New England Power Generators Ass'n v. Federal Energy Regulatory Commission

707 F.3d 364, 404 U.S. App. D.C. 66, 2013 WL 561490
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 15, 2013
Docket11-1422, 11-1465
StatusPublished
Cited by30 cases

This text of 707 F.3d 364 (New England Power Generators Ass'n v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Power Generators Ass'n v. Federal Energy Regulatory Commission, 707 F.3d 364, 404 U.S. App. D.C. 66, 2013 WL 561490 (D.C. Cir. 2013).

Opinion

*366 BROWN, Circuit Judge:

The Federal Energy Regulatory Commission must ensure the rates charged for electric generation capacity are “just and reasonable.” Federal Power Act (FPA) § 205(a), 16 U.S.C. § 824d(a). Until recently, only two types of rates were involved: tariff rates and contract rates. FERC’s review of tariff rates is subject to considerable discretion. On the other hand, unless a contract rate is contrary to the public interest, FERC must presume it to be just and reasonable under the Mobile-Sierra doctrine, a principle that began with two eponymous Supreme Court precedents: United Gas Pipe Line Co. v. Mobile Gas Serv. Corp. (Mobile), 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956), and Fed. Power Comm’n v. Sierra Pac. Power Co. (Sierra), 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956).

The debut of capacity auctions poses a new challenge. In this case FERC reviewed rates resulting from an auction process and concluded that though the rates are not contract rates, they warrant the Mobile-Sierra presumption anyway — a move that upset two groups of petitioners for opposite reasons. The New England Power Generators Association (“NEPGA”) likes the result but not the reasoning: it argues the auction results, as contract rates, must receive the Mobile-Sierra presumption. Another group, comprising the Maine Public Utilities Commission and the Attorneys General of Massachusetts and Connecticut (collectively, the “State Petitioners”), supports much of FERC’s reasoning but not the result: they contend that because the auction results are not contract rates, FERC cannot presume them just and reasonable. We dismiss NEPGA’s petition for lack of standing and deny the State Petitioners’ petition on the merits.

I

A

Regulated energy suppliers file compilations of their rate schedules, called “tariffs,” with FERC. See Morgan Stanley Capital Grp., Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty., 554 U.S. 527, 531, 128 S.Ct. 2733, 171 L.Ed.2d 607 (2008). Suppliers must abide by these tariffs when providing service to electricity purchasers, though they may change their tariffs if they afford FERC advance notice. See 16 U.S.C. § 824d(c), (d); Morgan Stanley, 554 U.S. at 531, 128 S.Ct. 2733. Along with the unilateral filing of tariffs, the FPA also allows suppliers to set rates with individual purchasers via bilateral contract, though these contracts must also be filed with FERC before going into effect. See Morgan Stanley, 554 U.S. at 531, 128 S.Ct. 2733. All rates, whether determined by tariff or contract, must be “just and reasonable.” 16 U.S.C. § 824d(a). This standard entitles FERC to some discretion, and the agency “traditionally reviewed and set tariff rates under the ‘eost-of-service’ method, which ensures that a seller of electricity recovers its costs plus a rate of return sufficient to attract necessary capital.” Morgan Stanley, 554 U.S. at 532, 128 S.Ct. 2733.

Though bilateral contracts and unilateral tariffs offer separate methods of rate-setting, a seller cannot abrogate a contract rate simply by filing a new tariff with FERC. See Mobile, 350 U.S. at 336-37, 76 S.Ct. 373. Nor may FERC conclude a new tariff supersedes a contract rate just because the latter would not qualify as “just and reasonable” under the cost-of-service method; rather, FERC, pursuant to the Mobile-Sierra doctrine, may only upset such a contractually determined rate when “the rate is so low as to adversely affect the public interest — as *367 where it might impair the financial ability of the public utility to continue its service, cast upon other consumers an excessive burden, or be unduly discriminatory.” Sierra, 350 U.S. at 355, 76 S.Ct. 368; see also Morgan Stanley, 554 U.S. at 533-35, 128 S.Ct. 2733.

B

We adopt the facts as previously summarized in NRG Power Mktg., LLC v. Me. Pub. Utils. Comm’n, 558 U.S. 165, 130 S.Ct. 693, 175 L.Ed.2d 642 (2010), and Me. Pub. Utils. Comm’n v. FERC (“MPUC I"), 520 F.3d 464 (D.C.Cir.2008) (per curiam):

In capacity markets, transmission providers pay generators for the option to buy a quantum of power rather than directly purchasing wholesale electricity. NRG, 130 S.Ct. at 697. As a failsafe, transmission providers typically purchase more capacity than necessary to satisfy expected demand. Id. That way, if a spike in demand occurs, customers will not experience a power interruption.

For some time, the situation in New England proved precarious, with capacity supplies only barely satisfying regional demand. Id. To mitigate this predicament, several generators sought to enter into “reliability must-run” contracts with the New England Independent System Operator (“ISO”). 1 These contracts would allow generators to recover their full cost of service as a means of guaranteeing their continued operation in areas suffering from supply shortages. See Devon Power LLC, 103 FERC ¶ 61,082, 61,266-68 (2003). FERC denied the generators’ request, limiting recovery to certain maintenance costs going forward. Id. at 61,266. FERC also directed the ISO to file a mechanism for setting different prices for separate subre-gions within New England depending on their capacity needs. See id. at 61,271. The ISO response met with some opposition, and FERC instituted proceedings for the parties to negotiate a settlement. See Devon Power LLC, 113 FERC ¶ 61,075, 61,271-72 (2005). A settlement agreement endorsed by all but 8 of the 115 negotiating parties was filed in March 2006, and FERC adopted it. See Devon Power LLC, 115 FERC ¶ 61,340, 62,304, 62,306 (2006).

Central to the settlement agreement is the “Forward Capacity Auction,” at which generators commit themselves to selling a certain amount of capacity at a particular price three years in advance. Id. at 62,-306. The Forward Capacity Auction is a “descending clock auction,” in which the ISO, after announcing a starting price, gradually reduces its offered price until the capacity bids equal the amount the ISO determined is necessary to guarantee grid reliability. See id. at 62,306-07; see also PSEG Energy Res. & Trade LLC v. FERC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michigan Electric Transmission Company, LLC v. FERC
141 F.4th 1296 (D.C. Circuit, 2025)
Natl Infusion Center v. Becerra
116 F.4th 488 (Fifth Circuit, 2024)
American Municipal Power, Inc. v. FERC
86 F.4th 922 (D.C. Circuit, 2023)
LSP Transmission Holdings II, LLC v. FERC
45 F.4th 979 (D.C. Circuit, 2022)
Coalition of MISO Transmission v. FERC
45 F.4th 1004 (D.C. Circuit, 2022)
Wabash Valley Power Association, Inc. v. FERC
45 F.4th 115 (D.C. Circuit, 2022)
Hemp Industries Association v. DEA
36 F.4th 278 (D.C. Circuit, 2022)
Al Seraji v. McAleenan
District of Columbia, 2020
Viola v. Federal Deposit Insurance Corp
District of Columbia, 2019
Cic Servs., LLC v. Internal Revenue Serv.
925 F.3d 247 (Sixth Circuit, 2019)
Georgia v. Pruitt
326 F. Supp. 3d 1356 (S.D. Georgia, 2018)
Lower E. Side People's Fed. Credit Union v. Trump
289 F. Supp. 3d 568 (S.D. Illinois, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
707 F.3d 364, 404 U.S. App. D.C. 66, 2013 WL 561490, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-power-generators-assn-v-federal-energy-regulatory-commission-cadc-2013.