA also explained that its approval documents contained only estimates of reasonable costs, and that the final federal share of costs would be determined at the project’s closeout when adjustments would be made for unreasonable costs or costs associated with improvements. In its approval, FEMA also gave Holy Cross permission to rebuild its campus in a new location, the Gentilly neighborhood of New Orleans. Construction began there in 2008. Holy Cross completed construction of the Middle and High School buildings in 2009, the Administration Building in 2010, and the Central Services Plant in 2011. In 2015 at the projects’ closeout, the Department of Homeland Security’s Office of Inspector General completed an audit of Holy Cross’s receipt of $89.3 million in federal funding from FEMA under the Stafford Act. The audit concluded that Holy Cross did not follow federal procurement standards in awarding 21 contracts totaling $82.4 million and recommended that FEMA disallow that money as “ineligible contract costs.” FEMA only partially followed the audit’s recommendation. Instead of disallowing the recommended $82.4 million in federal grant funding, FEMA planned to disallow—or “deobligate,” as it puts it—only $7,998,081. FEMA concluded that Holy Cross spent federal grant funds on ineligible improvements to its campus that went beyond the permissible

3 Case: 23-30085 Document: 85-1 Page: 4 Date Filed: 05/22/2024

replacement costs to rebuild to the building’s pre-Katrina state. FEMA invited Holy Cross to supply additional documentation supporting its claimed costs during final inspection for FEMA to consider and explained that “[s]hould Holy Cross supply adequate supporting documentation, FEMA may reinstate costs accordingly.” Holy Cross appealed this decision to FEMA. During that appeal, FEMA twice requested supporting documentation from Holy Cross and met with representatives from the school on several occasions. Holy Cross sent FEMA a PowerPoint presentation and some of the requested documentation. Ultimately, FEMA granted the first appeal in part, allowing an additional $3 million in reasonable costs, reducing the deobligated amount to $4,829,095.90. Holy Cross again appealed, and FEMA denied the appeal in full. The agency concluded that Holy Cross made improper improvements to its campus and failed to follow federal contract-procurement standards, so it affirmed the approximately $4.8 million deobligation. Holy Cross then filed suit against FEMA and its administrator, Deanne Criswell, under the Administrative Procedure Act seeking an order vacating FEMA’s order and remanding to the agency. Both parties filed cross-motions for summary judgment, and the district court granted Criswell and FEMA’s motion and denied Holy Cross’s. Holy Cross appeals and presses two arguments. First, Holy Cross contends that the Stafford Act protects Holy Cross from deobligation. Second, it argues that FEMA acted arbitrarily and capriciously. II We review a district court’s grant of summary judgment de novo, applying the same standards as the district court. Lexon Ins. Co., Inc. v. Fed.

4 Case: 23-30085 Document: 85-1 Page: 5 Date Filed: 05/22/2024

Deposit Ins. Corp., 7 F.4th 315, 320 (5th Cir. 2021) (citing Spring St. Partners- IV, L.P. v. Lam, 730 F.3d 427, 435 (5th Cir. 2013)). Under the APA, the Court must uphold the agency’s action unless it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). The court’s “task is to determine whether the agency examined the pertinent evidence, considered the relevant factors, and articulated a reasonable explanation for how it reached its decision.” Associated Builders & Contractors of Tex., Inc. v. Nat’l Lab. Rels.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doe 1 v. KPMG LLP
398 F.3d 686 (Fifth Circuit, 2005)
Kornman & Associates, Inc. v. United States
527 F.3d 443 (Fifth Circuit, 2008)
Skidmore v. Swift & Co.
323 U.S. 134 (Supreme Court, 1944)
Brown v. Gardner
513 U.S. 115 (Supreme Court, 1994)
Bates v. United States
522 U.S. 23 (Supreme Court, 1997)
R.P. v. Alamo Heights Independent School District
703 F.3d 801 (Fifth Circuit, 2012)
Trout Point Lodge, Limited v. Doug Handshoe
729 F.3d 481 (Fifth Circuit, 2013)
Spring Street Prt - IV, L.P. v. Douglas Lam
730 F.3d 427 (Fifth Circuit, 2013)
Jose Rodriguez-Avalos v. Eric Holder, Jr.
788 F.3d 444 (Fifth Circuit, 2015)
Department of Commerce v. New York
588 U.S. 752 (Supreme Court, 2019)
Sierra Club v. EPA
939 F.3d 649 (Fifth Circuit, 2019)
Baltimore Gas and Electric Company v. FERC
954 F.3d 279 (D.C. Circuit, 2020)
FCC v. Prometheus Radio Project
592 U.S. 414 (Supreme Court, 2021)
Huawei Tech USA v. FCC
2 F.4th 421 (Fifth Circuit, 2021)
Lexon Ins v. FDIC
7 F.4th 315 (Fifth Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Holy Cross College v. Criswell, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holy-cross-college-v-criswell-ca5-2024.