Rocky Mountain Power Company v. Federal Power Commission

409 F.2d 1122, 133 U.S. App. D.C. 205, 1969 U.S. App. LEXIS 9315
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 16, 1969
Docket21138_1
StatusPublished

This text of 409 F.2d 1122 (Rocky Mountain Power Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rocky Mountain Power Company v. Federal Power Commission, 409 F.2d 1122, 133 U.S. App. D.C. 205, 1969 U.S. App. LEXIS 9315 (D.C. Cir. 1969).

Opinion

409 F.2d 1122

ROCKY MOUNTAIN POWER COMPANY, Petitioner,
v.
FEDERAL POWER COMMISSION, Respondent,
Public Service Company of Colorado, Colorado River Water Conservation District, Humble Oil & Refining Company, Public Utilities Commission of the State of Colorado, Intervenors.

No. 21138.

United States Court of Appeals District of Columbia Circuit.

Argued April 22, 1968.

Decided January 16, 1969.

Mr. Charles F. Brannan, Denver, Colo., with whom Mr. Smith W. Brookhart, Washington, D. C., was on the brief, for petitioner.

Mr. William H. Arkin, Attorney, Federal Power Commission, with whom Messrs. Richard A. Solomon, General Counsel, Peter H. Schiff, Solicitor, and Drexel D. Journey, Assistant General Counsel, Federal Power Commission, were on the brief, for respondent.

Mr. Robert L. McCarty, Washington, D. C., with whom Mr. Kenneth Balcomb, Jr., Glenwood Springs, Colo., was on the brief for intervenor Colorado River Water Conservation District, argued on behalf of all intervenors.

Messrs. Carl Illig, Houston, Tex., Northcutt Ely and C. Emerson Duncan, II, Washington, D. C., were on the brief for intervenor Humble Oil & Refining Company.

Mr. Robert Lee Kessler, Denver, Colo., was on the brief for intervenor Public Utilities Commission of the State of Colorado.

Before BASTIAN, Senior Circuit Judge, and LEVENTHAL and ROBINSON, Circuit Judges.

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

We have before us a petition to review an order of the Federal Power Commission dismissing an application for authorization to construct and operate hydroelectric facilities. The dismissal stemmed from petitioner's inability, during the more than six years of the application's pendency, to make a satisfactory showing as to the economic and financial feasibility of its project.

We have carefully reviewed the record and conclude that it does not sustain the claims of error that petitioner advances. These we now discuss in two phases. The first chronicles the panorama of administrative events giving rise to the controversy here. The second explicates the considerations and principles that lead us to affirm the Commission.

* Petitioner filed an application on January 5, 1961, seeking a license to construct and operate a large hydroelectric project on tributaries of the White and Colorado Rivers in northwestern Colorado for the generation and sale for resale of electric energy.1 Within a month, after initial review of the application, the Commission advised petitioner that it was insufficiently detailed in several major respects, including a showing as to petitioner's ability to finance the project and to market its output. The Commission requested specific information and, on March 17, not having received it, again called petitioner's attention to the deficiencies. A year later, they still remained and on March 30, 1962, the Commission, referring to its earlier communications, warned petitioner of the possible consequences:

The Commission has instructed the staff to clear the docket of inactive applications, so that if you do not desire to have the application actively processed at this time, it is suggested that you apply for its withdrawal or the staff will recommend that it be dismissed if the balance of the information requested in its aforesaid letters is not received within 60 days.

Petitioner responded on May 4 with materials expanding the project, and stated that an agreement with prospective purchasers was "believed to be imminent." Requesting additional time, petitioner promised that "[i]nformation concerning such agreement will be furnished promptly, together with information necessary to establish the economic feasibility and proposed financial arrangements for completing the project." To this request the Commission acceded.

The Commission waited ten months and on March 20, 1963,2 informed petitioner that it must remedy the deficiencies in its application, then two years old, within 90 days or suffer its dismissal.3 On the last day of this grace period, petitioner asked for and received a 60-day extension to August 30. Six days before its expiration, petitioner was granted a 90-day extension on representations that negotiations with potential purchasers had produced "an expressed intention" amounting to "commitments" to purchase power from the project.

Again the Commission waited, this time for over a half-year, and then, on March 19, 1964, inquired as to the negotiations. Receiving no answer, the Commission inquired again on June 23. Petitioner responded by letter on October 22, asking for a conference with the Commission's staff. The conference was held, and petitioner wrote on November 13 that "[t]here can be no serious question but that a market for this power exists," and that "discussions we have had with responsible financial sources convince [petitioner's president] that as soon as tangible evidence is available that firm contracts for the sale of this power will be concluded, the financing of the project is assured."

On May 11, 1965, the Commission wrote that it had received no satisfactory reply to its requests for information as to market and financing plans, and that petitioner's failure to supply it within 30 days would constitute grounds for rejection of its application. Petitioner, on June 10, asked for a nine-month extension, urging that the public interest would be served by its continuing efforts to secure a market.

The Commission reacted on August 19 by scheduling a hearing nine months hence, for May 23, 1966. The order designating the hearing directed petitioner to file all its testimony and exhibits by March 1, 1966, including

a full and complete statement of a definite plan for the financing of the project, and a full and complete statement of definite plans for the marketing of the electric power to be produced by the project. Failure to comply with this directive will constitute a basis for a motion to dismiss the application for a license for lack of completeness.

On the date of the order, various objectants, public and private, were permitted to intervene.

At a prehearing conference held on April 12, 1966, petitioner admitted that no contracts for the sale of power had been consummated, and that a financing plan could not be developed prior to such consummation. These developments prompted motions by certain intervenors to dismiss petitioner's application. A Commission order of April 29, however, directing petitioner to resubmit its evidence,4 forestalled action on the motions, and afforded another opportunity for submission of evidence regarding marketing and financing potentials.

At the hearing, and on the basis of petitioner's resubmission, the Commission's staff and a number of the intervenors united in motions for dismissal of the application for lack of a definite plan as to marketing and financing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanford v. Kepner
344 U.S. 13 (Supreme Court, 1952)
Federal Power Commission v. Idaho Power Co.
344 U.S. 17 (Supreme Court, 1952)
Federal Power Commission v. Oregon
349 U.S. 435 (Supreme Court, 1955)
Udall v. Federal Power Commission
387 U.S. 428 (Supreme Court, 1967)
National Coal Ass'n v. Federal Power Commission
191 F.2d 462 (D.C. Circuit, 1951)
State of Oregon v. Federal Power Commission
211 F.2d 347 (Ninth Circuit, 1954)
City Of Pittsburgh v. Federal Power Commission
237 F.2d 741 (D.C. Circuit, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
409 F.2d 1122, 133 U.S. App. D.C. 205, 1969 U.S. App. LEXIS 9315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rocky-mountain-power-company-v-federal-power-commission-cadc-1969.