Connecticut Department of Public Utility Control v. Federal Energy Regulatory Commission

593 F.3d 30, 389 U.S. App. D.C. 178, 2010 U.S. App. LEXIS 1977, 2010 WL 323197
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 29, 2010
Docket08-1199
StatusPublished
Cited by8 cases

This text of 593 F.3d 30 (Connecticut Department of Public Utility Control v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connecticut Department of Public Utility Control v. Federal Energy Regulatory Commission, 593 F.3d 30, 389 U.S. App. D.C. 178, 2010 U.S. App. LEXIS 1977, 2010 WL 323197 (D.C. Cir. 2010).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

*32 WILLIAMS, Senior Circuit Judge:

In calculating the permissible return on equity for ISO New England, Inc., a regional organization of transmission owners, the Federal Energy Regulatory Commission explicitly hiked the rate in order to induce the ISO and its members to proceed swiftly in the completion of certain key transmission projects. It applied the incentive—a 100 basis point bonus in their return on equity—primarily to projects completed by December 31, 2008. Petitioners, mainly state utility regulators in New England, challenge the decision, arguing that the bonus, which presumably will be paid by power consumers in New England, is contrary to applicable precedent, and arbitrary and capricious. We deny the petition.

Hi Hi *

ISO New England, Inc., and owners of various New England transmission facilities, applied on October 31, 2003, to establish a new regional transmission organization (“RTO”) in New England for the purpose of coordinating energy transmission in that area. Shortly after filing the application to establish the RTO, the transmission owners asked FERC to establish the return on equity percentage for transmission investments contemplated in the new RTO’s expansion plan. Specifically, the RTO asked FERC to set a base return on equity, plus an incentive of 50 basis points (0.50%) to induce the utilities to join the RTO, and an additional incentive of 100 basis points (1%). FERC conditionally approved the RTO and the 50 basis point incentive for RTO participation. See ISO New England Inc., 106 FERC ¶ 61,280, 2004 WL 595610 (2004); see also Maine Pub. Utils. Comm’n v. FERC, 454 F.3d 278 (D.C.Cir.2006) (upholding the 50 basis point incentive).

As to the 100 basis point bonus, the Commission ordered a hearing before an administrative law judge, at which the transmission owners would be required to “demonstrate why the [100 basis point] adder is needed to incent investment in new transmission facilities and whether the adder should apply to all types of transmission expansion or be more narrowly focused on ... innovative, less expensive technologies.” ISO New England, 106 FERC ¶ 61,280, at P 249. Petitioners do not dispute the Commission’s conclusion that even with the adder the total rate of return afforded to the transmission owners is within the range of reasonable returns. See Bangor Hydro-Electric Co., 117 FERC ¶ 61,129, at P 19, 2006 WL 3085670 (2006) (“Opinion No. 489”) (calculating a zone of reasonable returns from 7.3% to 13.1%).

At the hearing, the transmission owners introduced expert testimony suggesting that the incentive, applied to the projects at issue before us, would cost customers $148.2 million in present value terms in the form of higher rates, but, by protecting customers from future reliability costs, would yield them benefits worth $76 million for each year by which the incentive accelerated the transmission projects’ completion (putting aside “less easily quantified benefits”). Rebuttal Testimony of Michael M. Schnitzer, J.A. 567-77; see also Bangor Hydro-Electric Co., 111 FERC ¶ 63,048, at PP 160-163, 2005 WL 1256259 (2005). (Petitioners do not attack the expert analysis, though they say it’s largely irrelevant.) Hence, in the transmission owners’ view, the incentive would provide ratepayers an unequivocal net benefit if it accelerated completion of the projects by two years. Nevertheless, another transmission owner expert witness conceded that the projects would be completed even *33 tually whether or not they received an incentive. Id. at P 158.

The ALJ found this evidence inadequate to show a “need” for the adder within the meaning of the Commission’s prior order as she understood it. The evidence cited above, she said, did “not show that the adder will result in building of transmission that would otherwise not be built at all or that the ... projects would [otherwise not] be built in a ‘timely’ manner.” Id. at P 163.

The Commission reversed the ALJ, expressing the view that she had erred in requiring the utilities to show “that ‘but for’ the incentive, the projects at issue will not be built.” Opinion No. 489, 117 FERC ¶ 61,129, at P 104. Instead, the Commission described “the applicable standard [as] whether (i) the proposed incentive falls within the zone of reasonable returns; and (ii) there is some link or nexus between the incentives being requested and the investment being made, i.e., to demonstrate that the incentives are rationally related to the investments being proposed.” Id. at P 105. (We will return to the Commission’s “rationally related” standard, but we should say upfront that the Commission clearly did not mean the equivalent of the famously easy-going “rational basis review” that courts apply under some provisions of the Constitution.) The Commission found that its standard was met since “the proposed incentive will give project owners a significant impetus to push hard for their projects at all phases of the approval process.” Id. at P 109.

On rehearing, the Commission limited the incentive to projects completed by December 31, 2008. Bangor Hydro-Electric Co., 122 FERC ¶ 61,265, at PP 55, 64, 2008 WL 762219 (2008) (“Order on Rehearing”). Transmission owners with projects completed after that date must seek incentives on a case-by-case basis in their rate filings, following a procedure the Commission adopted in response to the Energy Policy Act of 2005, Pub.L. No. 109-58, § 1241, 119 Stat. 594, 961-62 (codified at 16 U.S.C. § 824s). See Order on Rehearing, 122 FERC ¶ 61,265, at P 63; see also Opinion No. 489, 117 FERC ¶ 61,129, at P 113 (noting that the incentive “is consistent with EPAct 2005 and [FERC’s] final rule issued pursuant to EPAct 2005,” i.e., Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057, order on reh’g, 117 FERC ¶ 61,345 (2006)). After the petition for review was filed in this matter, the Commission granted a waiver of the December 31, 2008, cut-off date for certain projects. See, e.g., Bangor Hydro-Electric Co., 124 FERC ¶ 61,136, at P 26, 2008 WL 2965718 (2008); Northeast Utils. Serv. Co., 124 FERC ¶ 61,044, at P 63, 2008 WL 2780585 (2008).

Petitioners launch several attacks on the legal standard that FERC applied. They regard the “rationally related” nexus requirement as attenuated and vague; absent more specific criteria for ascertaining the presence or absence of the required nexus, they contend that the standard is not really a requirement at all. In their view, every transmission owner will be able to satisfy the nexus requirement and thus secure a 100 basis point adder up to the outer limit of the “zone of reasonableness.”

We are sympathetic to petitioners’ concern about the “rationally related” formulation’s facial vagueness. But the Commission’s application of the standard in this case belies the notion that it employed the phrase as a fig leaf for accepting any link, however nominal or trivial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
593 F.3d 30, 389 U.S. App. D.C. 178, 2010 U.S. App. LEXIS 1977, 2010 WL 323197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connecticut-department-of-public-utility-control-v-federal-energy-cadc-2010.