Cng Transmission Corporation v. Federal Energy Regulatory Commission

40 F.3d 1289, 309 U.S. App. D.C. 258, 1994 U.S. App. LEXIS 34340
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 9, 1994
Docket93-1634
StatusPublished
Cited by9 cases

This text of 40 F.3d 1289 (Cng Transmission Corporation v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cng Transmission Corporation v. Federal Energy Regulatory Commission, 40 F.3d 1289, 309 U.S. App. D.C. 258, 1994 U.S. App. LEXIS 34340 (D.C. Cir. 1994).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

CNG Transmission Corporation (“CNG”) petitions for review of an order of the Federal Energy Regulatory Commission (“FERC” or “Commission”) denying CNG’s request to treat a loss of natural gas from its Sabins-ville, Pennsylvania storage facility as a regulatory asset, pending FERC’s decision whether to allow CNG to recover the loss in its rates. We recognize CNG as an aggrieved party for purposes of judicial review under the Natural Gas Act (“NGA”), but deny CNG’s petition for review on the merits.

I. BACKGROUND

CNG Transmission Corp., a wholly-owned subsidiary of Consolidated Natural Gas Company, is an interstate natural gas pipeline company with transmission facilities in West Virginia, Virginia, Maryland, Pennsylvania, Ohio, and New York. One of its assets is the Sabinsville storage facility, an underground natural gas storage field developed from a depleted natural gas reservoir in Tioga County, Pennsylvania. Like other storage fields, the Sabinsville facility normally loses some gas, usually capacity in the course of a year. This normal annual loss is considered an ordinary part of the company’s cost of service, and CNG recovers the value of the lost gas either in its base rates or through separate purchased gas adjustment (“PGA”) charges. In 1991, however, CNG determined that over a 15-year period from 1972 through 1986, it had incurred a loss of 3.3 billion cubic feet (“Bcf’) from its gas reserves at Sabinsville in addition to the expected “normal” loss of 2 Bcf over the same period. On November 1,1991, CNG sought authority from FERC’s Chief Accountant to defer this loss, which it valued at $8,984,255, 1 by recording it as a credit (or “regulatory asset”) in Account No. 182.1 (“Extraordinary property losses”) until FERC could determine in the course of a section 4 rate proceeding whether CNG is entitled to recoup the loss through its future rates.

In a letter order dated January 22, 1992, FERC’s Chief Accountant denied CNG’s application, stating that CNG could treat the loss as a “regulatory asset” only if there were a “reasonable assurance” that the Commission would allow the loss to be recovered in a future rate proceeding. In this case, the Chief Accountant said, “doubt exists as to the ultimate recoverability of these gas losses” because CNG’s failure to identify the losses prior to 1991 despite semi-annual inventories over the 15-year period in which the losses occurred raised questions about the timeliness of CNG’s application and the soundness of its inventory measurement methods and reporting practices. The Chief Accountant specifically questioned CNG’s failure to include any part of this gas loss in its previous requests for rate adjustments when it must have known the loss was occurring, despite FERC regulations requiring that adjustments for gas losses be made in a “timely manner.” The Chief Accountant therefore directed CNG to record the loss in Account No. 823, “Gas losses,” 18 C.F.R. Part 201, Account 823, its standard gas loss account *1292 where the loss is treated as a current expense. The Chief Accountant emphasized, however, that this interim accounting treatment “does not preclude CNG from seeking recovery of these losses in a fixture rate filing.” The Chief Accountant issued this ruling without a formal evidentiary hearing, but after CNG had submitted information supporting its application and responded to FERC staff requests for additional information.

CNG thereupon filed a request for rehearing before the Commission, contending that the Chief Accountant’s order was inconsistent with FERC’s past treatment of similar gas losses; that the order was based on an insufficient evidentiary record; and that the company was entitled to a full evidentiary hearing to explain why it had been unable to detect and report the loss before 1991. On July 22, 1993, the Commission issued an order denying CNG’s request for rehearing, in which the Commission upheld the Chief Accountant’s determination. CNG Transmission Corp., 64 F.E.R.C. ¶ 61,110 (1993). CNG subsequently initiated a rate proceeding pursuant to Section 4 of the NGA, seeking, among other things, a rate adjustment to recoup the gas loss at Sabinsville. CNG now petitions for review of FERC’s July 22, 1993 order.

II. Analysis

This case presents three questions: (1) Is CNG an “aggrieved party” for purposes of judicial review under the Natural Gas Act? (2) Did the Natural Gas Act, FERC’s own regulations, and the Fifth Amendment require FERC to hold a formal evidentiary hearing before determining whether CNG was entitled to its requested accounting treatment? (3) Did FERC act arbitrarily, capriciously, and without adequate support in the record when it denied CNG’s requested accounting treatment?

A. “Aggrieved Party”

As a threshold matter, FERC contends that CNG is not entitled to judicial review because it is not an “aggrieved party” within the meaning of § 19(b) of the Natural Gas Act, which provides that “[a]ny party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain review of such order in the United States Court of Appeals....” 15 U.S.C. § 717r(b) (1988). Judicial review is limited to “orders of definitive impact, where judicial abstention would result in irreparable injury to a party.” Papago Tribal Utility Auth. v. FERC, 628 F.2d 235, 238 (D.C.Cir.), cert. denied, 449 U.S. 1061, 101 S.Ct. 784, 66 L.Ed.2d 604 (1980). “To show aggrievement, a plaintiff must allege facts sufficient to prove the existence of a ‘concrete, perceptible harm of a real, non-speculative nature.’ ” North Carolina Util. Comm. v. FERC, 653 F.2d 655, 662 (D.C.Cir.1981) (quoting Public Citizen v. Lockheed Aircraft Corp., 565 F.2d 708, 716 (D.C.Cir.1977)).

FERC contends that its interim accounting treatment of CNG’s gas loss is “merely a formal bookkeeping requirement” and does not have any immediate effect on CNG’s rates, which will be established in a separate rate proceeding. Respondent’s Brief at 13. CNG replies that whether or not it eventually recoups this loss through its rates, in the meantime it has suffered a “concrete, perceptible harm of a real, non-speculative nature” insofar as it has been forced to take a $7.1 million write-off from its 1993 income, affecting “company value, investor return, and thus, the ability to attract capital,” and “depriving] CNG of earnings that may be necessary to pay dividends, make capital expenditures, and accommodate other unforeseen needs_” Petitioner’s Reply Brief at 2-3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
40 F.3d 1289, 309 U.S. App. D.C. 258, 1994 U.S. App. LEXIS 34340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cng-transmission-corporation-v-federal-energy-regulatory-commission-cadc-1994.