Louisville Gas & Electric Co. v. Federal Power Commission

129 F.2d 126, 1942 U.S. App. LEXIS 4702
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 29, 1942
Docket8564
StatusPublished
Cited by24 cases

This text of 129 F.2d 126 (Louisville Gas & Electric Co. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisville Gas & Electric Co. v. Federal Power Commission, 129 F.2d 126, 1942 U.S. App. LEXIS 4702 (6th Cir. 1942).

Opinion

SIMONS, Circuit Judge.

The petitioner now considering itself aggrieved by three orders of the respond-. ent, dated respectively October 31, 1933, September 30, 1937, and October 31, 1939, in view of the direction in the last order, petitions this court to annul and set them all aside. Preliminarily, or as an alternative it moves for leave to adduce additional evidence, and impliedly that the controversy be remanded to the Power Commission for the purpose of considering such evidence. The respondent, alleging that the court is without jurisdiction to re *129 view the 1933 and 1937 orders, on the ground that the petitioner did not apply for a rehearing on the second, or seek a court review of either, but, on the contrary, purported to comply, moves to dismiss the petition in respect to the review sought of the first and second orders.

The petitioner is a Kentucky corporation engaged in the electric and gas business in the city of Louisville. In 1925 it acquired, through an affiliate, the Louisville Hydro Electric Company, a license issued by the respondent for Project 289. This project is located in the Ohio River at Louisville, and the Ohio being a navigable stream, construction therein was permissible only under license of the respondent in pursuance of the provisions of the Federal Water Power Act of June 10, 1920, 16 U.S.C.A. § 791 et seq. The Louisville Hydro Electric Company at the time it applied for license, and during construction of the project, was affiliated with the petitioner. Subsequently it was dissolved and the project and license were transferred to the petitioner with the written approval of the Commission and subject to certain conditions, on October 17, 1934. Following completion of the project, Hydro, as required by § 4 of the Act and Article 17 of the license, filed a “verified initial cost statement” in which it claimed $7,829,738.-72 to be its actual legitimate original cost as of November 30, 1929.

The Commission made a detailed audit of all the data in support of the claim, and following a preliminary staff report thereon, and a hearing upon Hydro’s protest before the full Commission, rendered an opinion and entered its first order determining the petitioner’s original cost to be $6,996,093.52, thus disallowing as part of original cost various items totaling $833,645.20 claimed by Hydro, granting it leave, however, to submit additional evidence with respect to some of the disallowed items. The order is that of October 31, 1933, the first of those here sought to be reviewed, and required the licensee to establish and maintain control ledger sheets or accounts with reference to the project, beginning with the entry of the amount found by the Commission as its actual legitimate original cost, and to establish and maintain subsidiary ledger sheets, accounts, or records showing and substantiating all entries in the control account and classifying the total for fixed capital in appropriate detail and in accordance with the Commission’s rules and regulations. The petitioner applied for a rehearing with respect to some of the disallowed items, and it being granted, the Commission entered its second order, that of September 30, 1937, increasing its determination of actual legitimate original cost to $7,218,188.67 and disallowing $611,-550.05 of the amount claimed by the company as cost. The petitioner was again directed to conform its books and accounts accordingly. No application was made for rehearing on this second determination, and.no review was sought of the 1933 order or of its modification by the 1937 order.

The petitioner undertook to comply with the order of September 30, 1937, and on September 12, 1938, advised the Commission that it had, by proper journal entries, and in conformity with its terms, adjusted its books to show the Commission’s determination of actual original cost after transferring a minor item to a non-project account.

On April 4, 1939, the Commission directed the petitioner to show cause why the amount of the disallowed items should not be transferred as a charge against the company’s appropriate surplus account in accordance with its orders of October 31, 1933, and September 30, 1937, and the provisions of the uniform system of accounts prescribed for public utilities and licensees. To this the company made response denying that it had failed to comply with the Commission’s orders, and denying the authority of the Commission to require that the disallowed items be charged to surplus It supported its denial by argument, but neither requested nor suggested further hearing nor indicated that it desired to introduce testimony. On October 31, 1939, the Commission adopted its third order, and finding that no cause had been shown as required, directed the petitioner to write off the sum of $601,937.57 1 against its earned surplus account. The petitioner applied for rehearing on December 4, 1939. This was automatically denied by the Commission’s failure to act thereon for a period of 30 days, under the provisions of § 313(a) of the Act, 16 U.S.C.A. § 825Z(a). The present petition for review to this court followed.

*130 The first question presented relates to the scope of the review and is raised by the Commission’s motion to dismiss the petition insofar as it prays review of the 1933 and 1937 orders. Section 313(a) precludes review of an order of the Commission unless the petitioner has made application for a rehearing, and § 313(b) limits the time of review to the sixty-day period following the entry of an order upon an application for rehearing. The Commission therefore contends that since there was no petition for rehearing filed in respect to the 1937 order, and no timely court review sought of either the 1933 or 1937 orders, we are without jurisdiction to consider them. The petitioner responds that the first two orders of the Commission did not adversely affect it and would not affect it unless and until the determination contained therein was in some way used to its detriment, and that the petitioner therefore was not aggrieved and so had no right to appeal. Asserting that the Commission had jurisdiction to determine the net investment of a licensed project for specific purposes only, and since actual legitimate original cost was but one of the factors to be considered in arriving at net investment, and the time had not arisen when the Commission could use its determination for any purpose, it had, therefore, no objection to complying with the first two orders and entering the amounts specified in them as bookkeeping entries even though it believed that the determinations were erroneous. It construed them as mere findings, directing no determinative action affecting its interests. It was only when the third order was entered which, for the first time, specifically directed the disallowed amounts to be charged to surplus, that the petitioner considered itself aggrieved and so entitled to a court review. It now contends that all questions relative to the Commission’s adjudication of actual legitimate original cost may here be reviewed as well as the authority of the Commission to direct disallowed items to be charged to surplus.

In support of its contention that the first two orders of the Commission were not appealable, it points to the limited statutory purposes of the Commission’s determination of actual legitimate original cost. Section 803(d), 16 U.S.C.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estrin v. Moss
430 S.W.2d 345 (Tennessee Supreme Court, 1968)
United States v. Daniel Wesley Harris
331 F.2d 600 (Sixth Circuit, 1964)
Wilson v. Loew's Inc.
298 P.2d 152 (California Court of Appeal, 1956)
Overfield v. Pennroad Corporation
146 F.2d 889 (Third Circuit, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
129 F.2d 126, 1942 U.S. App. LEXIS 4702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisville-gas-electric-co-v-federal-power-commission-ca6-1942.