Alabama Power Co. v. Federal Power Commission

128 F.2d 280, 75 U.S. App. D.C. 315, 1942 U.S. App. LEXIS 4731, 1942 WL 75797
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 30, 1942
Docket7853
StatusPublished
Cited by35 cases

This text of 128 F.2d 280 (Alabama Power Co. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alabama Power Co. v. Federal Power Commission, 128 F.2d 280, 75 U.S. App. D.C. 315, 1942 U.S. App. LEXIS 4731, 1942 WL 75797 (D.C. Cir. 1942).

Opinion

MILLER, Associate Justice.

In 1921, the Federal Power Commission issued to the Alabama Power Company a license authorizing the construction of a hydroelectric project on the Coosa River, a navigable stream in the State of Alabama. Upon completion of the project the Company filed with the Commission, in 1930, a cost statement claiming $10,646,-056.76 as the total cost of the project. After audit, hearings, and reconsideration following application for rehearing, the Commission, on December 19, 1932, found the cost to be $7,094,913.69, and ordered the Company to conform its accounts accordingly. In 1933, the Company filed suit in the District Court of the United States for the District of Columbia to enjoin enforcement of the Commission’s orders. Following a trial on the merits, that court dismissed the bill of complaint. On appeal, the United States Court of Appeals reviewed the proceedings and contentions of the parties in extenso; affirmed the Commission’s determinations and orders in part and reversed in .part. By way of summary this court said: “We hold that the trial court correctly sustained the Commission’s allowances for land, taxes and interest, and its refusal to allow the fee of the Dixie Construction Company. But we hold further that the trial court should have directed the Commission to consider the cost of the water right at Lock 15 *283 and to have required the Commission to allow not merely the out-of-pocket, cost of electric energy but the total cost exclusive of profit, and therefore to have required the Commission to determine whether or not the rate of 1.187 per k. w. h. included any element of profit. We further hold that since the case must be returned to the Commission in respect of the foregoing items, it would be proper for the Commission to allow the licensee further opportunity to introduce evidence of the cost of financing, engineering, and promotional services prior to 1913 included in the Power Company’s claimed figure of $3,-500,000. We therefore reverse the decree of the trial court with orders to direct the Federal Power Commission to proceed in accordance with this opinion.” 1

Pursuant to the court’s direction, the Commission, between November 30, 1939 and January 9, 1940, held hearings on the remanded items and fixed the actual legitimate original cost of the project at $7,209,363.99; increasing its earlier determination in the following amounts: “ * * * (1) $51,966.58 as the ‘total cost exclusive of profit’ of electric energy furnished by petitioner to the project during its construction; (2) $66,603.78 as the actual reasonable cost of this project’s portion of the Lock 15 water right; and (3) $26,-540.82 additional interest during construction.” It found that the Company had presented no evidence of the cost of financing, engineering, and promotional services prior to 1913 and made no allowance therefor.

On this appeal, the first question presented for our decision is the cost of the water right at Lock 15. In Alabama Power Co. v. McNinch, 2 we said: “The Commission erred, however, in failing to consider the cost to the licensee of the water right owned by the Wetumpka Power Company at Lock 15, which was down-stream from Duncan’s Riffle. No lands at Lock 15 are involved in the Mitchell Dam project and apparently the Commission for that reason failed to allow the cost of any water rights at Lock 15. The record shows, however, that the Wetumpka Power Company had the right under Alabama law to develop Lock 15 by a dam which would have, impounded water to a height which would have flooded Duncan’s Riffle, the present site of Mitchell Dam proper, to a depth of approximately 14 feet. The Mitchell Dam project therefore was erected in derogation of the water right of the Wetumpka Power Company at Lock 15, at least to this extent. The right of the Wetumpka Power Company passed to the licensee in the merger of 1913. The trial court should have directed the Commission to allow the introduction of evidence as to the cost to the Power Company in 1913 of the right of the Wetumpka Power Company to develop Lock 15 to an extent which would have made the Mitchell Dam project impossible, and to allow such cost as part of the original cost of the project.”

Both parties now agree that the cost of the water right at Lock 15 should be measured by the market value of the securities issued therefor. They disagree as to how that market value should be determined. At the hearing before the Commission, the Company renewed its contentions — which were fully considered and rejected in our earlier opinion — as to the formula which should be used; and urges that we now abandon our earlier decision in favor of those contentions. Consistently with this steadfastly maintained position, the Company introduced evidence to prove the cost of the water right at Lock 15, in terms of values “not as an isolated project, but as part of the more efficient and valuable two dam development [Mitchell Dam and Jordan Dam]. * * * made possible by single ownership of all dam sites * * *.” It insisted that the consideration paid for control of the water right at Lock 15 was in no way identical with the value of such water right when utilized at Mitchell Dam and Jordan Dam “in an economic two high dam development of the entire head in that stretch of the river.” Its expert witness then set up as the “major factors which would determine the value of the water power sites * * * ” reestablished “as of a 1913 point of view * * *” the following: “1. The market and the ability of the market to absorb the power. 2. The number and size of the new hydro plants to be brought in on the system, the available capacity, and the schedule of development of these sites which were already owned by the company. 3. The construction costs which would be incurred in the development of these hydro plants, and the associated op *284 erating and annual carrying costs. 4. The cost of providing this power from the most effective alternative source. In this case that would be from steam plants. Consideration of the costs of power from alternative steam plants necessarily involves the determination of the capital cost of constructing such alternative steam plants, and the annual operating costs taking into consideration, the improvement in efficiency which could have been foreseen in 1913.” His conclusion, as to the cost which should be allocated to Lock IS, is then summarized in petitioner’s brief as follows: “ * * * At this point, the witness exercised his expert judgment and opinion and stated that he would have advised the prospective purchaser that it would not 'be justified in paying more than one-half of the 1913 present worth of the sites, namely, for Mitchell $1,450,000; Jordan $2,300,000; Lock 14— $1,200,000; Lock IS — $750,000; Lock 18— $1,600,000. * * * The witness then used these last figures, representing his judgment or opinion, rather than any arithmetical calculation * * * in determining the value of the water rights at Lock 15 to the extent that the same contributed to the Mitchell Dam project. The excess value of Mitchell over Lock 14, or the value contributed to the Mitchell property by Lock 15, was determined on the basis of these figures to be reasonably worth to a prospective purchaser $250,000.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Beck
526 F. Supp. 2d 1291 (S.D. Florida, 2007)
Anderson v. Eby
998 F.2d 858 (Tenth Circuit, 1993)
Duke Power Company v. Federal Power Commission
401 F.2d 930 (D.C. Circuit, 1968)
State of California v. Federal Power Commission
345 F.2d 917 (Ninth Circuit, 1965)
Bellington v. Township of East Windsor
112 A.2d 268 (Supreme Court of New Jersey, 1955)
New England Telephone & Telegraph Co. v. United States
53 F. Supp. 400 (D. Massachusetts, 1943)
Niagara Falls Power Co. v. Federal Power Commission
137 F.2d 787 (Second Circuit, 1943)
Alabama Power Co. v. Federal Power Commission
134 F.2d 602 (Fifth Circuit, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
128 F.2d 280, 75 U.S. App. D.C. 315, 1942 U.S. App. LEXIS 4731, 1942 WL 75797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alabama-power-co-v-federal-power-commission-cadc-1942.