Rocky Mountain Power Co. v. Federal Power Commission

409 F.2d 1122
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 16, 1969
DocketNo. 21138
StatusPublished
Cited by1 cases

This text of 409 F.2d 1122 (Rocky Mountain Power Co. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rocky Mountain Power Co. v. Federal Power Commission, 409 F.2d 1122 (D.C. Cir. 1969).

Opinion

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

We have before us a petition to review an order of the Federal Power Commis[1124]*1124sion dismissing an application for authorization to construct and operate hydroelectric facilities. The dismissal stemmed from petitioner's inability, during the more than six years of the application’s pendency, to make a satisfactory showing as to the economic and financial feasibility of its project.

We have carefully reviewed the record and conclude that it does not sustain the claims of error that petitioner advances. These we now discuss in two phases. The first chronicles the panorama of administrative events giving rise to the controversy here. The second explicates the considerations and principles that lead us to affirm the Commission.

I

Petitioner filed an application on January 5, 1961, seeking a license to construct and operate a large hydroelectric project on tributaries of the White and Colorado Rivers in northwestern Colorado for the generation and sale for resale of electric energy.1 2Within a month, after initial review of the application, the Commission advised petitioner that it was insufficiently detailed in several major respects, including a showing as to petitioner’s ability to finance the project and to market its output. The Commission requested specific information and, on March 17, not having received it, again called petitioner’s attention to the deficiencies. A year later, they still remained and on March 30, 1962, the Commission, referring to its earlier communications, warned petitioner of the possible consequences:

The Commission has instructed the staff to clear the docket of inactive applieations, so that if you do not desire to have the application actively processed at this time, it is suggested that you apply for its withdrawal or the staff will recommend that it be dismissed if the balance of the information requested in its aforesaid letters is not received within 60 days.

Petitioner responded on May 4 with materials expanding the project, and stated that an agreement with prospective purchasers was “believed to be imminent.” Requesting additional time, petitioner promised that “ [information concerning such agreement will be furnished promptly, together with information necessary to establish the economic feasibility and proposed financial arrangements for completing the project.” To this request the Commission acceded.

The Commission waited ten months and on March 20, 1963,8 informed petitioner that it must remedy the deficiencies in its application, then two years old, within 90 days or suffer its dismissal.3 On the last day of this grace period, petitioner asked for and received a 60-day extension to August 30. Six days before its expiration, petitioner was granted a 90-day extension on representations that negotiations with potential purchasers had produced “an expressed intention” amounting to “commitments” to purchase power from the project.

Again the Commission waited, this time for over a half-year, and then, on March 19, 1964, inquired as to the negotiations. Receiving no answer, the Commission inquired again on June 23. Petitioner responded by letter on October 22, asking for a conference with the [1125]*1125Commission’s staff. The conference was held, and petitioner wrote on November 13 that “[t]here can be no serious question but that a market for this power exists,” and that “discussions we have had with responsible financial sources convince [petitioner’s president] that as soon as tangible evidence is available that firm contracts for the sale of this power will be concluded, the financing of the project is assured.”

On May 11, 1965, the Commission wrote that it had received no satisfactory reply to its requests for information as to market and financing plans, and that petitioner’s failure to supply it within 30 days would constitute grounds, for rejection of its application. Petitioner, on June 10, asked for a nine-month extension, urging that the public interest would be served by its continuing efforts to secure a market.

The Commission reacted on August 19 by scheduling a hearing nine months hence, for May 23, 1966. The order designating the hearing directed petitioner to file all its testimony and exhibits by March 1, 1966, including

a full and complete statement of a definite plan for the financing of the project, and a full and complete statement of definite plans for the marketing of the electric power to be produced by the project. Failure to comply with this directive will constitute a basis for a motion to dismiss the application for a license for lack of completeness.

On the date of the order, various objectants, public and private, were permitted to intervene.

At a prehearing conference held on April 12, 1966, petitioner admitted that no contracts for the sale of power had been consummated, and that a financing plan could not be developed prior to such consummation. These developments prompted motions by certain intervenors to dismiss petitioner’s application. A Commission order of April 29, however, directing petitioner to resubmit its evidence,4 forestalled action on the motions, and afforded another opportunity for submission of evidence regarding marketing and financing potentials.

At the hearing, and on the basis of petitioner’s resubmission, the Commission’s staff and a number of the intervenors united in motions for dismissal of the application for lack of a definite plan' as to marketing and financing. The hearing examiner found himself unable to “say that the basis for the [August 19th Commission] ruling no longer exists” and so referred the motions to the Commission. On February 16, 1967, on findings that petitioner had not provided sufficient evidence of the project’s financial feasibility or a market for its power output, the Commission, one commissioner dissenting, issued an opinion and order dismissing the application without prejudice to refiling at such time as petitioner could provide all of the required information.5 On a petition for rehearing, the Commission confirmed its action,6 and the matter then came here for review.

II

The parties are seemingly in agreement on several points that deserve brief mention at the outset. Nobody doubts the Commission’s power to require an applicant to submit reasonably adequate information denoting the eco-' nomic and financial feasibility of his hydroelectric project. It is uncontroverted here that petitioner had been unable to effect any binding arrangement for the sale of the power it wishes to produce. [1126]*1126It is also undisputed that petitioner needs outside funding to finance its project. It is clear, too, that such financing depends, among other things, upon petitioner’s ability to first secure firm contracts for the sale of the power. At the same time, it is known that there is a potential demand for electric energy in Nebraska and its surrounding states. These circumstances weigh heavily as we consider petitioner’s conten^ tion that the Commission erred in dismissing its application.7

The chief factual issue dividing petitioner and the Commission related to petitioner’s prospects for securing binding commitments to supply customers in the Nebraska area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
409 F.2d 1122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rocky-mountain-power-co-v-federal-power-commission-cadc-1969.